Orezone Reports Q1-2025 Production and HARD ROCK Expansion Update
OREZONE GOLD CORPORATION
450-505 Burrard Street
Vancouver, BC, V7X 1M3
T: 778-945-8977
OREZONE REPORTS Q1-2025 PRODUCTION AND HARD ROCK EXPANSION UPDATE
April 16, 2025 – Vancouver, BC - Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF) (the “Company”
or “Orezone”) is pleased to announce its Q1-2025 gold production results and a construction update for
the Stage I hard rock expansion at its Bomboré Gold Mine. All dollar amounts are in USD unless otherwise
indicated and abbreviation “M” means million.
Q1-2025 Production Results
• Gold production of 28,688 ounces
• Gold sales of 28,943 ounces at an average realized price of $2,851 per ounce for sales of $82.5M
• Quarter-end cash balance of $102.0M and senior debt of $65.2M after principal repayments of
$4.8M in the quarter
• Safety milestone of 20 million person-hours worked without a Loss Time Injury (“LTI”) achieved
in March
Stage I Hard Rock Construction Update
• Construction of the Stage I hard rock expansion remains ahead of schedule and on budget. First
gold pour and mill commissioning on track for Q4-2025
• Engineering is ahead of schedule with 85% progress to the end of March
• Procurement is substantially complete with only minor bulk material top-ups outstanding
• SAG mill major components are now onsite, well ahead of schedule for the longest lead items
• Concrete works remain ahead of schedule with the dump pocket and SAG mill foundations
significantly advanced, and CIL tank foundations complete
• Structural/Mechanical/Piping contractor has mobilized and is progressing with CIL tank
installation
• Several mining areas for hard rock mining have now been readied in preparation for
commencement of hard rock mining later this year
• Completed first monthly hard rock expansion video, which can be viewed here
Patrick Downey, President & CEO stated, “Q1 was another solid operating quarter at Bomboré, with
slightly lower than planned gold ounces produced as a result of re-scheduled mill maintenance. Mined
tonnage was ahead of plan for the quarter, which keeps the Company well-positioned to achieve its 2025
production guidance of 115,000-130,000 ounces.
During the quarter, the Company achieved a major milestone of 20 million person-hours worked without
a LTI. This industry leading safety record speaks to the exceptional effort on injury prevention by the entire
Bomboré team which has instilled a pervasive, safety first, culture onsite.
- 2 -
Throughout the quarter, the Company made material progress advancing the Stage I hard rock expansion,
with concrete foundations for the dump pocket and SAG mill significantly advanced , and CIL tank
installation now underway. The Stage I hard rock expansion remains ahead of schedule and on budget,
with first gold and mill commissioning on track for Q4-2025. Completion of the Stage I expansion will mark
a material transformation in the Bomboré operation, with gold production forecast ed to increase by
approximately 45% from current levels to 170,000-185,000 ounces in 2026.
Further positioning the Company for a significant transformation, Orezone announced during the quarter
that: (1) it is advancing a secondary listing on the Australian Securities Exchange (“ASX”), with a target
listing in mid-2025, and (2) is evaluating plans to accelerate the Stage II hard rock expansion to an overall
5.0 million tonnes per annum (“Mtpa”) two years ahead of schedule (see news release dated February 23,
2025). While subject to final Board approval, the Stage II expansion is forecasted to inc rease the overall
gold production profile at Bomboré to 220,000 -250,000 ounces per year. We also expect to release drill
results from the P17S and P17 area in the coming weeks as we target the high-grade extensions of these
highly prospective zones.”
Bomboré Q1-2025 Production Results (100% Basis)
Unit Q1-2025
Ore processed Tonnes 1,511,303
Ore grade Au g/t 0.67
Plant recovery % 87.9
Gold produced Au oz 28,688
Hard Rock Plant and Operations Overview
The 2.5Mtpa Stage I hard rock expansion is designed to process higher-grade hard rock ore. The expansion
is independent of the adjacent 6.0Mtpa oxide plant but will utilize a number of shared services and
infrastructure including the tailings storage facility , warehouses, administration complex, and technical
services. The concentrated scope of the brownfield expansion significantly reduces schedule and budget
risk in comparison to a new build, with the ramp -up to benefit from the well -established mining,
processing, and maintenance teams onsite.
