Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

PGLD.V ·

P2 Gold Gabbs Project Update

Corporate Updates

P2 Gold Gabbs Project Update

VANCOUVER, BC

,

Nov. 10, 2025

/CNW/ -

P2 Gold Inc.

("P2" or the "Company") (TSXV: PGLD)

(OTCQB: PGLDF) provides an update on activities at its wholly-owned gold-copper Gabbs Project

located on the Walker-Lane Trend in

Nevada

.

Expansion and Exploration Drilling

A reverse circulation (RC) drill rig was mobilized to site on

October 22, 2025

and expansion and infill

drilling is underway. To date, 12 RC holes have been completed at the Sullivan Zone with 24 holes

planned totaling 4,900 meters. When drilling is complete at

Sullivan

, the RC drill will be moved to the

Lucky Strike Zone to complete a 47-hole, 10,000-meter infill and expansion drill program. Drill

results will be reported as received with initial results expected before year-end.

Geotechnical and Metallurgical Drilling

A diamond drill rig is currently mobilizing to site. The drill rig is being used to drill geotechnical drill

holes to support the feasibility study and to provide metallurgical samples for feasibility metallurgical

testing. The diamond drill program is expected to consist of 17 holes totaling 3,500 meters. The

initial holes will focus on providing additional metallurgical samples for column leach tests and then

pit slope stability for the proposed

Sullivan

and Lucky Strike Zone open pits.

Feasibility-Level Studies

The Company has begun the process of awarding contracts in support of the Gabbs Project

Feasibility Study and mining plan of operations. Contracts awarded to date include:

Barr Engineering Co for a feasibility level pit slope stability study for the proposed

Sullivan

and

Lucky Strike open pits

Kautz Environmental Consultants, Inc. for the completion of a cultural inventory of the proposed

Gabbs

mine site

Aqua Hydrogeologic Consulting for a hydrogeologic model in the area around the proposed

open pits and process water rights

Western Biological for an expanded biological survey

Kappas Cassiday for optimized heap leach and mill processing metallurgical studies

Welsh Hagen for leach pad and process facility foundation geotechnical studies

These studies and the ongoing drill program are expected to be completed in the second quarter of

2026. At the end of drilling, an updated Mineral Resource estimate will be prepared from which an

optimized mine plan will be developed. The information from the various field studies will be used in

the design of the process and ancillary facilities. Capital and operating costs will be estimated and

used to form the basis of the economic analysis of the Feasibility Study.

Qualified Person

Ken McNaughton

, M.A.Sc., P.Eng., Chief Exploration Officer, P2 Gold, is the Qualified Person, as

defined by National Instrument 43-101, responsible for the Gabbs Project. Mr. McNaughton has

reviewed, verified, and approved the scientific and technical information in this news release.

About P2 Gold Inc.

P2 Gold is a mineral exploration and development company focused on advancing its gold-copper

Gabbs Project on the Walker Lane Trend in

Nevada

, where work to support a feasibility study is

underway. A positive preliminary economic assessment has outlined a long-life, mid-size mine at

Gabbs

with annual average production of 109,000 ounces gold, 15,000 tonnes copper over a 14.2-

year mine life. The Gabbs Project has excellent infrastructure with access via paved Hwy 361, and

power and water on site. Additional metallurgical work is being planned, and a water permit is

expected in the fourth quarter of this year. All zones on the property remain open and additional

exploration targets, near surface and at depth, are drill ready.

Neither the TSX Venture Exchange (the "Exchange") nor its Regulation Services Provider (as that

term is defined in the policies of the Exchange) accepts responsibility for the adequacy or accuracy

of this release.

Forward Looking Information

This press release contains "forward-looking information" within the meaning of applicable securities

laws that is intended to be covered by the safe harbours created by those laws. "Forward-looking

information" includes statements that use forward-looking terminology such as "may", "will", "expect",

"anticipate", "believe", "continue", "potential" or the negative thereof or other variations thereof or

comparable terminology. Such forward-looking information includes, without limitation, information

with respect to the Company's expectations, strategies and plans for the Gabbs Project including the

Company's planned expenditures and exploration activities.

Forward-looking information is not a guarantee of future performance and is based upon a number

of estimates and assumptions of management at the date the statements are made as well as the

other assumptions disclosed in this news release. Furthermore, such forward-looking information

involves a variety of known and unknown risks, uncertainties and other factors which may cause the

actual plans, intentions, activities, results, performance or achievements of the Company to be

materially different from any future plans, intentions, activities, results, performance or achievements

expressed or implied by such forward-looking information and risks associated with mineral

exploration, including the risk that actual results and timing of exploration and development will be

different from those expected by management. See "Risk Factors" in the Company's annual

information form for the year ended

December 31, 2024

, dated

March 21, 2025

filed on SEDAR+ at

www.sedarplus.com

for a discussion of these risks.

The Company cautions that there can be no assurance that forward-looking information will prove to

be accurate, as actual results and future events could differ materially from those anticipated in such

information. Accordingly, investors should not place undue reliance on forward-looking information.

Except as required by law, the Company does not assume any obligation to release publicly any

revisions to forward-looking information contained in this press release to reflect events or

circumstances after the date hereof.

SOURCE

P2 Gold Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/November2025/10/c1771.html

%SEDAR: 00045664E

For further information:

For further information, please contact: Joseph Ovsenek, President &

CEO, (778) 731-1055; Michelle Romero, Executive Vice President, (778) 731-1060; P2 Gold Inc.,

Suite 789, 999 West Hastings Street, Vancouver, BC, V6C 2W2, [email protected], (SEDAR filings:

P2 Gold Inc.)

CO: P2 Gold Inc.

CNW 03:30e 10-NOV-25