Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

PRU.TO ·

JUNE 2023 QUARTER REPORT Perseus exceeds gold production and cost guidance for FY23 and H2 FY23; Cash and bullion increased to US$522M

Corporate Updates

26 JULY 2023

NEWS RELEASE

PERSEUS MINING LIMITED

Level 2, 437 Roberts Road, Subiaco WA 6008

ABN: 27 106 808 986

1

JUNE 2023 QUARTER REPORT

Perseus exceeds gold production and cost guidance for FY23 and H2

FY23; Cash and bullion increased to US$522M

PERTH, Western Australia/ July 26, 2023/Perseus Mining Limited (“Perseus” or the “Company”) (TSX & ASX: PRU) reports

on its activities for the three months’ period ended June 30, 2023 (the “Quarter”).

• Key Operating highlights for the June 2023 quarter, the June 2023 Half Year and the full 2023 Financial Year include:

PERFORMANCE

INDICATOR UNIT MARCH 2023 QUARTER JUNE 2023 QUARTER JUNE 2023 HALF YEAR 2023 FINANCIAL YEAR

Gold recovered Ounces 130,275 136,634 266,909 535,281

Gold poured Ounces 130,512 137,586 268,098 538,642

Production Cost US$/ounce 831 811 820 820

All-In Site Cost (AISC) US$/ounce 971 1,007 989 959

Gold sales Ounces 135,111 140,533 275,644 537,564

Average sales price US$/ounce 1,821 1,933 1,878 1,803

Cash margin US$/ounce 850 926 889 844

Notional Cashflow US$ million 111 127 238 452

– Quarterly gold production of 136,634 ounces at AISC of US$1,007 per ounce and cash margin of US$926 per

ounce.

– Gold production and AISC significantly outperformed market production and cost guidance for June 2023 Half

Year and 2023 Financial Year.

– Quarterly gold sales of 140,533 ounces, up 4% (+5,422 ounces) from the March 2023 quarter.

– Average sale price of gold was US$1,933 per ounce, up 6% (+US$112 per ounce) from the March 2023 quarter.

– Average cash margin of US$926 per ounce of gold sold up 9% (+US$76 per ounce) from the March 2023 quarter.

– Notional cashflow of US$127 million during the quarter, up 14% (+US$16 million) from the March 2023 quarter.

– Group rolling 12-month TRIFR remained stable at 1.20.

• Strong quarterly cashflows further strengthened Perseus’s financial position with available cash and bullion of

US$522 million with zero debt.

• Net cash and bullion balance increased US$51 million from the March 2023 quarter.

• Organic growth activities including Mineral Resource drill outs and feasibility studies at Yaouré’s CMA Underground

Project progressed on schedule. Results due in the September 2023 quarter.

• Perseus’s total economic contribution to its host countries of Ghana, Côte d’Ivoire and Sudan was ~US$158 million

(approximately 58% of revenue) during the quarter.

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

• Pre-development activities at Meyas Sand Gold Project (MSGP) in Sudan suspended due to security concerns, with FID

originally planned for the December 2023 Half Year now deferred.

OPERATIONS

PRODUCTION, COSTS AND NOTIONAL CASHFLOW

Perseus’s three operating gold mines, Yaouré and Sissingué in Côte d’Ivoire, and Edikan in Ghana combined to produce

136,634 ounces of gold in the June 2023 quarter. The weighted average production cost across all three operations was

US$811 per ounce, while the weighted average AISC incurred during the quarter was US$1,007 per ounce of gold.

In the June 2023 quarter, combined gold sales totalled 140,533 ounces. The w eighted average gold price realised was

US$1,933 per ounce, US$112 per ounce more than the March 2023 quarter price of US$1,821 per ounce.

Perseus’s average cash margin for the June 2023 quarter was US$926 per ounce, 9% better than the cash margin achieved

during the March 2023 quarter. Notional operating cashflow from operations was US$127 million, US$16 million more than

the March 2023 quarter, driven by the improved gold price achieved and increased production offset slightly by higher AISC.

