Patriot Maintains Exploration & Development Momentum at Corvette with Extensive Summer-Fall Workplan

Corporate Updates

Patriot Battery Metals Inc.

Suite 700 - 838 W. Hastings Street, Vancouver, BC, Canada, V6C 0A6

www.patriotbatterymetals.com TSX: PMET / ASX: PMT / OTC: PMETF / FSE: R9GA

Patriot Maintains Exploration & Development Momentum at

Corvette with Extensive Summer-Fall Workplan

June 26, 2024 – Vancouver, BC, Canada June 27, 2024 – Sydney, Australia

Highlights

• 2024 Summer-Fall exploration program commences at Corvette:

o Two exploration rigs operating at the CV13 Pegmatite, primarily undertaking step-

out drilling targeting extensions of the recently discovered high-grade Vega Zone.

o Two drill rigs collecting geotechnical and hydrogeological information to support

advanced development and economic studies through feasibility.

o Surface exploration activities underway, including detailed mapping at CV5 and

CV13, channel sampling, and prospecting of prospective trends.

• Additional rigs to be added starting in early July, focused on continued infill and

geomechanical drilling at the CV5 Pegmatite.

• Successful commissioning of a 100% -owned exploration camp proximal to the Property

and all-season road access from the camp to the CV5 Pegmatite, reducing travel time and

significantly increasing exploration efficiency and cost effectiveness.

o Building on the successful relationship with the Cree, the new camp facilities have

adopted the name Shaakichiuwaanaan Camp.

• Environmental baseline data collection is being undertaken in partnership with First

Nations, representing a key milestone in progressing the Environmental and Social Impact

Assessment (ESIA), due for submission in September 2025.

Patriot Battery Metals Inc. (the “Company” or “Patriot”) (TSX: PMET) (ASX: PMT)

(OTCQX: PMETF) (FSE: R9GA) is pleased to provide an update on the 2024 Summer -Fall

exploration and development programs at its 100%-owned Corvette Property (the “Property” or

“Project”) located in the Eeyou Istchee James Bay region of Quebec. The Project, which hosts the

CV5 Spodumene Pegmatite with a maiden M ineral Resource Estimate (“MRE”) of 109.2 Mt at

1.42% Li 2O Inferred1, is situated approximately 13.5 km south of the regional and all ‑weather

Trans-Taiga Road and powerline infrastructure.

This multi -pronged and multi drill rig field work program has been designed to support the

continued exploration and development of the Corvette Project . Work is anticipated to include

step-out drilling at the recently discovered Vega Zone at the CV13 Pegmatite, infill drilling at the

CV5 Pegmatite, as well as surface mapping and prospecting.

Additionally, significant environmental baseline data collection will continue to build on previous

years in support of an Environmental and Social Impact Assessment (ESIA ) submission for the

Project, which is on schedule for September 2025

Summer-Fall Exploration Program Underway

CV13 Pegmatite (Vega Zone)

The 2024 Summer-Fall exploration program has commenced with two drill rigs now testing the

recently discovered Vega Zone at the CV13 Pegmatite (see news release dated June 10, 2024 ).

The objective of the program is to further expand and delineate the recently discovered high -

grade mineralization at Vega . Approximately 10,000 m of drilling is under consideration this

summer-fall targetting the CV13 Spodumene Pegmatite and immediate corridor towards the CV5

Spodumene Pegmatite.

Because the Vega Zone was discovered in the final days of the 2024 winter program, only limited

follow-up drilling has been completed. Results to date include 34.4 m at 2.90% Li2O (CV24-470),

and 33.4 m at 2.40% Li 2O, including 1.7 m at 7.01% Li 2O ( CV24-507). The high -grade

mineralization is relatively flat -lying to shallow dipping and remains open in multiple directions,

with the results of multiple step-out holes remaining to be reported.

CV5 Pegmatite

Infill drilling at the CV5 Pegmatite is scheduled to resume in early July and will continue through

late September. Several drill rigs will be deployed to support an increase in MRE confidence from

the Inferred category to the Indicated category . This drilling will target Inferred blocks as

categorized in the pending MRE update, with the ultimate objective of delineating a coherent body

of Indicated Mineral Resource blocks to underpin a Feasibility Study scheduled for the second half

of 2025.

The Company anticipates adding an additional rig in August to undertake geomechanical drilling at

CV5 to support advanced open-pit design . These drill holes will be completed at various

orientations proximal to CV5 and the conceptual pit, and will target specific host rock types and

structure, with optical and acoustics televiewer data to also be collected.

Additionally, several fences of drilling are planned across the conceptual open-pit to test for

mineralized pegmatite where waste rock has been modelled due to a lack of drill data.