This Stage I expansion is scheduled for commissioning in Q4-2025 and as with the oxide plant, which had
a nameplate capacity of 5.2Mtpa, the Company views the potential to achieve materially higher
throughput rates than that of the 2.5Mtpa Stage I design.
With the strong price of gold, the Company continues to evaluate the timing of the Stage II hard rock
expansion, which will increase the nameplate hard rock throughput to 5.0Mtpa, yielding a forecasted
overall production profile of 225,000 -250,000 ounces per year. With a 5.0Mtpa jaw crusher currently
being installed in Stage I, the Stage II expansion will primarily consist of a ball mill, pebble crusher,
thickener, four additional CIL tanks and a gold room upgrade. Consideration in the Stage I design and
layout has been made to easily accommodate these Stage II additions.
- 3 -
Figure 1: Bomboré Processing Complex – Hard Rock Plant Layout (blue labels) Relative to Oxide Plant and Other
Established Infrastructure (white labels)
Figure 2: Stage I Hard Rock Expansion – Major Plant Component Construction
- 4 -
Contact Information
Patrick Downey
President and Chief Executive Officer
Kevin MacKenzie
Vice President, Corporate Development and Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673 0663
[email protected] / www.orezone.com
For further information please contact Orezone at +1 (778) 945-8977 or visit the Company’s website at
www.orezone.com.
The Toronto Stock Exchange neither approves nor disapproves the information contained in this news
release.
Qualified Persons
The scientific and technical information in this news release was reviewed and approved by Mr. Rob
Henderson, P. Eng, Vice -President of Technical Services and Mr. Dale Tweed, P. Eng., Vice -President of
Engineering, both of whom are Qualified Persons as defined under NI 43-101 - Standards of Disclosure for
Mineral Projects.
Cautionary Note Regarding Forward-Looking Statements
This press release contains certain information that may constitute “forward -looking information” within the
meaning of applicable Canadian Securities laws and “forward-looking statements” within the meaning of applicable
U.S. securities laws (together, “f orward-looking statements”). Forward-looking statements are frequently
characterized by words such as “plan”, “expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”, “potential”,
“possible” and other similar words, or statements that certain events or conditions “may”, “will”, “could”, or “should”
occur. Forward-looking statements in this press release include, but are not limited to, statements that Orezone is
positioned for a transformational 2025 , the Company is positioned well to achieve its 2025 production guidance of
115,000-130,000 ounces, the target of listing on the ASX in mid -2025, the construction of the Stage I h ard rock
expansion is well advanced (and fully financed) with completion and commissioning set for Q4 -2025 and once
commissioned, will increase annual production by approximately 45 %, the potential greater capacity than the
2.5Mtpa design of the hard rock plant, and statements with resect to the Stage II hard rock expansion.
All such forward-looking statements are based on certain assumptions and analyses made by management in light
of their experience and perception of historical trends, current conditions and expected future developments, as well
as other factors management and the qualified persons believe are appropriate in the circumstances.
All forward-looking statements are subject to a variety of risks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected in the forward-looking statements including, but not
limited to, delays caused by pandemics, terrorist or other violent attacks (including cyber security attacks), the failure
of parties to contracts to honour contractual commitments, unexpected changes in laws, rules or regulations, or their
enforcement by applicable authori ties; social or labour unrest; changes in commodity prices; unexpected failure or
inadequacy of infrastructure, the possibility of unanticipated costs and expenses, accidents and equipment
breakdowns, political risk, unanticipated changes in key management personnel and general economic, market or
business conditions, the failure of exploration programs, including drilling programs, to deliver anticipated results
and the failure of ongoing and uncertainties relating to the availability and costs of financin g needed in the future,
- 5 -
and other factors described in the Company's most recent annual information form and management discussion and
analysis filed on SEDAR+. Readers are cautioned not to place undue reliance on forward -looking statements.
Although the forward-looking statements contained in this press release are based upon what management of the
Company believes are reasonable assumptions, the Company cannot assure investors that actual results will be
consistent with these forward-looking statements. These forward-looking statements are made as of the date of this
press release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities
laws, the Company does not assume any obligation to update or revise the forward -looking statements contained
herein to reflect events or circumstances occurring after the date of this press releas e.