Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ORE.TO ·

Orezone Reports First Quarter 2024 Results

Financials

OREZONE GOLD CORPORATION

450-505 Burrard Street

Vancouver, BC, V7X 1M3

T: 778-945-8977

[email protected]

Orezone Reports First Quarter 2024 Results

May 13, 2024 – Vancouver, BC - Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF) (“Orezone” or

“Company”) reported its operational and financial results for the first quarter of 2024. The Company will

host a conference call and webcast on May 14, 2024 commencing at 8:00am PT to discuss its Q1-2024

results. Additional details are provided at the end of this press release.

All dollar amounts are in USD unless otherwise stated and abbreviation “M” means million.

Patrick Downey, President and CEO, commented “ Our Bomboré mine had another quarter of consistent

performance, delivering 30,139 ounces of gold production, mine earnings of $27 million, and positive free

cashflow. In addition, we successfully commissioned the powerline connection to the national grid and

substantially completed the construction of the MV3 resettlement site which will open mining access to

the Siga East deposit in the third quarter of 2024.

Importantly, we continue to reinvest in the Bomboré mine and, after a careful review of available financing

alternatives, the Company has decided to pursue its Phase II Hard Rock Expansion in two stages to better

align capital requirements with funding sources. We have now received a debt proposal for the first stage

of the expansion from our senior lender, Coris Bank, which we expect to finalize in the very near future.”

2024 FIRST QUARTER HIGHLIGHTS

(All mine site figures on a 100% basis) Q1-2024 Q1-2023

Operating Performance

Gold production oz 30,139 41,301

Gold sales oz 31,229 43,139

Average realized gold price $/oz 2,066 1,892

Cash costs per gold ounce sold1 $/oz 1,127 799

All-in sustaining costs1 (“AISC”) per gold ounce sold $/oz 1,324 926

Financial Performance

Revenue $000s 64,685 81,712

Earnings from mine operations $000s 26,882 39,670

Net income attributable to shareholders of Orezone1 $000s 11,697 22,560

Net income per common share attributable to

shareholders of Orezone1

Basic

Diluted

$

$

0.03

0.03

0.07

0.06

Adjusted EBITDA1 $000s 25,928 42,645

Adjusted earnings attributable to shareholders of

Orezone1 $000s 7,736 24,574

Adjusted earnings per share attributable to

shareholders of Orezone1 $ 0.02 0.07

- 2 -

(All mine site figures on a 100% basis) Q1-2024 Q1-2023

Cash and Cash Flow Data

Operating cash flow before changes in working capital $000s 20,357 41,137

Operating cash flow $000s 13,637 38,926

Free cash flow1 $000s 2,013 31,498

Cash, end of period $000s 15,597 45,172

1 Cash costs, AISC, Adjusted EBITDA, Adjusted earnings, Adjusted earnings per share, and Free cash flow

are non-IFRS measures. See “Non-IFRS Measures” section below for additional information.

• Safety: Continued strong safety performance in Q1 -2024 with 1.41 million hours worked without a

lost-time injury.

• Debt Reduction: Principal repayment of XOF 3.0 billion ($5.0 million) in Q1 -2024 on the Company’s

senior loans with Coris Bank International (“Coris Bank”).

• Liquidity: On May 10, 2024, the Company closed and drew down on a XOF 12.0 billion (~$20 million)

bridge loan with Coris Bank in order to improve the Company’s cash position. The Company intends

to refinance the bridge loan with the project loan for its Phase II hard rock expansion with Coris Bank

expected in Q3-2024.

The Phase II Hard Rock Expansion

A hard rock plant, to complement the existing Phase I oxide plant, is required to process the fresh rock

and lower transition mineral reserves of the Bomboré orebody.

The Company originally contemplated constructing a 4.4 million tonnes per annum (“Mtpa”) hard rock

plant in a single stage as outlined in its 2023 feasibility study. Following a recent review of available

financing sources, the Company has decided to complete this brownfield expansion in two stages to better

manage its capital requirements. Stage 1 will consist of an initial 2.5Mtpa hard rock plant, with a future

Stage 2 expansion increasing hard rock plant throughput to 5.0Mtpa – 7.0Mtpa.