In addition to the resource drilling, a n expansive hydrogeological and geotechnical drill program

commenced on site in early June. The program includes approximately 5 6 drill holes of various

size (NQ, HQ, PQ, and 6 inch), design, and depth.

The geotechnical drilling will test rock and overburden characteristics at various proposed

infrastructure locations to support the development of the Project. This includes areas for the

proposed mine camp, waste rock piles, process plant, and other ancillary infrastructure.

The hydrogeological drill program will include the installation of monitoring wells and down-hole

equipment, as well as packer testing (Figure 1) within the conceptual open-pit and other proposed

infrastructure locations. Additionally, three large diameter drill holes will be completed (two 6

inch and one PQ) in the CV5 area to conduct long-duration pumping tests for operational water

supply and pit dewatering design. The data will further refine the preliminary hydrogeological

model for CV5 developed in 2023.

Figure 1: Site of drill hole CV24 -537, situated north of CV5, completed for geotechnical purposes and

monitoring well installation.

An updated MRE for the Corvette Project, incorporating all drilling through April 2024, is

scheduled for release in August 2024. This update will include both the CV5 and CV13 spodumene

pegmatites underpinning a consolidated Mineral Resource statement for the Corvette Project.

Surface exploration began in late May and will include detailed geological mapping at CV5 and

CV13, in addition to channel sampling of pegmatite outcrop. Channel samples may effectively

approximate a “horizontal drill hole”, thereby further constraining the geological model at surface

with robust sample data.

Baseline Environmental Data Collection to Support the ESIA

In order to facilitate the completion of the Environment and Social Impact Assessment (ESIA), due

for submission to the regulators in September 2025, the Company is continuing baseline

environmental data gathering at the Corvette Project throughout the year (Figure 2).

Baseline environment data collection is being completed in partnership with local First Nations.

Key areas of focus include vegetation, wildlife, and fish. Field studies are designed to meet the

Project guidelines issued by the government of Quebec in April 2024. R eports on the field work

will be completed in June 2025 and will inform the placement of Project infrastructure, the

assessment of potential impacts, and the development of environmental mitigation measures.

Figure 2: Gantt chart of Environmental baseline work completed to date and planned to support the

submission of the ESIA.

Shaakichiuwaanaan Exploration Camp Phase One Completed

The Company has completed the first phase of its 100% -owned exploration camp at Corvette,

with a capacity of 80 persons , which supported the majority of its activities over the recently

completed winter program (Figure 3). This camp is currently being expanded to facilitate

accommodation for up to 150 persons and is anticipated to be operational later in the year.

Additional utilities infrastructure is being installed over the coming months to ensure that this

camp can be the sole operational cent re for all activities at the Corvette Project. The camp area

includes provision for accommodation, office facilities, a workshop for contractors , and a core

processing building inclusive of on-site core storage.

The new Shaakichiuwaanaan Camp is located closer to site than the previously utilized privately

owned camp (Mirage Outfitters Camp), significantly reducing exploration costs and ensuring year-

round accommodation for the Patriot team to ensure seamless operations at the Corvette Project.

Figure 3: Shaakichiuwaanaan Camp at KM-270 of the Trans-Taiga Road. Trans-Taiga Road (upper left) and

the Company’s all-season road (right).

In response to a request from the tallyman and the community of Chisasibi, Patriot is pleased to

name the camp Shaakichiuwaanaan. The name means ‘climbing a hill, or mountain’, three of which

are prevalent in the Project area (Figure 4).

Figure 4: Photo showing the three mountains/hills inspiring the camp’s name (Shaakichiuwaanaan)

For reference, a ll of these Project areas, including the camp, drilling (inclusive of CV13 and all

other known surface spodumene outcrops at Corvette), and planned infrastructure development

areas, all currently fall within trapline CH39 on the traditional territory of the Cree First Nation

of Chisasibi only.

On June 1, the Patriot Board, Executives, site workers, and members of the Cree community

shared a special celebration including building a sabtuan (long teepee) and sharing traditional food

at the Shaakichiuwaanaan Camp (Figure 5). The elders and members of the tallyman’s family

traveled by helicopter with Patriot team members to offer tobacco at the lake located near CV5.

Figure 5: Celebration ceremony at Camp Shaakichiuwaanaan in partnership with the local Cree Community

of Chisasibi.

All-Season Road Operational

The Company is pleased to announce that the CV5 Pegmatite is now road accessible year-

round through the successful connection of CV5 to Shaakichiuwaanaan Camp at KM-270 of the

Trans-Taiga Road. The Company continues to undertake maintenance ( and some improvement

works) on the ~ 20 km all-season gravel road, which now allows for access through to the

southwest side of the CV5 Deposit.

