NEWS RELEASE

November 9, 2022

Perpetua Resources Announces Supplemental Draft EIS Highlights Positive

Environmental Outcomes

Perpetua’s Modified Mine Plan identified as Preferred Alternative due to improvements in water quality

and temperature and site access benefits.

Modified Mine Plan expected to deliver net environmental benefits based on the comprehensive

scientific analysis mandated by the National Environmental Policy Act.

BOISE, ID – Perpetua Resources Corp. (Nasdaq: PPTA / TSX: PPTA) (“Perpetua Resources” or “Perpetua”

or “the Company”) announced today that the Supplemental Draft Environmental Impact Stat ement

(“SDEIS”) published by the United States Forest Service (“USFS”) on October 28, 2022 highlights the net

positive environmental outcomes that the Stibnite Gold Project (“Project”) can provide to the abandoned

mine site based on the results of comprehensive scientific analysis conducted by the USFS over the last

six years. The USFS identified Perpetua Resources’ proposed action, the “ Modified Mine Plan ,” as the

Preferred Alternative because the Modified Mine Plan:

1. Incorporates water management and closure activities to reduce the duration of long-term water

treatment requirements,

2. Includes measures to manage stream temperatures, and

3. Reduces potential impacts associated with access, transportation , and hazardous materials on

alternative access routes to the project site.

The USFS also concluded the Preferred Alternative would reasonably accomplish the purpose and need

for consideration of approval of the Stibnite Gold Project, while giving consideration to environmental,

economic, and technical factors. Under the National Environmental Policy Act (“NEPA”), a “Preferred

Alternative” is identified by a Federal agency in a Draft Environmental Impact Statement (“DEIS”) to let

the public know which action the agency is leaning toward selecting as final.

“We are proud that the USFS recognizes Perpetua’s diligent efforts to improve environmental outcomes

for the historic mining area through the redevelopment of the Stibnite Gold Project,” said Laurel Sayer,

President and CEO of Perpetua Resources. “We designed our Project to improve river habitat and water

quality. The feedback we have heard from our stakeholders, through the NEPA process and public

engagement, has helped us enhance our plan and we are pleased to see the USFS highlighted some of

these improvements in the SDEIS.”

The SDEIS compares the environmental impacts of the Modified Mine Plan to leaving the project site as

it is today (“baseline conditions”). In identifying the Modified Mine Plan as the Preferred Alternative, the

SDEIS articulates several specific ways that the Modified Mine Plan is expected to improve environmental

conditions in certain key areas relative to the baseline conditions, including improving water quality,

mitigating effects on water temperature, and increasing access to habitat for fish. Several of these

conclusions from the SDEIS are summarized below.

Responsible Mining. Critical Resources. Clean Future.

2

Modified Mine Plan Increases Access to Fish Habitat Relative to Baseline Conditions:

• Net increase in available fish habitat both during operations and following closure and

reclamation, including an estimated increase in critical habitat available to Chinook salmon and

bull trout by over 19 km and to steelhead by over 8 km

• Net increase in suitable rearing habitat for steelhead and improved thermal suitability of newly

accessible habitat for Chinook salmon resulting from improved water temperatures in the East

Fork South Fork Salmon River

• Permanent, regional , and beneficial effect on Chinook salmon, steelhead, bull trout and

westslope cutthroat trout within the vicinity of the mine driven by the removal of fish barriers and

planned restoration activities

• Increased habitat available for potential occupancy and increased occupancy probability for bull

trout and westslope cutthroat trout following completion of restoration activities including

construction of the Stibnite Lake; however, there are net impacts to bull trout critical habitat

projected from operations and the post-closure configuration of the Tailings Storage Facility

(“TSF”)

• Long-term and beneficial effect on fish resulting from reduced contaminant concentrations in

the East Fork South Fork of the Salmon River downstream from the Project site – approximately