These strong results summarised in Tables 1, 2 and 3 below, confirm Perseus’s position as one of the world’s higher

performing mid-tier gold producers in the financial year ending 30 June 2023.

Table 1: Gold Production Summary by Mine

MINE

TOTAL GOLD RECOVERED (OUNCES) TOTAL GOLD POURED (OUNCES)

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Yaouré 64,753 72,367 137,120 273,941 64,512 72,117 136,629 274,971

Edikan 53,720 50,232 103,952 209,929 54,096 51,939 106,035 212,992

Sissingué 11,803 14,035 25,838 51,411 11,904 13,530 25,434 50,679

Group 130,275 136,634 266,909 535,281 130,512 137,586 268,098 538,642

Table 2: Gold Sales by Mine

MINE

TOTAL GOLD SOLD (OUNCES) REALISED GOLD PRICE (US$ PER OUNCE)

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Yaouré 67,578 76,720 144,298 279,471 1,800 1,930 1,869 1,800

Edikan 54,705 51,925 106,630 208,998 1,834 1,924 1,878 1,787

Sissingué 12,828 11,888 24,716 49,095 1,877 1,985 1,929 1,888

Group 135,111 140,533 275,644 537,564 1,821 1,933 1,878 1,803

Table 3: All-In Site Costs (AISC) and Notional Cash Flow by Mine

MINE

ALL-IN SITE COST (US$/OUNCE) NOTIONAL CASHFLOW FROM OPERATIONS (US$ MILLION)

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Yaouré 803 771 786 755 65 84 149 286

Edikan 1,067 1,123 1,094 1,076 41 40 81 149

Sissingué 1,458 1,805 1,647 1569 5 2 7 16

Group 971 1,007 989 959 111 127 238 452

YAOURÉ GOLD MINE, CÔTE D’IVOIRE

Refer to Table 4 below for details of operating and financial parameters recorded at the Yaouré gold mine during the June

2023 quarter and relevant prior periods.

During the quarter, Yaouré produced 72,367 ounces of gold at a production cost of US$603 per ounce and an AISC of US$771

per ounce. The weighted average sales price of the 76,720 ounces of gold sold during the quarter was US$1,930 per ounce,

giving rise to a cash margin of US$1,159 per ounce. Notional operating cashflow generated during the quarter by Yaouré

was US$84 million, or US$19 million more than in the March 2023 quarter.

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

This performance resulted in Yaouré producing 137,120 ounces of gold at an AISC of US$786 per ounce for the June 2023

Half Year and in the process, outperforming market guidance for the period of 117,500 to 130,000 ounces of gold production

at an AISC of US$900 to US$1,000 per ounce.

The strong operating performance at Yaouré reflected an improvement of 12% in head grade of processed ore (2.54 g/t gold

compared to 2.26 g/t gold), but all other operating KPIs were very similar to those recorded in the March 2023 quarter,

including throughput rates (485 tph compared to 491 tph), mill runtime (90% compared to 91%), and gold recovery rates

(identical at 92.4%).

Table 4: Yaouré Quarterly Performance

PARAMETER UNIT DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Gold Production & Sales

