Ethos trenches 0.48% V2O5 over 130 m at Pine Pass Vanadium Project
Suite 1430 – 800 West Pender Street, Vancouver, BC V6C 2V6
Ethos trenches 0.48% V2O5 over 130 m at Pine Pass Vanadium Project
Vancouver, BC – November 1, 2018, Ethos Gold Corp. (“ Ethos ” or the “ Company ”)
(TSXV:ECC) (OTCQX:ETHOF) is pleased to announce the completion of the 2018 sampling
and trenching program (Phase 2 work) and to provide initial trench results for its Pine Pass
vanadium project, located on the John Hart Highway, north-eastern British Columbia
approximately 70 kilometers west of Chetwynd, and 200 kilometers north of Prince George.
Following up on initial soil, rock, and stream sedi ment sampling (see September 25, 2018 press
release), five trenches were hand dug at Pine Pass in September and early October 2018.
Trenches 18PPT1, 2 and 5 were hand dug across the p rojected east limb of the host syncline
which dips approximately 45-50 ˚ to the west. Trenches 18PPT3 and 4 were dug acros s the
projected west limb which dips approximately 50-60 ˚ to the east. Additionally, a line of
continuous rock chip sampling (18MST1) was complete d across the west limb mineralized
horizon on a road cut on the John Hart Highway.
A 100 m interval in Trench 1 (18PPT1) on the eastern syncline limb subcrop (see Figure 1 )
returned the following results (continuous along trench):
Length
(m) V2O5 Grade
15 0.44%
10 unable to get to bedrock
23 0.47%
25 0.25%
27 0.45%
100
This interval is contained within a broader mineral ized envelope: in Trench 1 there were
cumulative sample intervals (not continuous: there is one 10m and one 7m gap) of 255 m
averaging 0.27% V2O5.
2
Trench 2 (18PPT2) located approximately 1.1 km south east of Trench 1 also on the eastern
limb subcrop (see Figure 1) returned the following results:
Length
(m) V2O5 Grade
29 0.45%
offset in trench
130 0.48%
159
These Trench 2 intervals are also contained within a broader mineralized envelope: in Trench 2
there were cumulative sample intervals (not continu ous: there is one offset gap and one 10m
gap) of 218 m averaging 0.43% V2O5.
The beds in Trenches 1 and 2 are dipping approximat ely 45-50 ˚ to the south-west and the
sampled intervals will have to be adjusted to true width. The trenches appear to be oriented
approximately parallel to the dip direction (perpen dicular to strike). While it is very preliminary
true widths of the mineralized beds may be in the r ange of approximately 70% of the measured
lengths.
Continuous rock chip sampling (sample line 18MST1 ) was completed along a road cut on
the John Hart Highway approximately 3.5 km south east of Trench 2 (approximately 4.6 km
south east of Trench 1) and returned the following results:
Length
(m) V2O5 Grade
50 0.39%
Including:
20 0.45%
This sampling is in the western limb of the synclin e with near vertically dipping beds so these
intervals are believed to be close to true widths.
3
Figure 1
4
Descriptions and sample summaries of the trenches are below:
Trench# Zone Description Length
(m)
No. of
Samples
Average
Sample
length (m)
Comments
18PPT1 West Limb
Outcrop of laminated and fissile
carbonaceous Black Shale, locally
interbedded with carbonaceous Grey
Siltstone.
255 84 3 Assays Received
18PPT2 West Limb
Outcrop of laminated, fiss ile, and sooty
Black Shale with minor carbonaceous Grey
Siltstone
218 74 3 Assays Received
18PPT3 East Limb Outcrop of d ark g rey, semi-massive grey
Siltsone with minor Black Shale 73 22 3 Assays Pending
18PPT4 East Limb Outcrop and Talus of Black Shale and Grey
Siltstone 33 9 4 Assays Pending
18PPT5 West Limb Outcrop/Subcrop and Talus of Black Shale
with minor Grey Siltstone 69 23 3 Assays Pending
18MST1 West Limb Chip Sampling of Black Shale outcrop at
Road Cut 65 13 5 Assays Received
Other sampling in this Phase 2 work included:
• 89 rock grab samples collected (assays pending)
• 535 soil samples collected across 9 lines at a 10m spacing: 6 across the west limb and 3
across the east limb (assays pending).