40% reduction in arsenic and 58% reduction in antimony in surface water

Modified Mine Plan Improves Water Quality and Mitigates Effects on Water Temperature Relative to

Baseline Conditions:

• Greatly reduced the volume and duration of long-term water treatment due to the adoption of

a refined, comprehensive water management plan, and updated closure strategy incorporating

engineered cover systems over the TSF, and backfilled Yellow Pine and Hangar Flats pits which

improve surface water quality

• Improvements in stream temperatures across the majority of the site including significant

temperature reductions in Meadow Creek below East Fork Meadow Creek and overall reduced

temperatures in the East Fork South Fork Salmon River relative to baseline conditions due to

enhanced riparian planting prescriptions, incorporation of temperature buffering lake feature,

and piping of Meadow Creek summer low flow around the TSF during operations

• Temperature increases of up to 6.6OC are predicted in upper Meadow Creek above East Fork

Meadow Creek following restoration of the stream across the TSF and prior to establishment of

riparian vegetation, but summer maximum temperatures are expected to drop to one degree

below baseline conditions once riparian vegetation is fully mature

“Perpetua Resources has always been committed to modern, responsible mining practices,” said Deb

Filler, Yellow Pine resident. “Today, the East Fork South Fork of the Salmon River is polluted from mining

wastes left in Meadow Creek. Perpetua’s plan will improve water quality in our backyard, restore fish

passage that has been blocked for decades, and create hundreds of jobs for l ocal residents while

producing a critical mineral our country needs.”

The extensive scientific analysis by the USFS and cooperating agencies, combined with the additional

public review of the SDEIS, fortify the rigorous environmental review process mandate d by NEPA.

Identification of the Modified Mine Plan as the Preferred Alternative by the USFS is a major milestone in

the advancement of the Project and provides clarity for the remainder of the NEPA process. The

Company anticipates that the USFS will updat e its schedule for the remain der of the NEPA process

following the SDEIS comment period which is expected to end January 10, 2023.

Responsible Mining. Critical Resources. Clean Future.

3

For further information about Perpetua Resources Corp., please contact:

Chris Fogg

Investor Relations Manager

[email protected]

[email protected]

Mckinsey Lyon

Vice President External Affairs

[email protected]

Website: www.perpetuaresources.com

About Perpetua Resources and the Stibnite Gold Project

Perpetua Resources Corp., through its wholly owned subsidiaries, is focused on the exploration, site

restoration and redevelopment of gold-antimony-silver deposits in the Stibnite-Yellow Pine district of

central Idaho that are encompassed by the Stibnite Gold Project. The Project is one of the highest-

grade, open pit gold deposits in the United States and is designed to apply a modern, responsible

mining approach to restore an abandoned mine site and produce both gold and the only mined source

of antimony in the United States. Further advancing Perpetua Resources’ ESG and sustainable mining

goals, the Project will be powered by the lowest carbon emissions grid in the nation and a portion of

the antimony produced from the Project will be supplied to Ambri, a US-based company

commercializing a low-cost liquid metal battery essential for the low-carbon energy transition. In

addition to the company’s commitments to transparency, accountability, environmental stewardship,

safety and community engagement, Perpetua Resources adopted formal ESG commitments which can

be found here.

Forward-Looking Information and Cautionary Note

Investors should be aware that the publication of the SDEIS and the identification by the USFS of the Modified Mine

Plan as the Preferred Alternative does not indicate any commitments on the part of the USFS with regard to a final

decision. In developing the Final Environmental Impact Statement (“FEIS”), the next phase of the NEPA planning

process, the USFS may select various actions based on the Modified Mine Plan or each of the alternatives analyzed

in the S DEIS. The SDEIS is subject to review and comment by the public through the public review period, which

may be extended by the USFS in its sole discretion. In addition, statements contained in this news release that are

not historical facts are "forward-looking information" or "forward-looking statements" (collectively, "Forward-Looking

Information") within the meaning of applicable Canadian securities legislation and the United States Private Securities

