Permitting Process for Midas Gold’s Stibnite Gold Project Continues to Advance Record of Decision for Proposed Stibnite Gold Project Still Expected in Late Q4 2020

Permits & Approvals

Page 1 of 3

Permitting Process for Midas Gold’s Stibnite Gold Project Continues to Advance

Record of Decision for Proposed Stibnite Gold Project Still Expected in Late Q4 2020

VANCOUVER, BRITISH COLUMBIA – Midas Gold Corp. (MAX:TSX / MDRPF:OTCQX) (“Midas Gold” or the “Company”)

reported today that permitting for the Stibnite Gold Project (“Project”) continues to move forward on the schedule

announced on April 2, 2019, without any additional delays. Midas Gold Idaho, a subsidiary of Midas Gold, has been

working closely with federal and state regulators to ensure that the permitting remains on track with the agreed

schedule. This is the second quarter in a row that the United States Forest Service ( “USFS”) has held to issuing a

Draft Environmental Impact Statement (“EIS”) for public comment in late Q4 2019. This schedule also forecasts

issuing a Final EIS and Draft Record of Decision (“ROD”) in Q3 2020 and the Final ROD for the Project in late Q4

2020. The USFS, in cooperation with the six other federal, state and local agencies responsible for the permitting

schedule, provided the updated timeline as part of its quarterly update on the Project, which is located in Valley

County, 44 miles northeast of Cascade and 14 miles from Yellow Pine, Idaho.

“We are pleased that the USFS continues to meet the permitting schedule published in April 2019 and that, in a

few months’ time, the public will be able comment on our proposed project,” said Laurel Sayer President & CEO of

Midas Gold Idaho. “After years of thorough analysis and review, we are getting closer to fully realizing the benefits

of the Stibnite Gold Project. Through redevelopment of a brownfields site, this Project is designed to restore fish

habitat, reconnect salmon to their native spawning grounds and address numerous legacy impacts from historical

mining activities in order to improve water quality. If permitted, we will bring hundreds of well-paying jobs to rural

Idaho and invest hundreds of m illions of dollars in the state while bringing environmental restoration to a long-

abandoned mine site. We want to see all of this happen and we will continue to work closely with regulators to

meet the project timeline.”

Joint Review Process

Seven federal, state and local agencies involved in permitting the Project signed the Stibnite Joint Review Process

Memorandum of Understanding (“MOU”) in 2017, committing to work together to evaluate the Plan of Restoration

and Operations (“PRO”) for the Stibnite Gold Project under the National Environmental Policy Act (“NEPA”). The

MOU was designed so agencies could collaborate in the review and preparation of the EIS, meet the requirements

of the public process and follow a mutually agreed upon schedule. Agency cooperation and collaboration remains

key to the timeliness and completeness of the process.

Permitting Schedule

The PRO was accepted as complete by the USFS in December 2016, and the USFS submitted a Notice of Intent to

initiate review of the Project and then conducted Public Scoping in June and July of 2017. Since that time, the USFS,

their contractor AECOM, and other cooperating agencies have continued with their review of the PRO, baseline

data and public comments, defining potential alternatives and analyzing them, and reviewing additional

information they requested and which Midas Gold Idaho has provided. In response to agency comments and, based

on the results of analysis of potential outcomes modelled by Midas Gold Idaho, Midas Gol d Idaho modified a

number of Project components in order to reduce Project footprint, improve water quality and enhance habitat.

This modified PRO (“ModPRO”) is being considered alongside other alternatives being assessed by the regulators

under NEPA.

Under NEPA, r egulators need to ensure that they meet the regulatory requirements to support a robust and

defensible Record of Decision. During the review process, regulators filed 127 requests for additional information

(“RFAI”) in order to evaluate the tho roughness of the environmental impact analysis and have received tens of

thousands of pages of additional data and analysis to aid in their careful consideration of the proposed plan and

various alternative development scenarios, including those set out in the ModPRO. In January and April 2019, the

USFS had pushed back the release of the Draft EIS, in order to accommodate thorough and

comprehensive evaluations of the information provided in the ModPRO and in response to information provided

under the RFAIs.

NEWS RELEASE

October 07, 2019

#2019-13

Page 2 of 3

“Our team is working hard to design, permit and build a modern mining project that can be profitable and have a

positive impact on the local community and environment,” said Laurel Sayer, CEO of Midas Gol d Idaho. “We

appreciate the painstaking review by the USFS because we know it will make our project better. In fact, through

the permitting process, we have been able to identify multiple refinements to our initial proposal that reduce the

project impact and improve environmental outcomes, including those detailed in the modified PRO. We are proud

of the work we have completed and look forward to moving into the next phase of permitting. We appreciate the

USFS and other regulator’s commitment to the maintain the permitting timeline as they complete their review.”

Next Steps in the Regulatory Process

The USFS, on behalf of the various regulatory agencies, is currently completing the alternatives assessment and

environmental analysis as required by NEPA. Th is is the core of the review process and provides the basis for

drafting of the Draft EIS, which is currently being prepared.

The next opportunity for public review and comment will come when the agencies release the Draft EIS, which is

currently anticipated to take place late Q4 2019, with a 45- day public comment period to commence following

publication of the Draft EIS. After the comment period, the USFS and cooperating agencies would produce the Final

EIS and a Draft ROD as well as addressing public comments received on the Draft EIS. Upon publication of the Final

EIS, there would be a period for objections and resolution before a Final ROD is published. A positive final decision

would allow Midas Gold Idaho to seek the issuance of the final permits that are dependent on the ROD being issued.