A preliminary capital cost for this initial 2.5Mtpa hard rock plant is estimated at $80 million, significantly

less than the $167.5 million estimated for the 4.4Mtpa hard rock plant. The Company expects to finance

the construction costs of this Stage 1 hard rock plant (rescoped “Phase II Hard Rock Expansion”) primarily

through senior debt and cash flow generated from its Phase I oxide operations during the construction

period.

The Company has significantly advanced discussions with Coris Bank for additional project debt and

anticipates concluding a binding debt commitment in June 2024. Based on forecasted construction and

key equipment timelines, the Company expects first gold from the Phase II Hard Rock Expansion to be

achieved in late 2025.

The Company intends to provide more detailed guidance for its Phase II Hard Rock Expansion later this

year after the Company has secured a binding debt commitment and Board approval to proceed with the

expansion.

- 3 -

BOMBORÉ GOLD MINE (100% BASIS) – OPERATING HIGHLIGHTS

Q1-2024 Q1-2023

Safety

Lost-time injuries frequency rate (LTIFR) per 1M hours 0.00 0.00

Personnel-hours worked 000s hours 1,410 928

Mining Physicals

Ore tonnes mined tonnes 2,402,533 2,205,056

Waste tonnes mined tonnes 3,123,099 2,382,135

Total tonnes mined tonnes 5,525,631 4,587,191

Strip ratio waste:ore 1.3 1.1

Processing Physicals

Ore tonnes milled tonnes 1,355,619 1,445,693

Head grade milled Au g/t 0.78 0.96

Recovery rate % 89.0 92.2

Gold produced Au oz 30,139 41,301

Unit Cash Cost

Mining cost per tonne $/tonne 3.48 2.91

Mining cost per ore tonne processed $/tonne 8.02 6.51

Processing cost $/tonne 9.24 9.21

Site general and admin (“G&A”) cost $/tonne 3.79 3.23

Cash cost per ore tonne processed $/tonne 21.05 18.96

Cash Costs and AISC Details

Mining cost (net of stockpile movements) $000s 10,867 9,417

Processing cost $000s 12,520 13,322

Site G&A cost $000s 5,134 4,667

Refining and transport cost $000s 117 148

Government royalty cost $000s 5,132 4,912

Gold inventory movements $000s 1,416 2,019

Cash costs1 on a sales basis $000s 35,186 34,485

Sustaining capital $000s 4,018 3,530

Sustaining leases $000s 73 187

Corporate G&A cost $000s 2,069 1,731

All-In Sustaining Costs1 on a sales basis $000s 41,346 39,933

Gold sold Au oz 31,229 43,139

Cash costs per gold ounce sold1 $/oz 1,127 799

All-In Sustaining Costs per gold ounce sold1 $/oz 1,324 926

1 Non-IFRS measure. See “Non-IFRS Measures” section for additional details.

Bomboré Production Results

Gold production in Q1 -2024 was 30,139 ounces, a decline of 27% from the 41,301 ounces produced in

Q1-2023. The lower gold production is attributable to an 18% decrease in head grades, a 6% decline in

plant throughput, and a 3% decrease in plant recoveries. The better head grade achieved in Q1-2023 was

primarily the result of processing of high -grade stockpiles accumulated during the Phase I construction

which have now been fully depleted. Mill availability in Q1 -2024 was impacted by the commissioning of

- 4 -

grid power to site and from the shortage of power from the national grid towards the end of the quarter.

In addition, as mining deepens in the certain pits, the quantity of transition ore has started to increase.

The presence of transition ore results in slightly lower metallurgical recoveries, lower plant throughput,

and additional plant maintenance due to the harder nature of the ore.

Plant throughput, head grades, and recoveries are expected to improve from a greater blend of oxide ore

once mining commences at Siga East in Q3-2024.

Bomboré Operating Costs

AISC per gold ounce sold in Q1 -2024 was $1,324, a 43% increase from the $926 per ounce sold in Q1 -

2023. The higher AISC is primarily the result of: (a) lower Q1-2024 gold production and sales as explained

above; (b) greater per ounce royalty costs from new royalty rates that took effect in October 2023 and

from a higher realized selling price; and (c) increased mining costs.