Litigation Reform Act of 1995. Forward -Looking Inform ation includes, but is not limited to, disclosure regarding

possible events, next steps and courses of action including environmental clean up actions by us and our contractors;

our ability to comply with and obtain permits related to the Stibnite Gold Pro ject; actions to be taken by the USFS,

the State of Idaho and other government agencies and regulatory bodies; the timing of the public review period;

predictions regarding improvements to water quality, water temperature, and fish habitats and other environmental

conditions at the site, including with respect to process and timing of such improvements; reduction of the Project

footprint and the anticipated benefits and other effects thereof; our ability to successfully implement the Project and

the occurrence of the expected benefits from the Project, including contributions to the workforce, national security

and clean energy transition; our and Ambri Inc.’s ability to perform under the supply agreement, which agreement is

subject to certain conditions, including identification of one or more refiners to transform our antimony concentrate

into antimony metal, and mutual agreement on certain material terms, including volume and pricing. In certain cases,

Forward-Looking Information can be ide ntified by the use of words and phrases or variations of such words and

phrases or statements such as "anticipate", “expect” “plan”, “likely”, “believe”, “intend”, “forecast”, “project”,

“estimate”, "potential", "could", "may", "will", "would" or “should”. In preparing the Forward-Looking Information in

this news release, Perpetua Resources has applied several material assumptions, including, but not limited to,

assumptions that the current exploration, development, environmental and other objectives concerning the Stibnite

Responsible Mining. Critical Resources. Clean Future.

4

Gold Project can be achieved and that its other corporate activities will proceed as expected; that the review

process under the NEPA (including any joint review process involving the USFS, the State of Idaho and other agencies

and regu latory bodies) as well as the public review process and SDEIS will proceed in a timely manner and as

expected; that we will be able to obtain sufficient funding to finance permitting, pre -construction and construction

of the Project and that all requisite information will be available in a timely manner. Forward-Looking Information are

based on certain material assumptions and involve known and unknown risks, uncertainties and other factors which

may cause the actual results, performance or achievements of Perpetua Resources to be materially different from any

future results, performance or achievements expressed or implied by the Forward -Looking Information. Such risks

and other factors include changes in laws and regulations and changes in the application of standards pursuant to

existing laws and regulations which may result in unforeseen results in the permitting process; uncertainty

surrounding input to be received from regulators and community stakeholders; risks related to dependence on key

personnel; risks related to unforeseen delays in the review process including availability of personnel from the USFS,

State of Idaho and other stated, federal and local agencies and regulatory bodies (including, but not limited to, future

US government shutdowns); risks related to opposition to the Project; risks related to increased or unexpected costs

in operations or the permitting process; risks that necessary financing will be unavailable when needed on acceptable

terms, or at all; risks related to the outcome of litigation and potential for delay of the Project, as well as those factors

discussed in Perpetua Resources' public filings with the U.S. Securities and Exchange Commission (the “SEC”) and

its Canadian disclosure record. Although Perpetua Resources has attempted to identify important factors that could

affect Perpetua Resources and may cause actual actions, events or results to differ materially from those described

in Forward -Looking Information, there may be other factors that cause actions, events or results not to be as

anticipated, estimated or intended. There can be no assurance that Forward -Looking Information will prove to be

accurate, as actual results and future events could differ materially from those anticipated in such statements.

Accordingly, readers should not place undue reliance on Forward -Looking Information. For further information on

these and other risks and uncertainties that may affect the Company’s business, see the “Risk Factors” and

“Management’s Discussion and Analysis of Financial Condition and Results of Operations” sections of the Company’s

filings with the SEC, which are available at www.sec.gov and with the Canadian securities regulators, which are

available at www.sedar.com. Except as required by law, Perpetua Resources doe s not assume any obligation to

release publicly any revisions to Forward -Looking Information contained in this news release to reflect events or

circumstances after the date hereof or to reflect the occurrence of unanticipated events.