Orvana Reports Q3 FY2024 Production and Exploration Update from Orovalle, Spain

Exploration Programs

1

For Immediate Release TSX:ORV

Date: July 16, 2024 #08-2024

ORVANA REPORTS Q3 FY2024 PRODUCTION

AND EXPLORATION UPDATE FROM OROVALLE, SPAIN

TORONTO, ONTARIO, July 16 , 202 4 - Orvana Minerals Corp. (TSX:ORV) (the “Company” or

“Orvana”) is pleased to report production and exploration updates for the third quarter of fiscal year 2024

(“Q3 FY2024) ending June 30, 2024 and revised guidance for production for the year ended September

30, 2024, from Orovalle, Spain.

Highlights

• Q3 FY2024 Production: 13,078 Gold Equivalent Ounces, 29% higher than the previous quarter.

• Outlook: Production guidance for the fiscal year ended September 30, 2024 (“FY2024”) is updated

from that disclosed in the Company’s Management’s Discussion and Analysis for the three and six

months ended March 31, 2024.

FY2024 Production Previous Guidance Revised Guidance

Gold (oz) 41,000 - 45,000 37,000 – 39,000

Copper (million lbs) 3.3 – 3.7 3.7 – 3.9

• Q3 FY2024 Exploration: 2,835 m of Infill and Brownfield drilling, with key intercepts in Boinas South

and Area 208 as follows:

­ DDH 24SB200: 14.00 m @ 11.82 g/t Au

­ DDH 24A21927: 13.20 m @ 4.04 g/t Au

­ DDH 24A21929: 7.25 m @ 10.32 g/t Au

­ DDH 24A21935: 4.40 m @ 5.29 g/t Au

­ DDH 24A21936: 11.70 m @ 4.94 g/t Au

Juan Gavidia, CEO of Orvana stated: “We are pleased with the operational recovery at Orovalle after a

challenging first half of the year. We have achieved a quarterly production of more than 150,000 tonnes,

improving at the same time gold grade and recovery. We believe that Orovalle can continue increasing

production levels, at the same time that we maintain our focus on safe and efficient operations”.

2

Q3 FY2024 Production Results

­ The mill processed approximately 150,843 tonnes, 11% higher than the prior quarter.

­ Gold production was 39% higher than the prior quarter due to higher tonnage milled, grade

and recovery.

­ Copper production was 10% lower than the prior quarter due to lower grade and recovery,

partially offset by higher tonnage milled.

Q3 FY2024 Q2 FY2024 Q3 FY2023 YTD Q3 FY2024 FY 2024

Revised Guidance

Ore milled (tonnes) 150,843 136,371 163,996 417,481

Gold equivalent (oz)(1) 13,078 10,101 13,398 32,729

Gold

Grade (g/t) 2.37 1.97 2.41 2.15

Recovery (%) 94.1 90.0 90.8 92.1

Production (oz) 10,832 7,775 11,522 26,600 37,000 – 39,000

Copper

Grade (%) 0.39 0.47 0.29 0.39

Recovery (%) 76.3 78.0 76.6 76.9

Production (K lbs) 986 1,095 801 2,783 3,700 - 3,900

Silver

Grade (g/t) 8.30 8.17 6.84 7.78

Recovery (%) 76.7 74.6 72.0 74.7

Production (oz) 30,872 26,728 25,965 77,994

(1) Gold Equivalent Ounces (“GEO”) were calculated using the following average market prices:

Q3 FY2024: $2,337.99/oz Au, $28.86/oz Ag, $4.42/lb Cu

Q2 FY2024: $2,071.76/oz Au, $23.36/oz Ag, $3.83/lb Cu

Q3 FY2023: $1,977.33/oz Au, $24.20/oz Ag, $3.85/lb Cu

GEO is a Non -GAAP Financial Performance Measure. For further information and detailed

reconciliations, please see the “Non-GAAP Financial Performance Measures” section of the Company’s

Q2 FY2024 MD&A.

