PPX Mining Continues Advancing Construction of Its GOLD and Silver Processing Plant

Mine Development & Operations Metallurgy & Processing

PRESS RELEASE

PPX MINING CONTINUES ADVANCING CONSTRUCTION OF ITS

GOLD AND SILVER PROCESSING PLANT

Toronto – November 12, 2025 – PPX Mining Corp. (TSX .V: PPX; BVL: PPX, the “Company” or

“PPX”) is pleased to announce that construction of PPX Min ing’s processing plant continues to advance

steadily, with major milestones achieved across all operational areas. Civil works for the leaching zone are

complete and tank installation is underway, while c rushing and milling components are nearing full

assembly with equipment largely on site. Fabricatio n of reagent tanks and flotation equipment has been

finalized, with installation progressing on schedul e. Desorption units, geotube tailings infrastructur e, and

key laboratory facilities are currently under const ruction, supported by the arrival of geotextile mat erials

and laboratory instruments. Complementing these eff orts, the Company has commenced the construction

of auxiliary works, including a 200-square-meter an alytical/metallurgical laboratory and the first 370 -

meters of reinforced concrete security perimeter wall, both expected to be completed by year-end.

Leaching Area

The civil works for the leaching area have been com pleted, and the installation of tanks, managed by J PC

Ingenieros, has begun. All metal-mechanical materials are 100% purchased and delivered to site. Welding

and assembly of the first four tanks are being fina lized, while the bases for the remaining four tanks are

underway, with completion expected by mid-December.

Images 1: Leaching tanks installation and assembly progress

Images 2: Leaching tanks installation and assembly progress

Images 3: Leaching tanks installation and assembly progress

Crushing Area

All equipment has been fabricated, and the majority is already on site, except for the fine ore hopper, which

is currently being transported from Lima to the project site. The containment wall for the coarse ore hopper

has been redesigned and will now be built in reinforced concrete.

Image 4: Fine ore hopper ready for shipment from Lima

Milling Area

Both mills have been installed and aligned, includi ng their drive systems. Installation of the pump bo xes

for mill discharge and the associated pumps is in p rogress. The level control system for the pump feed

boxes has been ordered and is pending delivery. The cyclone tower and both cyclone assemblies are now

in place. Measurements of the mill liners have been taken for local fabrication of spare parts in Peru.

Image 5: Mills with installed pump boxes

Reagent Preparation Area

All civil works have been completed, and all reagen t supply pumps are on site. The largest reagent

preparation tanks have been fabricated and are being transported to the project.

Image 6: Completed fabrication of main reagent tanks for cyanide and flocculant preparation

Flotation Area

All equipment has been delivered to site, and civil works for the flotation cells are in progress. The

concentrate thickener installation is approximately 50% complete, and the filter press foundations hav e

been completed, with installation now underway.

Image 7: Flotation area and thickener installation progress

Desorption Area

All desorption equipment has been fabricated in Lima and will be transported to site once the ongoing civil

works are completed.

Images 8: Completed Electrowinning Cells,

Image 9: Gas Extractors Production Completed

Image 10: Metallic Bases for Desorption Plant

Geotube Tailings Storage Area

The earthworks are finished, and the installation of the drainage system is about to begin. The first shipment

of geotextiles and geomembranes, purchased from Chi na, has arrived in Peru and is being transported to

the project site.

Image 11: Transport of Geotextiles from Callao Port to Site

Metallurgical Laboratory

Major laboratory equipment has been purchased and is awaiting completion of the civil works, which began

last week. The laboratory structure will be built with drywall and concrete, and is currently in the foundation

and slab preparation stage. The facility will cover 200 m² and will analyze both plant and mine samples.

Image 12: Construction of concrete slab and sanitary installations for laboratory

Security Perimeter Wall

The first 370 meters of prefabricated concrete wall have been installed, representing 20% completion of the

total perimeter. The wall is expected to be fully completed by year-end.

Images 13: Perimeter Wall Construction Progress

Images 14: Perimeter Wall Construction Progress

John Thomas, CEO of PPX Mining Corp. commented: “The ongoing progress we are achieving at the Igor

Plant reflects the dedication of our entire team an d our commitment to transforming PPX into a fully

integrated gold producer. Construction is advancing across all key areas, from leaching and milling to

auxiliary facilities, ensuring that every component meets the highest technical and environmental standards.

This is an important phase for PPX as we build the foundation for future gold and silver production growth

and create lasting value for our shareholders, employees, and local communities.”

About PPX Mining Corp:

PPX Mining Corp. (TSX.V: PPX.V, SSE: PPX, BVL: PPX) is a Canadian exploration and development

company with assets in northern Peru. The Company's 100% owned Igor gold and silver project is located

in the prolific northern Peruvian gold belt in the department of La Libertad. PPX is pursuing a two-pronged

strategy to further develop and explore Project Igor. The Callanquitas structure is open along strike and at

depth. Parallel structures have not yet been explored. The new discoveries in Portachuelos in 2018, as well

as the exploration targets in Domo and Tesoros, sho w that the Igor Project is becoming a district-scal e

project with multiple deposits and mineralized zone s. Evaluating mineral development alternatives in

parallel with exploration drilling will provide dual catalysts for growth and increased shareholder value.

All scientific and technical information in this pr ess release has been reviewed and approved by John

Thomas, P. Eng., who is the CEO of the Company and a qualified person under the definitions established

by National Instrument 43-101.

On behalf of the Board of Directors

John Thomas

Chief Executive Officer

82 Richmond Street East

Toronto, Ontario M5C 1P1

Canada

416-361-0737

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined

in the policies of the TSX Venture Exchange) accept s responsibility for the adequacy or

accuracy of this release.

Cautionary Statement

This press release contains forward-looking informa tion and forward-looking statements (collectively,

“forward-looking statements”) as such terms are defined by applicable securities laws, including, but not limited

to statements regarding test results, future plans or management estimates. Forward-looking statements are

statements that relate to future events. In this context, forward-looking statements often address expected future

business and financial performance and often contain words such as “anticipate,” “believe,” “plan,” “e stimate,”

“expect,” and “intend,”, statements that an action or event “may,” “might,” “could,” “should,” or “wil l” be taken

or occur, or other similar expressions. Forward-loo king statements are subject to a number of known an d

unknown risks and uncertainties, many of which invo lve factors or circumstances that are beyond the

Company’s control, and the Company’s actual results could differ materially from those stated or impli ed in

forward-looking statements due to many various fact ors. Such uncertainties and risks include, among ot hers,

delays in obtaining or inability to obtain required regulatory approvals in connection with this trans action.

Although the Company believes that the expectations reflected in the forward-looking statements are reasonable,

the Company cannot guarantee that the events and ci rcumstances reflected in the forward-looking statem ents

will be achieved or occur. The timing of events and circumstances and actual results could differ mate rially

from those projected in the forward-looking stateme nts. Accordingly, one should not place undue relian ce on

forward- looking statements. All forward-looking st atements contained in this press release are made a s of

today’s date, and the Company undertakes no obligat ion to update or publicly revise any forward-lookin g

statements, whether as a result of new information, future events or otherwise, unless required by law.