The construction of the all -season road to CV5 is a significant milestone for the Company ,

especially when coupled with Shaakichiuwaanaan Camp. This infrastructure has, and will continue

to, facilitate significant cost savings in exploration by reducing dependency on helicopters for the

movement of personnel , equipment , and logistical support , as well as dramatically reducing

distances to travel from staging to site (Shaakichiuwaanaan Camp versus Mirage Lodge).

The realization of these cost savings has already had a significant positive impact on the exploration

cost (measured by a $/m metric) since the camp became operational in January 2024.

Figure 6: The Company’s all -season road (~2 0 km in length) now operational and connecting the CV5

Deposit directly to KM-270 of the all-season Trans-Taiga Road and therefore the provincial road network.

About the CV Lithium Trend

The CV Lithium Trend is an emerging spodumene pegmatite district discovered by the Company

in 2017 and is interpreted to span more than 50 kilometres across the Corvette Property. The

core area includes the approximate 4.6 km long CV5 Spodumene Pegmatite, which hosts a maiden

Mineral Resource estimate of 109.2 Mt at 1.42% Li2O Inferred1.

To date, eight (8) distinct clusters of lithium pegmatite have been discovered across the Corvette

Property – CV4, CV5, CV8, CV9, CV10, CV12, CV13, and the recently discovered CV14. Given

the proximity of some pegmatite outcrops to each other, as well as t he shallow till cover in the

area, it is probable that some of the outcrops may reflect a discontinuous surface exposure of a

single, larger pegmatite “outcrop” subsurface.

Qualified/Competent Person

The information in this news release that relates to exploration results for the Corvette Property

is based on, and fairly represents, information compiled by Mr. Darren L. Smith, M.Sc., P.Geo.,

who is a Qualified Person as defined by National Instrument 43 -101 – Standards of Disclosure for

Mineral Projects, and member in good standing with the Ordre des Géologues du Québec (Geologist

Permit number 01968), and with the Association of Professional Engineers and Geoscientists of

Alberta (member number 87868). Mr. Smith has reviewed and approved the technical information

in this news release.

Mr. Smith is Vice President of Exploration for Patriot Battery Metals Inc. and holds common shares

and options in the Company.

Mr. Smith has sufficient experience, which is relevant to the style of mineralization, type of deposit

under consideration, and to the activities being undertaken to qualify as a Competent Person as

described by the Australasian Code for Reporting of Exploration Results, Mineral Resources and

Ore Reserves (the JORC Code). Mr. Smith consents to the inclusion in this news release of the

matters based on his information in the form and context in which it appears.

About Patriot Battery Metals Inc.

Patriot Battery Metals Inc. is a hard -rock lithium exploration company focused on advancing its

district-scale 100% owned Corvette Property located in the Eeyou Istchee James Bay region of

Quebec, Canada, and proximal to regional road and powerline infrast ructure. The Corvette

Property hosts the CV5 Spodumene Pegmatite with a maiden M ineral Resource Estimate of

109.2 Mt at 1.42% Li 2O Inferred1 and ranks as the largest lithium pegmatite resource in the

Americas based on contained lithium carbonate equivalent (LCE), and one of the top 10 largest

lithium pegmatite resources in the world. Additionally, the Corvette Property hosts multiple other

spodumene pegmatite clusters that remain to be drill tested, as well as more than 20 km of

prospective trend that remains to be assessed.

1 The CV5 Mineral Resource Estimate (109.2 Mt at 1.42% Li2O and 160 ppm Ta2O5 Inferred) is reported at a cut-

off grade of 0.40% Li2O with an Effective Date of June 25, 2023 (through drill hole CV23-190). Mineral Resources

are not Mineral Reserves as they do not have demonstrated economic viability. Largest lithium pegmatite resource

in the Americas based on contained LCE.

For further information, please contact us at [email protected] or by calling +1 (604)

279-8709, or visit www.patriotbatterymetals.com. Please also refer to the Company’s continuous

disclosure filings, available under its profile at www.sedarplus.ca and www.asx.com.au, for available

exploration data.

This news release has been approved by the Board of Directors.

“KEN BRINSDEN”

Kenneth Brinsden, President, CEO, & Managing Director

Brad Seward

Vice President, Investor Relations

T: +61 400 199 471

E: [email protected]

Olivier Caza-Lapointe

Head, Investor Relations – North America

T: +1 (514) 913-5264

E: [email protected]

Disclaimer for Forward-looking Information