Exploration Update – Orovalle

Drilled Meters – Q3 FY2024 Infill Brownfield TOTAL

El Valle Boinás

Area 208 (A2) 1,722 - 1,722

Boinás South (SB) 35 1,004 1,039

Boinás East (BE) - 74 74

TOTAL 1,757 1,078 2,835

3

Area 208:

1,722 m of infill drilling were executed in Area 208 (oxides) targeting to convert inferred resources into

measured and indicated. Area 208 is formed by several parallel oxide structures into limestone with

variable width affected by fault displacements and dipping to the east. Mineralization is open to the east.

Infill drilling program will continue during the fourth quarter.

Figure 1: Section A-A’ Area 208

Boinás South:

1,039 m were drilled continuing with the mineral definition between Boinas South and Black Skarn to add

new resources. Eight brownfield drill holes were executed intersecting calcic garnet skarn with narrow

mineralized bands in deeper levels and to the north. Dr illing program will continue during the first part of

the fourth quarter to complete the mineral definition.

Quality Control

Infill and brownfield drill holes samples were analyzed in Orovalle's Laboratory.

Sample preparation was carried out at the El Valle facility. All diamond core samples have been prepared

using the following procedure, once split:

- The core samples are dried at a temperature of 105ºC and then crushed through a jaw crusher to

95%<6 mm.

4

- The coarse-crushed sample is further reduced to 95%<425 microns using an LM5 bowl-and-puck

pulverizer.

- An Essa rotary splitter is used to take a 450 g to 550 g sub-sample of each split for pulverizing.

- The remaining reject portion is bagged and stored.

- The sample is reduced to a nominal - 200 mesh using an LM2 bowl -and-puck pulverizer. 140 g

sub-samples are split using a special vertical -sided scoop to cut channels through the sample

which has been spread into a pancake on a sampling mat.

- Samples are then sent to the laboratory for gold and base metal analysis.

- Leftover pulp is bagged and stored.

After sample preparation, 30g samples are analyzed for Au by fire assay with an atomic absorption

spectroscopy (AAS) finish and two-gram samples for Ag, As, Bi, Cu, Hg, Pb, Sb, Se, and Zn by ICP-optical

emission spectroscopy (ICP-OES) after an aqua regia digestion.

The reported work has been completed using industry standard procedures, including a quality

assurance/quality control (“QA/QC”) program consisting of the insertion of certified reference material,

blanks and duplicates samples into the sample stream.

The exploration update was prepared under the supervision of Guadalupe Collar Menéndez, a qualified

person for the purposes of NI 43-101 and an employee of Orovalle Minerals S.L., a subsidiary of Orvana.

Financial Performance:

Q3 FY2024 financial highlights will be released with the third quarter financials, expected mid- August,

2024.

ABOUT ORVANA – Orvana is a multi -mine gold-copper-silver company. Orvana’s assets consist of the

producing El Valle and Carlés gold -copper-silver mines in northern Spain, the Don Mario gold- silver

property in Bolivia, currently in care and maintenance, and the Taguas property located in Argentina.

Additional information is available at Orvana’s website (www.orvana.com).

For further information please contact:

Nuria Menéndez

Chief Financial Officer

E: [email protected]

Cautionary Statements – Forward-Looking Information

Certain statements in this presentation constitute forward -looking statements or forward- looking information within the meaning of

applicable securities laws (“forward-looking statements”). Any statements that express or involve discussions with respect to

predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but

not always, using words or phrases such as “believes”, “expects”, “plans”, “estimates” or “intends” or stating that certain actions,

events or results “may”, “could”, “would”, “might”, “will”, “are projected to” or “confident of” be taken or achieved) are not statements

of historical fact, but are forward-looking statements.

The forward-looking statements herein relate to, among other things, Orvana’s ability to achieve improvement in free cash flow; the

ability to maintain expected mining rates and expected throughput rates at El Valle Plant; the potential to extend the mine life of El