Feasibility Study Status

Midas Gold I daho’s technical team and consultants continue to advance their work on a feasibility study for the

Stibnite Gold Project, which will be completed following the issuance of the Draft EIS to ensure that any Project

components in the Draft EIS are addressed in the study. While substantially all of the work related to mineral

resource estimation, metallurgy, geotechnical, infrastructure (including road access, powerline, tunnel design) and

other aspects of the Project needed to support a feasibility study is w ell advanced, finalization of the design and

estimating of capital and operating costs and the actual feasibility study are awaiting completion of various ongoing

optimization studies and the Draft EIS.

As previously disclosed, the feasibility study looks to incorporate the results of a number of Project optimizations,

including updated mineral resource estimates, results of optimized metallurgy and processing, optimized layout

and plant design, and other considerations. A number of these optimizations are focused on reducing potential

environmental effects and impacts from mine redevelopment, and to enhancing the restoration of the site to

ensure a healthy, sustainable ecosystem during and after operations. The extended permitting schedule, resulting

from the delays announced in late 2018 and early 2019, does provide the opportunity to undertake certain value

engineering exercises, where deemed appropriate, and to include the results of such evaluations in the feasibility

study. As part of this Project optimization process, Midas Gold’s personnel and its consultants are also working to

optimize various aspects of the Project, including mine planning, scheduling and stockpiling, plant layout and water

management strategies.

Litigation Update

On or before October 18, 2019, Midas Gold Idaho will file its initial response to the lawsuit filed by the Nez Perce

Tribe under the Clean Water Act, which litigation was discussed in the news release dated June 7, 2019. Before the

action was filed, the Comp any was engaged, and continues to be, in negotiations with the United States

Environmental Protection Agency, the State of Idaho and the United States Forest Service to further address site

legacy conditions under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”),

issues that the Company did not create. Midas Gold Idaho continues to believe that, instead of litigation, the best

solution for the site is for all stakeholders to work together to implement the comprehensive reclamation and

restoration of the numerous legacy issues around the site, funded through cash flow from the redevelopment of

the site as a modern mining operation.

Stibnite Gold Project Permitting Background

A detailed presentation on the PRO can be found at www.midasgoldcorp.com. Details of previous news releases and

technical studies can be found filed under Midas Gold’s profile on SEDAR ( www.sedar.com) or at

www.midasgoldcorp.com.

For further information about Midas Gold Corp., please contact:

Page 3 of 3

Liz Monger -- Manager, Investor Relations (t): 778.724.4704

(e): [email protected]

Facebook: www.facebook.com/midasgoldidaho Twitter: @MidasIdaho

Website: www.midasgoldcorp.com

About Midas Gold and the Stibnite Gold Project

Midas Gold Corp., through its wholly owned subsidiaries, are focused on the exploration and, if warranted, site

restoration and development of gold -antimony-silver deposits in the Stibnite -Yellow Pine district of central Idaho

that are encompassed by its Stibnite Gold Project.

Forward-Looking Information

Statements contained in this news release that are not historical facts are "forward -looking information" or

"forward-looking statements" (collectively, "Forward -Looking Information") within the meaning of applicable

Canadian securities legislation and the United States Private Securities Litigation Reform Act of 1995. Forward

Looking Information includes, but is not limited to, disclosure regarding possible events, next steps and courses of

action including, but not limited to, actions to be taken by the USFS, the State of Idaho and other government

agencies and regulatory bodies; the anticipated permitting schedule; next steps in the regulatory process; and

potential timing for completion of a feasibility study. In certain cases, Forward-Looking Information can be identified

by the use of words and phrases or variations of such wo rds and phrases or statements such as "anticipates",

"complete", "comprehensive", "defensible", "ensure", "potential" and "robust", in relation to certain actions, events

or results "could", "may", "will", "would", be achieved. In preparing the Forward- Looking Information in this news

release, Midas Gold has applied several material assumptions, including, but not limited to, assumptions that the

current objectives concerning the Stibnite Gold Project can be achieved and that its other corporate activities will

proceed as expected; that general business and economic conditions will not change in a materially adverse manner;

that the formal review process under the NEPA (including a joint review process involving the USFS, the State of Idaho

and other agencies and regulatory bodies) as well as the public comment period and EIS will proceed in a timely

manner and as expected; and that all requisite information will be available in a timely manner. Forward-Looking

Information involves known and unknown risks, uncertainties and other factors which may cause the actual results,

performance or achievements of Midas Gold to be materially different from any future results, performance or

achievements expressed or implied by the Forward-Looking Information. Such risks and other factors include, among

others, changes in laws and regulations and changes in the application of standards pursuant to existing laws and

regulations which may result in unforeseen results in the review process under the NEPA; uncertainty surrounding

input to be received pursuant to the public comment period; risks related to dependence on key personnel; risks

related to unforeseen delays in the review process including availability of personnel from the USFS, State of Ida ho

and other agencies and regulatory bodies (including, but not limited to, future US government shutdowns); risks

related to the outcome of potential litigation; risks related to opposition to the Project, as well as those factors discussed in

Midas Gold's public disclosure record. Although Midas Gold has attempted to identify important factors that could

affect Midas Gold and may cause actual actions, events or results to differ materially from those described in

Forward-Looking Information, there may be other factors that cause actions, events or results not to be as

anticipated, estimated or intended. There can be no assurance that Forward- Looking Information will prove to be

accurate, as actual results and future events could differ materially from thos e anticipated in such statements.

Accordingly, readers should not place undue reliance on Forward- Looking Information. Except as required by law,

Midas Gold does not assume any obligation to release publicly any revisions to Forward- Looking Information

contained in this news release to reflect events or circumstances after the date hereof or to reflect the occurrence

of unanticipated events.