Total material mined Tonnes 16,360,821 8,716,713 8,337,953 17,054,666 33,415,487

Total ore mined Tonnes 2,607,389 1,280,134 1,403,455 2,683,589 5,290,978

Average ore grade g/t gold 1.86 1.92 1.72 1.82 1.84

Strip ratio t:t 5.3 5.8 4.9 5.4 5.3

Ore milled Tonnes 1,982,184 962,200 955,355 1,917,555 3,899,739

Milled head grade g/t gold 2.30 2.26 2.54 2.40 2.35

Gold recovery % 93.2 92.4 92.4 92.4 92.8

Gold produced ounces 136,821 64,753 72,367 137,120 273,941

Gold sales1 ounces 135,174 67,578 76,720 144,298 279,471

Average sales price US$/ounce 1,727 1,800 1,930 1,869 1,800

Unit Production Costs

Mining cost US$/t mined 2.92 2.88 2.93 2.91 2.91

Processing cost US$/t milled 12.09 12.67 12.59 12.63 12.35

G & A cost US$M/month 2.19 2.18 2.39 2.28 2.23

All-In Site Cost

Production cost US$/ounce 620 677 603 638 629

Royalties US$/ounce 86 104 102 103 94

Sub-total US$/ounce 706 781 705 741 724

Sustaining capital US$/ounce 18 22 66 45 32

Total All-In Site Cost2 US$/ounce 724 803 771 786 755

Notional Cashflow from Operations

Cash Margin US$/ounce 1,003 998 1,159 1,083 1,045

Notional Cash Flow US$M 137 65 84 149 286

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account

2. Included in the AISC for the June 2023 quarter is US$4 million of costs relating to excess waste stripping. When reporting cost of sales, in line with

accepted practice under IFRS, this cost will be capitalised and the costs amortised over the remainder of the relevant pit life.

MINERAL RESOURCE TO MILL RECONCILIATION

The reconciliation of processed ore tonnes, grade and contained gold relative to the Yaouré Mineral Resource block model

are shown in Table 5. During the June 2023 quarter, Perseus processed 11% more ore tonnes at 7% lower grade for an

overall increase of 3% in ounces compared to the Mineral Resource model. In the previous 6 and 12 months, Yaouré has

produced 4% more metal than the Mineral Resource model predicted. The performance of the Yaouré Mineral Resource

model to date is considered satisfactory.

Table 5: Yaouré Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.11 1.10 1.13

Head Grade 0.93 0.95 0.92

Contained Gold 1.03 1.04 1.04

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

EDIKAN GOLD MINE, GHANA

Table 6 below summarises the key operating and financial parameters recorded at Edikan during the June 2023 quarter and

relevant prior periods.

Edikan produced 50,232 ounces of gold at a production cost of US$903 per ounce and an AISC of US$1,123 per ounce in the

June quarter, slightly down from last quarter’s performance when it produced 53,720 ounces at an AISC of $1,067 per ounce.

Gold sales of 51,925 ounces were 5% less than the prior quarter, at a weighted average realised gold price of US$1,924 per

ounce, generating an average cash margin of US$801 per ounce, which was 4% more than in the prior quarter. However,

due to the lower production, notional cashflow of US$40 million was US$1 million lower than in the prior period.

Edikan continued to perform consistently well in the June 2023 quarter, matching internal expectations. This has resulted in

Edikan exceeding June 2023 Half Year production guidance of 87,500 to 100,000 ounces (103,952 ounces) and achieving

AISC below the bottom end of the cost guidance range of US$1,100 to US$1,200 per ounce (US$1,094 per ounce) for the

period.

Quarter on quarter, production KPIs were relatively steady with processed ore head grade slightly decreased (1.08 g/t gold

compared to 1.09 g/t gold), gold recovery rates marginally increased (92.9% compared to 91.8%), and steady mill runtime

(93% compared to 94%). Throughput rates were down slightly on the prior quarter (768 tph compared to 824 tph) but

remained within acceptable tolerance ranges.

Table 6: Edikan Quarterly Performance

PARAMETER UNIT DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Gold Production & Sales