Valle and Don Mario beyond their current life-of- mine estimates including specifically, but not limited to, Orvana’s ability to optimize

its assets to deliver shareholder value; estimates of future production (including without limitation, production guidance), operating

costs and capital expenditures; mineral resource and reserve estimates; statements and information regarding future feasibili ty

studies and their results; future transactions; future metal prices; the ability to achieve additional growth and geographic

diversification; and future financial performance, including the ability to increase cash flow and profits; future financing requirements;

mine development plans; the possibility of the conversion of inferred mineral resources to mi neral reserves; and Orovalle’s ability to

finalize the definitive Collective Bargain Agreement.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable

by the Company as of the date of such statements, are inherently subject to significant business, economic and competitive

uncertainties and contingencies, which includes, without limitation, as particularly set out in the notes accompanying the Company’s

most recently filed financial statements. The estimates and assumptions of the Company contained or incorporated by reference in

this news release, which may prove to be incorrect, include, but are not limited to the various assumptions set forth herein and in

5

Orvana’s most recently filed Management’s Discussion & Analysis and Annual Information Form in respect of the Company’s most

recently completed fiscal year (the “Company Disclosures”) or as otherwise expressly incorporated herein by reference as well as:

there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disr uptions,

damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at El Valle, Don Mario and

Taguas being consistent with the Company’s current expectations; political developments in any jurisdiction in which the Company

operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies

being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the

Company’s current mineral reserve and mineral resource estimates; labour and materials costs increasing on a basis consistent with

Orvana’s current expectations; and the availability of necessary funds to execute the Company’s plan. Without limiting the generality

of the foregoing, this news release also contains certain "forward -looking statements" within the meaning of applicable securities

legislation, including, without limitation, references to the results of the Company’s exploration activities, including but not limited to,

drilling results and analyses, mineral resource estimation, conceptual mine plan and operations, internal rate of return, sensitivities,

taxes, net present value, potential recoveries, design parameters, operating costs, capital costs, production data and econom ic

potential; the timing and costs for production decisions; permitting timelines and requirements; exploration and planned exploration

programs; and the Company's general objectives and strategies.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company’s control, affect the operations ,

performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated

or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors

include: the potential impact of global health and global economic conditions on the Company’s business and operations, including:

our ability to continue operations; and our ability to manage challenges presented by such conditions; the general economic, political

and social impacts of the continuing conflict between Russia and Ukraine, our ability to support the sustainability of our business

including through the development of crisis management plans, increasing stock levels for key supplies, monitoring of guidance from

the medical community, and engagement with local communities and authorities; fluctuations in the pr ice of gold, silver and copper;

the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estim ates;

variations in the grade of ore mined; variations in the cost of operations; the availability of qualified personnel; the Company’s ability

to obtain and maintain all necessary regulatory approvals and licenses; Orovalle’s ability to complete the permitting process of the

El Valle Tailings Storage Facility increasing the storage capacity; Orovalle’s ability to complete the stabilization project of the legacy

open pit wall; the Company’s ability to use cyanide in its mining operations; risks generally associated with mineral exploration and

development, including the Company’s ability to continue to operate the El Valle and/or ability to resume long-term operations at the

Carlés Mine; the Company’s ability to successfully implement a sulphidization circuit and ancillary facilities to process the current

oxides stockpiles at Don Mario; the Company’s ability to successfully carry out development plans at Taguas; sufficient funding to

carry out development plans at Taguas and to process the oxides stockpiles at Don Mario; EMIPA’s ability to complete the issuance

of the Bonds Program at Bolivia and any additional required financing to commence the OSP; the Company’s ability to acquire and

develop mineral properties and to successfully integrate such acquisitions; the Company’s ability to execute on its strategy; the

Company’s ability to obtain financing when required on terms that are acceptable to the Company; challenges to the Company’s

interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in

political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; the

challenges presented by global health conditions; fluctuating operational costs such as, but not limited to, power supply costs; current

and future environmental matters; and the risks identified in the Company’s disclosures. This list is not exhaustive of the factors that

may affect any of the Company’s forward-looking statements and reference should also be made to the Company’s Disclosures for

a description of additional risk factors.

Any forward-looking statements made herein with respect to the anticipated development and exploration of the Company’s mineral

projects are intended to provide an overview of management’s expectations with respect to certain future activities of the Compa ny

and may not be appropriate for other purposes. Forward -looking statements are based on management’s current plans, estimates,

projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-

looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers ar e

cautioned not to put undue reliance on forward- looking statements. The forward- looking statements made in this information are

intended to provide an overview of management’s expectations with respect to certain future operating activities of the Company and

may not be appropriate for other purposes.