Cash cost per ore tonne processed in Q1-2024 was $21.05 per tonne, an increase of 11% from the $18.96

per tonne in Q1-2023. The higher cash cost in Q1-2024 was predominantly due to increased mining and

site G&A costs, and from fewer ore tonnes processed. Mining costs have increased as lower benches are

mined resulting in longer hauls and more transition material that requires drill -and-blast prior to

excavation. In addition, unit mining costs have increased from a higher strip ratio and more management

fees from the mobilization of a second mining contractor in July 2023 to supplement material movement

of the main mining contractor. Site G&A costs reflect greater spending for security as the Company

expands its operations into the southern portion of the mining permit.

Processing costs per ore tonne has remained relatively stable from $9.21 per tonne in Q1 -2023 to $9.24

per tonne in Q1-2024. Unit processing costs were expected to decline in Q1-2024 from 2023 levels upon

the introduction of grid power to the Bomboré mine at the end of January 2024; however, the power

costs savings from using grid power has been offset by greater blend of transition ore requiring higher per

tonne consumption of power, grinding media, and main reagents; more plant maintenance to address

higher equipment wear; and from lower plant throughput resulting in fixed processing costs being

absorbed over fewer tonnes in Q1 -2024. Furthermore, the mine relied on more self generated power

beginning in March 2024 from lower-than-expected availability of grid power as the dry season impacted

the contributions of hydropower to the national grid.

Bomboré Growth Capital Projects

Grid Power Connection

The commissioning of the powerline to connect Bomboré to Burkina Faso’s national energy grid

commenced in January 2024 and was successfully energized by the end of the same month. As of March

31, 2024, the Company has incurred costs of $19.3M for the grid power connection, of which $1.1M was

incurred in Q1-2024.

- 5 -

Resettlement Action Plan (“RAP”) Phases II and III

RAP Phases II and III involve the construction of three new resettlement communities (MV3, MV2, and

BV2) in order to relocate households currently residing within the southern half of the Bomboré mining

permit. The Company has sequenced MV3 first in order to gain access to mining areas that are currently

contemplated in the 2024 mine plan.

Construction of MV3 was substantially completed in April 2024 with the Company now organizing with

local leaders and residents to relocate families into their new resettlement homes later in Q2 -2024. In

parallel, the Company has commenced earthworks for t he next resettlement site (MV2) and awarded

contracts to local companies to begin construction shortly.

As of March 31, 2024, the Company has incurred project-to-date costs of $13.5M for RAP Phases II and III,

of which $3.1M was incurred in Q1-2024.

NON-IFRS MEASURES

The Company has included certain terms or performance measures commonly used in the mining industry

that is not defined under IFRS, including “cash costs”, “AISC”, “EBITDA”, “adjusted EBITDA”, “adjusted

earnings”, “adjusted earnings per share”, and “free c ash flow”. Non -IFRS measures do not have any

standardized meaning prescribed under IFRS, and therefore , they may not be comparable to similar

measures presented by other companies. The Company uses such measures to provide additional

information and they should not be considered in isolation or as a substitute for measures of performance

prepared in accord ance with IFRS. For a complete description of how the Company calculates such

measures and reconciliation of certain measures to IFRS terms, refer to “Non -IFRS Measures” in the

Management’s Discussion and Analysis for the three months ended March 31, 2024 which is incorporated

by reference herein.

CONFERENCE CALL AND WEBCAST

The condensed consolidated interim financial statements and Management’s Discussion and Analysis are

available at www.orezone.com and on the Company’s profile on SEDAR+ at www.sedarplus.ca. Orezone

will host a conference call and audio webcast to discus s 2024 first quarter results on

May 14, 2024 at 8:00am PT (11:00am ET).

Webcast

Date: Tuesday, May 14, 2024

Time: 8:00 am Pacific time (11:00 am Eastern time)

Please register for the webcast here: Orezone Q1-2024 Conference Call and Webcast

Conference Call

Toll-free in U.S. and Canada: 1-800-715-9871

International callers: +646-307-1963

Event ID: 2084420

- 6 -

QUALIFIED PERSONS

The scientific and technical information in this news release was reviewed and approved by Dr. Pascal

Marquis, Geo., Senior Vice President of Exploration and Mr. Rob Henderson, P. Eng, Vice President of

Technical Services , both of whom are Qualified Persons as defined under NI 43 -101 Standards of

Disclosure for Mineral Projects.