Total material mined Tonnes 14,018,167 6,693,065 5,247,068 11,940,133 25,958,300

Total ore mined Tonnes 3,347,709 1,888,576 1,696,970 3,585,546 6,933,255

Average ore grade g/t gold 1.05 1.07 1.03 1.05 1.05

Strip ratio t:t 3.19 2.54 2.09 2.33 2.74

Ore milled Tonnes 3,527,865 1,671,960 1,566,231 3,238,191 6,766,056

Milled head grade g/t gold 1.03 1.09 1.08 1.09 1.06

Gold recovery % 90.5 91.8 92.9% 92.3% 91.4%

Gold produced ounces 105,977 53,720 50,232 103,952 209,929

Gold sales1 ounces 102,368 54,705 51,925 106,630 208,998

Average sales price US$/ounce 1,692 1,834 1,924 1,878 1,787

Unit Production Costs

Mining cost US$/t mined 4.14 4.20 4.69 4.42 4.27

Processing cost US$/t milled 9.15 9.87 10.39 10.12 9.62

G & A cost US$M/month 1.55 1.51 1.49 1.50 1.53

All-In Site Cost2

Production cost US$/ounce 940 916 903 910 925

Royalties US$/ounce 107 127 149 137 122

Sub-total US$/ounce 1,047 1,043 1,052 1,047 1,047

Sustaining capital US$/ounce 12 24 71 47 29

Total All-In Site Cost2 US$/ounce 1,059 1,067 1,123 1,094 1,076

Notional Cashflow from Operations1

Cash Margin US$/ounce 633 767 801 784 711

Notional Cash Flow US$M 67 41 40 81 149

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account.

2. Included in the AISC for the June quarter is US$2 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted

practice under IFRS, this cost will be capitalised and the costs amortised over the remainder of the relevant pit life.

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

MINERAL RESOURCE TO MILL RECONCILIATION

Reconciliation of processed ore tonnes, grade and contained ounces relative to the Edikan Mineral Resource block model is

in Table 7 below. During the June 2023 quarter, grade control predicted additional tonnes (+7%), higher grade (+7%) and

more ounces (+14%) when compared to the Mineral Resource Estimate (MRE). Over the past six months, Edikan has also

recorded more contained metal than predicted by the MRE. In addition, over a 12-month period, contained gold was also

more than that predicted by the MRE (8%). Therefore, Perseus regards the overall outperformance of Edikan as being within

normal industry standards.

Table 7: Edikan Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.07 1.06 1.05

Head Grade 1.07 1.04 1.03

Contained Gold 1.14 1.11 1.08

SISSINGUÉ GOLD MINE, CÔTE D’IVOIRE

Table 8 below summarises the key operating and financial parameters recorded at the Sissingué gold mine during the June

2023 quarter and relevant prior periods.

Table 8: Sissingué Quarterly Performance

PARAMETER UNIT DECEMBER 2022

HALF YEAR

MARCH 2023

QUARTER

JUNE 2023

QUARTER

JUNE 2023

HALF YEAR

2023 FINANCIAL

YEAR

Gold Production & Sales

Total material mined Tonnes 3,678,661 2,317,850 1,988,872 4,306,722 7,985,383

Total ore mined Tonnes 516,841 354,784 436,279 791,063 1,307,904

Average ore grade g/t gold 0.73 0.88 1.15 1.03 0.91

Strip ratio t:t 6.1 5.53 3.56 4.44 5.11

Ore milled Tonnes 799,722 468,679 394,727 863,406 1,663,128

Milled head grade g/t gold 1.09 0.85 1.19 1.01 1.05

Gold recovery % 91.5 91.6 93.0% 92.4% 91.9%

Gold produced ounces 25,573 11,803 14,035 25,838 51,411

Gold sales1 ounces 24,379 12,828 11,888 24,716 49,095

Average sales price US$/ounce 1,847 1,877 1,985 1,929 1,888

Unit Production Costs

Mining cost US$/t mined 3.85 3.71 4.80 4.20 4.05

Processing cost US$/t milled 16.58 12.69 17.86 15.04 15.78

G & A cost US$M/month 1.35 1.46 1.76 1.61 1.48

All-In Site Cost 2,3

Production cost US$/ounce 1,389 1,276 1,558 1,431 1,411

Royalties US$/ounce 95 121 86 101 98

Sub-total US$/ounce 1,484 1,397 1,644 1,532 1,509

Sustaining capital US$/ounce 6 61 161 116 60

Total All-In Site Cost US$/ounce 1,490 1,458 1,805 1,647 1,569

Notional Cashflow from Operations 3

Cash Margin US$/ounce 357 419 180 281 319

Notional Cash Flow US$M 9 5 2 7 16

Notes:

1. Gold sales are recognised in Perseus’s accounts when gold is delivered to the customer from Perseus’s metal account.

2. Included in the AISC for the June quarter is US$0.4 million of costs relating to excess waste stripping. When reporting cost of sales, in line with accepted

practice under IFRS, this cost will be capitalised, and the costs amortised over the remainder of the relevant pit life.

