Omai Gold Delivers PEA with After-Tax NPV5% of $556 Million and 19.8% IRR at a $1,950/oz Gold Price for Wenot Open Pit Project in Guyana
Omai Gold Delivers PEA with After-Tax NPV5% of $556 Million
and 19.8% IRR at a $1,950/oz Gold Price
for Wenot Open Pit Project in Guyana
(All dollar amounts are in United States dollars, unless otherwise stated)
April 4, 2024, Toronto, Ontario – Omai Gold Mines Corp. (OMG: TSXV; OMGGF: OTCQB) (“Omai Gold”
or the “Company”) is pleased to announce positive results from its first Preliminary Economic Assessment
(“PEA”) for the Wenot Project, one of the two gold deposits located on its 100%-owned Omai Property, in
Guyana. The PEA supports an initial open pit mining scenario for production averaging 142 ,000 ounces of
gold per year over a 13-year mine life, with peak year production of 184,000 ounces. Total Wenot production
is estimated at 1,840,000 ounces of payable gold. A spot gold price sensitivity of $2,200/oz supports an
after-tax Net Present Value5% (“NPV”) of $777 million, a 24.7% Internal Rate of Return (“IRR”), and a payback
period of 3.5 years.
Elaine Ellingham, President and CEO comments: “ We are extremely pleased with this first economic
assessment for the new Omai that incorporates only our Wenot open pit deposit at this time. This PEA is an
important step forward as it converts our successful exploration programs into a baseline production scenario
that shows potential for robust economic development for Omai to once again become a large- scale gold
producer, supported by the many benefits of a brownfields project including good road access, a nearby
skilled workforce and the strong support of government for re-development.”
“Although we have not included the adjacent Gilt Creek Deposit in this PEA economics, we are confident
that it will contribute to an overall future mine plan. Since Gilt Creek would be an underground mine, it would
have required significant additional engineering, time and cost , and our priority was to establish a baseline
valuation for our shareholders. We have fast-tracked the advancement of this project over the past two years
and are pleased to deliver these tangible results.”
PEA Highlights for Wenot Open Pit
▪ After-tax NPV 5% of $55 6 million and after -tax IRR of 19.8% based on $1,950/oz gold with a
sensitivity case at $2,200/oz gold giving an after-tax NPV5% of $777 million and IRR of 24.7%
▪ Initial capital (“Capex”) of $375 million and sustaining capital of $172 million over life-of-mine
▪ Projected average gold production of 142,000 oz per year over a 13-year mine life
After-tax payback of 4.3 years at base case $1,950/oz gold (3.5 years at $2,200/oz gold)
Average cash operating costs of $916/oz gold and all-in sustaining costs of $1,009/oz
Cumulative cash flow of $1.07 billion after-tax over 13 years on base case assumptions
Total payable gold production of 1.84 million ounces
Average head grade of 1.51 g/t Au and 92.5% process recovery
Average strip ratio for the open pit life-of-mine estimated at 7.8:1
Click here to view a 3D model of the Wenot Open Pit Deposit
Omai’s CEO continued, “We are pleased with the PEA results as it establishes the potential for a single
“superpit” for the Wenot deposit. We further believe that Omai holds exceptional potential to both expand the
mine plan and to boost the economics: 1) At Wenot, there are gold zones identified along strike and at depth
that can be expected to expand Mineral R esources within and outside the designed PEA pit ; 2) By
completing engineering studies and incorporating the adjacent Gilt Creek Deposit, the Omai mine plan could
potentially expand to a 20+ year mine life; and 3) By advancing work on two high-grade near-surface zones,
there is potential for higher grade process plant feed for the first few years that would boost economics
considerably. The PEA sets the stage for Omai to advance engineering and permitting initiatives towards a
Preliminary Feasibility Study (“ PFS”). With these goals in mind, we are anxious t o continue our work
advancing the Omai Project in 2024.”
OMG NEWS RELEASE 2
Financial and operating metrics from the PEA are presented in Table 1 below.
Note: The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too
speculative geologically to have the economic considerations applied to them that would enable them to
be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral
Resources that are not Mineral Reserves do not have demonstrated economic viability.
Table 1. Financial and Operating Metrics from the Preliminary Economic Assessment
2024 Wenot Preliminary Economic Assessment (PEA)
Highlights
Production
Mine life (years) 13.0
T otal gold production (ounces) 1,840,000
Average annual gold production (ounces) 142,000
To tal mineralization mined (tonnes) 41,101,000
T otal waste mined (tonnes) 322,291,000
T otal material mined (tonnes) 363,392,000
Total waste-to-mineralization ratio 7.8:1
Average gold grade (grams per tonne) 1.51
Gold Process Recovery (%) 92.5%
Average Process Plant throughput (tpd) 9,000
Operating Costs
Mining cost per tonne (T otal Material) $1.63
Mining cost per tonne (Mineralization) $14.44
Processing Cost per tonne $15.58
G&A cost per tonne $3.16
T otal cost per tonne processed 1,3 $33.19
Total cash cost (per ounce sold)1,3 $916
Mine-site all-in-sustaining cost (per ounce sold)2,3 $1009
1 Total cash costs include mining, processing, surface infrastructures, transport, G&A and royalty costs.
2 All-in sustaining cost (“AISC”) includes total cash costs, sustaining capital expenses to support the on-going operations, and
closure/reclamation.
3 Non-IFRS financial performance measures with no standardized definition under IFRS. Refer to the note at the end of this press
release.