About Orezone Gold Corporation

Orezone Gold Corporation (TSX: ORE OTCQX: ORZCF) is a West African gold producer engaged in mining,

developing, and exploring its 90%-owned flagship Bomboré Gold Mine in Burkina Faso. The Bomboré mine

achieved commercial production on its oxide operations on December 1, 2022, and is now focussed on its

staged hard rock expansion that is expected to materially increase annual and life-of-mine gold production

from the processing of hard rock mineral reserves. Orezone is led by an experienced team focused on

social responsibility and sustainability with a proven track record in project construction and operations,

financings, capital markets, and M&A.  

The technical report entitled Bomboré Phase II Expansion, Definitive Feasibility Study is available on

SEDAR+ and the Company’s website.

Patrick Downey

President and Chief Executive Officer

Vanessa Pickering

Manager, Investor Relations

Tel: 1 778 945 8977 / Toll Free: 1 888 673 0663

[email protected] / www.orezone.com

For further information please contact Orezone at +1 (778) 945-8977 or visit the Company’s website at

www.orezone.com.

The Toronto Stock Exchange neither approves nor disapproves the information contained in this news

release.

Cautionary Note Regarding Forward-Looking Statements

This press release contains certain information that constitutes “forward-looking information” within the

meaning of applicable Canadian Securities laws and “forward-looking statements” within the meaning of

applicable U.S. securities laws (together, “forward-looking statements”). Forward-looking statements are

frequently characterized by words such as “plan”, “expect”, “project”, “intend”, “believe”, “anticipate”,

“estimate”, “potential”, “possible” and other similar words, or statements that certain even ts or

conditions “may”, “will”, “could”, or “should” occur.

All forward-looking statements are subject to a variety of risks and uncertainties and other factors that

could cause actual events or results to differ materially from those projected in the forward -looking

statements including, but not limited to, terror ist or other violent attacks, the failure of parties to

- 7 -

contracts to honour contractual commitments, unexpected changes in laws, rules or regulations, or their

enforcement by applicable authorities; social or labour unrest; changes in commodity prices; unexpected

failure or inadequacy of infrastructure, the possibility of project cost overruns or unanticipated costs and

expenses, accidents and equipment breakdowns, political risk, unanticipated changes in key management

personnel, the spread of diseases, epidemics and pandemics diseases, market or business conditions, the

failure of exploration programs, including drilling programs, to deliver anticipated results and the failure

of ongoing and uncertainties relating to the availability and costs of financing needed in the future, and

other factors described in th e Company's most recent annual information form and management’s

discussion and analysis filed on SEDAR+ on www.sedarplus.ca. Readers are cautioned not to place undue

reliance on forward-looking statements.

Forward-looking statements are based on the applicable assumptions and factors management considers

reasonable as of the date hereof, based on the information available to management at such time. These

assumptions and factors include, but are not limited to, assumptions and factors related to the Company’s

ability to carry on current and future operations, including: development and exploration activities; the

timing, extent, duration and economic viability of such operations, including any mineral resour ces or

reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and

assessments; the Company’s ability to meet or achieve estimates, projections and forecasts; the

availability and cost of inputs; the price an d market for outputs, including gold; foreign exchange rates;

taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future

obligations; the ability to obtain timely financing on reasonable terms when require d; the current and

future social, economic and political conditions; and other assumptions and factors generally associated

with the mining industry.

Although the forward -looking statements contained in this press release are based upon what

management of the Company believes are reasonable assumptions, the Company cannot assure investors

that actual results will be consistent with these forward -looking statements. These forward -looking

statements are made as of the date of this press release and are expressly qualified in their entirety by

this cautionary statement. Subject to applicable securities laws, the Company does not assume any

obligation to u pdate or revise the forward -looking statements contained herein to reflect events or

circumstances occurring after the date of this press release.