3. Commercial production at Fimbiasso was declared 1 April 2023. A total of US$4.2 million of pre-commercial production operating costs have been

excluded from All-In-Site-Costs. Furthermore, the 269oz that were produced from Fimbiasso prior to the declaration of commercial production h ave

been deducted from the oz produced figures in the calculation of All-In-Site-Costs, cash margin, and notional cash flows.

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

Sissingué Complex produced total of 14,035 ounces of gold during the quarter, at a production cost of US$1,558 per ounce

and an AISC of US$1,805 per ounce. Gold production was 19% higher than the previous quarter, however AISCs were higher

due to the cessation of capitalisation of development and establishment costs with the commencement of commercial

production at Fimbiasso during the period.

The Sissingué operation now involves mining and processing of ore from low-grade stockpiles as well as from the remnants

of West Arm, Binkadi and Bagoé pits on the Sissingué Mining Lease along with mining, trucking and processing ore from the

satellite Fimbiasso East and West pits on the Fimbiasso Mining Lease.

During the quarter, the performance of Perseus’s ore haulage contractor improved after a slow start to operations, enabling

a progressively higher proportion of higher-grade ore from the satellite pits at Fimbiasso East and West, to be processed. By

the end of the quarter, daily haulage targets were being consistently exceeded.

Overall operating performance at the Sissingué Complex was mixed during the quarter. Head grade (1.19g/t gold) improved

by 40% relative to the last quarter, while runtime (-10%), and throughput rate (-7%) both lagged the prior quarter and the

recovery rate (93.0%) was better than the prior quarter.

The AISC of US$1,805 per ounce was higher than in the previous quarter due largely to Fimbiasso pre-production costs that

were being capitalised in prior quarters being expensed in June 2023 quarter, including costs associated with establishing a

haulage operation to transport Fimbiasso ore back to the central processing facility. The weighted average sales price of the

11,888 ounces of gold sold during the quarter was US$1,985 per ounce, giving rise to an average cash margin of US$180 per

ounce. Notional cashflow generated by the mine during the quarter totalled US$2 million.

BAGOÉ MINING LEASE

Perseus has lodged all documentation required for assessment of its application for an Exploitation Permit for the Bagoé

Project with the Ivorian Department of Mines, Petroleum and Energy and is currently being assessed . Community

consultations with the three regions likely to be impacted by the Bagoé mining operation are underway and progressing

well, with the consultation process successfully closed for the Boundiali region. The Exploitation Permit should be granted

on completion of these consultations and thereafter a Mining Convention covering the operation will be negotiated.

Construction of infrastructure required to support a mining operation at Bagoé will commence as soon as possible following

receipt of the Bagoé Mining Lease.

MINERAL RESOURCE TO MILL RECONCILIATION

The reconciliation of processed ore tonnes, grade and contained ounces relative to the Sissingué Complex Mineral Resource

block models is in Table 9 below. During the June Quarter, grade control has predicted additional tonnes (+5%) at higher

grade (+12%) resulting in an increase in overall ounces (+ 17%) when compared to the Mineral Resource Estimate (MRE).

Over the past six - and 12-month periods, Sissingué has processed overall more metal than the Mineral Resource model

estimation. The reconciliation between mineral resources and the mill at the Sissingué complex is considered satisfactory,

and improvement work continues to align the resource model more closely with the over-delivery of tonnes observed in the

grade control.

Table 9: Sissingué complex Block Model to Mill Reconciliation

PARAMETER BLOCK MODEL TO MILL CORRELATION FACTOR

3 MONTHS 6 MONTHS 1 YEAR

Tonnes of Ore 1.05 1.08 1.15

Head Grade 1.12 1.01 0.98

Contained Gold 1.17 1.10 1.12

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

GROUP GOLD PRODUCTION AND COST MARKET GUIDANCE

Group gold production and AISCs for the December 2023 Half Year and the 2023 Calendar Year are as shown below in

Table 10.

