Cornerstone Metals Provides Update on its Carlin Vanadium Project

Corporate Updates

Cornerstone Metals Provides Update on its Carlin Vanadium Project  

July 10, 2018 ‐ Vancouver, British Columbia  – Cornerstone Metals Inc. (TSX‐V: CCC) (OTCQB: CCCCF) (FSE: 

1PY) (“Cornerstone” or the “ Company”) is pleased to provide a project update on drilling plans, prel iminary 

engineering, metallurgy and environmental studies on its Carlin Vanadium Project, south of Carlin, Nevada. 

The  Company  has  secured  a  drill  contractor  to  conduct  an  infill  and  deposit  expansion  reverse  circulation 

(RC) drill program under its current BLM permit. The program wi ll commence in the first week of August and 

consist  of  approximately  40‐50  shallow  vertical  and  angled  RC  drill  holes.  Of  those,  three  holes  will  twin 

historic holes to provide additi onal comparisons for grades. Fi fteen holes will be conducted to infill parts of 

the  deposit  to  tight  40  metre  centres.  In  addition,  22‐32  holes  will  be  drilled  selectively  on  edges  of  the 

deposit  with  the  objective  of  expanding  the  size  of  the  deposit.  Upon  completion  of  the  drill  program,  a 

resource estimate will be prepared, based on all historic and Cornerstone drilling on the property.  

Company  CEO,  Paul  Cowley,  P.Geo.  conducted  a  site  visit  in  the  first  week  of  July  with  the  Company 

construction  advisor  and  the  Company’s  senior  mining  advisor  and  d i r e c t o r  t o  i d e n t i f y  a n d  r a n k  m u l t i p l e  

options  for  the  plant,  waste  rock  and  tailings  facilities  sites  on  the  property  and  to  review  infrastructure, 

including road, rail and power access. The site location, and s urrounding and onsite infrastructure are strong 

aspects of the project.  

The property has access from both the south and north; each rou te within three and five miles from paved 

highway. The town of Carlin, where rail is located, is 6 and 13  miles away via these two routes. Rail allows 

access for concentrates to market s in the US, Canada and intern ationally via ocean transport. There are two 

high voltage power lines within a 5 to 15 mile radius of the site.  

Two  of  the  potential  plant  site  locations  inspected  have  bedrock  near  to  surface  which  will  minimize  the 

concrete required for foundations. There are locations on site  for potential tailings and waste rock including 

the designed open pits which would be located in a line that po tentially could be backfilled with waste rock 

or tailings progressively should mining occur. 

The deposit host rock was examined and appears to be low to mod erate in hardness and heavily fractured 

which will require less energy to drill, blast, crush and grind. Rock crushing and grinding characteristics will be 

tested in an independent laboratory this month. 

Metallurgical  test  work  continues  at  Sherritt  Technologies  to  optimize  various  parameters  of  temperature, 

pressure  and  grind  size  with  the  aim  of  developing  a  conceptual  flowsheet.  The  third  round  of  testing, 

previously reported (news release dated June 20, 2018), achieved vanadium extraction levels of 95.5%.   

EM  Strategies,  Inc.  of  Reno,  Nevada  commenced  baseline  studies  on  the  project  in  May  2018  and  will 

continue  through  the  summer  and  fall.  This  baseline  work  includes  botany,  wildlife  and  cultural  studies, 

which will form the components to an application for the next level and stage of permitting. 

Vanadium prices for 98% flake V2O5 have steadily risen from und er US$3.00/lb less than 3 years ago. This 

week prices reached $17.50/lb.   

The  Carlin  Vanadium  deposit  is  considered  one  of  the  largest,  highest  grade  primary  vanadium  deposits  in 

North  America  (USGS  Professional  Paper  1802  Critical  Mineral  Resources  of  the  United  States—Economic 

and Environmental Geology and Prospects for Future Supply dated December 18, 2017).  

Vanadium’s Growing Importance for Steel Manufacturing and the Energy Sector 

Vanadium  is  growing  in  importanc e  for  key  industrial  manufactur ing  sectors  most  notably  steel  and 

renewable  energy.  Today,  more  than  85  percent  of  the  world’s  vanadium  is  used  in  steel  manufacturing 

applications.  Its  importance  to  the  energy  sector  is  also  growing  rapidly  with  more  than  10  percent  of 

vanadium production used in energy storage where its substantia l cost and performance benefits make it an 

alternative choice to lithium ion in several areas.  

About Cornerstone Metals Inc. 

Cornerstone  Metals  has  an  option  to  earn  a  100%  interest  in  the  Carlin  Vanadium  Project,  located  in  Elko 

County 22km by road (13 miles) from the town of Carlin, Nevada.  The project is comprised of 72 contiguous 

unpatented mineral claims totaling 461 hectares (1,140 acres).  The Carlin Vanadium Project hosts the Carlin 

Vanadium Deposit which is flat to shallow dipping and at shallo w depths, 0‐60m (0‐200 ft) below surface. 

ON BEHALF OF CORNERSTONE METALS INC.  

per: "Paul Cowley" 

CEO & President 

(604) 340‐7711 

[email protected] 

www.cornerstonemetals.ca 

Technical disclosure in this news release has been reviewed and  approved by Paul Cowley, P.Geo., a Qualified 

Person as defined by National Instrument 43‐101, and President and CEO of the Company. 

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of 

the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. 

Forward‐looking information  

Certain statements in this news release constitute "forward‐loo king" statements. These statements relate to 

future events or the Company's f uture performance and include t he Company’s ability to meet the conditions 

required to exercise in full its option to acquire the Carlin V anadium project and with respect to current and 

planned drill programs, the results of exploration programs, me tallurgical test work, and changes in mineral 

resources. All such statements  involve substantial known and un known risks, uncertainties and other factors 

which  may  cause  the  actual  results  to  vary  from  those  expressed   or  implied  by  such  forward‐looking 

statements.  Forward‐looking  statements  involve  significant  risks  and  uncertainties,  they  should  not  be  read 

as  guarantees  of  future  performance  or  results,  and  they  will  n ot  necessarily  be  accurate  indications  of 

whether or not such results will be achieved. Actual results co uld differ materially from those anticipated due 

to a number of factors and risks. Although the forward‐looking  statements contained in this news release are 

based upon what management of the Company believes are reasonab le assumptions on the date of this news 

release, the Company cannot assure investors that actual results will be consistent with these forward‐looking 

statements. The forward‐looking statements contained in this pr ess release are made as of the date hereof 

and  the  Company  disclaims  any  intention  or  obligation  to  update  or  revise  any  forward‐looking  statements 

whether  as  a  result  of  new  information,  future  events  or  otherwise,  except  as  required  under  applicable 

securities regulations.