Craig Roberts, P .Eng., President and CEO of Ethos stated:
“We are very pleased and excited with these initial trench and chip sampling
results. In Trenches 1 and 2 the grades are compar able with other development
stage black shale hosted vanadium projects and the widths are impressive.
These trenches are located 1.1 km apart and with th e mineralization hosted in
dipping bedded stratigraphy the drill target in thi s area appears relatively well
defined with a significant target envelope. The chi p sampling on the highway cut
is approximately 3.5 km south east of Trench 2 indi cating the potential to find
mineralization over a substantial strike distance. In total there is approximately 20
km of subcrop strike distance to explore at Pine Pa ss (approximately 10 km on
each syncline limb).
Moving forward we will proceed with work to submit permit applications for an
initial drill program to commence in the spring of 2019, as well as for additional
trenching and possibly some small test pits. We are also evaluating commencing
an initial metallurgical testwork program on sample material taken from the
trenches starting in the next several weeks.
With current net cash of approximately $Cdn 5.8 mil lion Ethos is well positioned
to execute on these next phases of work.
As previously noted the advantageous location of th e Pine Pass vanadium
project cannot be over stated. Pine Pass is locate d on a paved highway 70 km
5
from Chetwynd, British Columbia (population 2,600). The property has been
partially logged, and there is good access via logg ing roads from the highway.
There are power, natural gas, and railway lines alo ng this corridor. There is
significant mining and other resource activity in t his region of British Columbia,
providing excellent support infrastructure, mining suppliers and skilled workers”.
QA/QC, Qualified Person, and Contact
All samples were delivered to ALS Chemex in Kamloop s and/or North Vancouver, British
Columbia for analysis of select elements by ICP-MS analysis using 4 acid-digestion. Quality
control entailed insertion of company standards, bl anks, and duplicates into the trench sample
stream. In addition, ALS Chemex routinely inserted blanks and standards into the sample
stream at the assay laboratory. All reported standa rd and blank assay values, as well as
duplicates were within an acceptable margin of error.
Work at Pine Pass is being supervised by Jo Price, M.Sc., MBA, P .Geo, a consultant to the
Company. She is a Qualified Person as defined under National Instrument 43-101 and has read
and approved this release.
For additional information please contact Craig Roberts at 604-682-4750 or view the Company’s
website, www.ethosgold.com .
Ethos Gold Corp.
Per: " Craig Roberts "
Craig Roberts P .Eng., Interim President & CEO
Forward-Looking Statement Cautions:
This press release contains certain "forward-lookin g statements" within the meaning of Canadian
securities legislation, including statements regard ing future exploration plans and development potent ial
on the Pine Pass project. Although the Company beli eves that such statements are reasonable, it can
give no assurance that such expectations will prove to be correct. Forward-looking statements are
statements that are not historical facts; they are generally, but not always, identified by the words
"expects," "plans," "anticipates," "believes," "int ends," "estimates," "projects," "aims," "potential, " "goal,"
"objective," "prospective," and similar expressions , or that events or conditions "will," "would," "ma y,"
"can," "could" or "should" occur, or are those stat ements, which, by their nature, refer to future eve nts.
The Company cautions that Forward-looking statement s are based on the beliefs, estimates and opinions
of the Company's management on the date the stateme nts are made and they involve a number of risks
and uncertainties. Consequently, there can be no as surances that such statements will prove to be
accurate and actual results and future events could differ materially from those anticipated in such
statements. Except to the extent required by applic able securities laws and the policies of the TSX
Venture Exchange, the Company undertakes no obligat ion to update these forward-looking statements if
management's beliefs, estimates or opinions, or oth er factors, should change. Factors that could cause
future results to differ materially from those anti cipated in these forward-looking statements include the
risk of accidents and other risks associated with m ineral exploration operations, the risk that the Co mpany
6
will encounter unanticipated geological factors, or the possibility that the Company may not be able t o
secure permitting and other governmental clearances , necessary to carry out the Company's exploration
plans, and the risk of political uncertainties and regulatory or legal changes in the jurisdictions wh ere the
Company carries on its business that might interfer e with the Company's business and prospects. The
reader is urged to refer to the Company's reports, publicly available through the Canadian Securities
Administrators' System for Electronic Document Anal ysis and Retrieval (SEDAR) at www.sedar.com for a
more complete discussion of such risk factors and t heir potential effects
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in
the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of
this release.