Table 10: Production and Cost Guidance

PARAMETER UNITS JUNE 2023 HALF YEAR

(ACTUAL)

DECEMBER 2023 HALF YEAR

(FORECAST)

2023 CALENDAR YEAR

(FORECAST)

Yaouré Gold Mine

Production Ounces 137,120 125,000 to 140,000 262,100 to 277,120

All-in Site Cost USD per ounce 786 850 to 950 818 to 864

Sissingué Gold Mine

Production Ounces 25,838 27,500 to 32,500 53,338 to 58,338

All-in Site Cost USD per ounce 1,647 1,700 to 1,900 1,677 to 1,777

Edikan Gold Mine

Production Ounces 103,952 90,000 to 100,000 193,952 to 203,952

All-in Site Cost USD per ounce 1,094 1,200 to 1,300 1,146 to 1,190

PERSEUS GROUP

Production Ounces 266,909 242,500 to 272,500 509,409 to 539,500

All-in Site Cost USD per ounce 989 1,080 to 1,190 1,035 to 1,085

NEWS RELEASE | JUNE 2023 QUARTER REPORT

PERSEUSMINING.COM

SUSTAINABILITY

SUSTAINABILITY GOVERNANCE

During the quarter, Perseus continued to strengthen its sustainability governance through:

• Continued work on strengthening Group safety performance with the roll-out of Phase 2 of the “Safely Home Every

Day” (SHED) program across our sites. This included one-on-one coaching and Train-the-Trainers sessions, as well as

Supervisors skills development sessions and training of Safety Champions.

• Yaouré Community Trust Fund management committee established by the Ministry of Mines, Petroleum and Energy.

The local development plan is being finalised in consultation with the 15 local communities with completion expected

in July.

• First public hearing as part of the Bagoé Environment Permit (EP) application process successfully completed at

Boundiali, with the process underway in Mbengué and Korhogo regions.

SUSTAINABILITY PERFORMANCE

This quarter, Perseus continued its strong sustainability performance relative to objectives and targets, as shown below in

Table 11 and summarised as:

• Safety:

– Safety performance across the portfolio remained stable, with the Group Total Recordable Injury Frequency Rates

(TRIFR) decreasing slightly from 1.29 at the end of March 2023 to 1.20 at the end of June 2023 , which remains

higher than the FY23 threshold of 1.10 and target of 0.8. There were two recordable injuries for the June quarter

across the Group.

– Lost Time Injury Frequency (LTIFR) across the Group remains stable at 0.26 for the June quarter from 0.25 in March.

• Social:

- Total economic contribution to Perseus’s host operating countries Ghana and Côte d’Ivoire for the quarter was

~US$158 million (up US$2m from last quarter and approximately 58% of revenue), which included 77% of the

Company’s procurement on Purchase Order Value basis paid to local suppliers, and ~US$1.3 million in social

investment (includes accrual for Yaouré).

- Local and national employment decreased slightly to 94% for the reporting quarter. Across the Group, the

proportion of female employees declined slightly to 11.4% for the June 2023 quarter (from 12.4% in the March

quarter).

- There were no significant community events (Category 3 or above) reported during the June quarter.

• Environment:

– Total Scope 1 and 2 Greenhouse Gas emissions intensity per ounce of gold produced decreased to 0.48 tCO2-e/oz

for the quarter ended June 2023from 0.53 tCO2-e/oz for the quarter ended March 2023.

– Zero significant (Consequence 3) environmental or tailings dam integrity issues occurred during the period.

In achieving the above, the following sustainability challenges were encountered by Perseus during the quarter:

• Safety remains a key priority for the Company, with emphasis placed on hand safety following two injuries sustained

during the quarter and further roll-out of the SHED program.

• Illegal mining activities on some of Perseus’s mining and exploration licence areas continue to present challenges for

the Company. Perseus continues to work closely with relevant government authorities to manage these activities that

have proven to negatively impact both the environmental and social fabric of local communities.