OMG NEWS RELEASE 3
Capital Costs
Initial capital expenditure (Initial Capex)3 $375.2 M
Sustaining capital expenditures3 $171.5 M
Net reclamation costs (cost less salvage value) $0
T otal capital expenditure – life of mine $546.8 M
T otal capital expenditure (per ounce sold) – life of mine $297/oz
Base Case Economic Analysis: $1,950 per ounce Gold Price
IRR (after-tax) 19.8%
NPV @ 0% discount rate (millions, after-tax) $1,067.7
NPV @ 5% discount rate (millions, after-tax) $556.4
Payback (years) 4.3
Economic Analysis Sensitivity at $2,200 per ounce Gold Price
IRR (after-tax) 24.7%
NPV @ 0% discount rate (millions, after-tax) $1,402.5
NPV @ 5% discount rate (millions, after-tax) $776.6
Payback (years) 3.5
Financial Analysis and Sensitivities
The Project generates cumulative after-tax free cash flow of $1,067 million and average annual free cash
flow of $112.5 million over the 13-year producing mine life.
Figure 1. After-tax Cash Flow over Life-of-Mine
OMG NEWS RELEASE 4
The PEA financial analysis is sign ificantly influenced by gold price, operating costs and capital costs as
shown in Table 2. For example, at the base case gold price of US$1,950/oz, the Wenot Project generates
after-tax NPV of $556.4 million using a 5% discount rate with an after -tax IRR of 19.8%. However, a 10%
sensitivity increase to the base case gold price to $2,145/oz, results in an after-tax NPV of $728.2 million and
an after-tax IRR of 23.7% with a payback period of 3.6 years from the commencement of production.
Table 2. PEA Sensitivities to Gold Price, Operating Costs (Opex) and Capital Costs (Capex)
Gold Price Sensitivities
Range GOLD PRICE After Tax NPV (5%) ($M) IRR Payback (Yrs)
-20% $1,560 210.1 11.1% 8.4
-10% $1,755 384.1 15.7% 5.8
0 $1,950 556.4 19.8% 4.3
10% $2,145 728.2 23.7% 3.6
20% $2,340 899.8 27.3% 3.2
Opex Sensitivities
Range OPEX After Tax NPV (5%) ($M) IRR Payback (Yrs)
-20.0% $807 706.3 23.6% 3.7
-10.0% $908 631.5 21.7% 3.9
0.0% $1,009 556.4 19.8% 4.3
10.0% $1,110 481.1 17.9% 4.7
20.0% $1,211 406.0 15.9% 5.8
Capex Sensitivities
Range CAPEX After Tax NPV (5%) ($M) IRR Payback (Yrs)
-20.0% $300 638.8 24.7% 3.5
-10.0% $338 597.7 22.1% 3.9
0.0% $375 556.4 19.8% 4.3
10.0% $413 514.9 17.9% 4.7
20.0% $450 473.5 16.2% 5.4
Gold Production
Annual production over the life-of-mine from the Wenot pit is expected to average 14 2,000 ounces of gold
with a peak year production of 184,000 ounces, for total payable gold production of 1,840,000 ounces.
Figure 2. Wenot Production Profile
0
50,000
100,000
150,000
200,000
1 2 3 4 5 6 7 8 9 10 11 12 13
Annual Gold
Production (Koz)
Production Year
Wenot Gold Production Profile
OMG NEWS RELEASE 5
Capital Costs
The initial capital costs are estimated at $375.2 million, with life-of-mine sustaining costs estimated at $172
million. Contingencies of $ 54 million and $18 million are included in initial and sustaining capital costs ,
respectively. These estimates were based on current costs and quotes received from potential local vendors
with other estimates based on references and experience from similar operations.
The main components of the $375.2 million initial capital costs include: $100 million for the processing plant
equipment and buildings plus $75 million indirect costs to construct the process plant , $46 million for mining
equipment and surface preparation, $45 million for surface civil and infrastructure, $33 million for capitalized
pre-stripping, $20 million for owner’s costs, and $54 million contingency.
The main components of the $172 million sustaining capital include: $139 million for mining equipment , $9
million for tailings and water treatment, $6 million for process plant equipment, and $18 million contingency.
Cash Costs
Total cash cost including royalties is estimated at $41.00 per tonne processed or $916/oz of payable gold.
The all -in-sustaining cost is estimated at $1, 009/oz of payable gold. Operating cost estimates were
developed using vendor quotes and knowledge of similar operations with productivities being derived from
benchmarking and industry practices.
Table 3. Total Cash Costs
Mining Cost (per tonne processed) $14.44
Processing Cost (per tonne processed) $15.58
G&A Cost (per tonne processed) $3.16
To tal Cost (per tonne of processed) 1 $33.19
Royalties (per tonne processed) $7.81
To tal Cash Cost (per ounce sold)1,3 $916
Mineral Resource Estimate
The PEA is based only on the Wenot O pen Pit Deposit and excludes the adjacent Gilt Creek D eposit.
Management believes that the Gilt Creek Deposit, which would require underground mining, is sufficiently
attractive to be integrated into a larger mine plan , however, to accelerate and simplify this current PEA, it
was excluded.
On February 8, 2024, the Company announced an updated Mineral Resource Estimate (“MRE”) for the Omai
Property in Guyana (Wenot and Gilt Creek Deposits). It details a total Indicated MRE of 1.985 million ounces
of gold averaging 2.15 g/t Au and an Inferred MRE of 2.279 million ounces averaging 2.26 g/t Au.
The PEA is based on the Wenot Deposit, with an Indicated MRE of 834,000 ounces averaging 1.48 g/t Au
and an Inferred MRE of 1,614,000 ounces averaging 1.99 g/t Au. The pit design used in the PEA does not
include 58,600 oz of Indicated Mineral Resources and 456,900 oz of Inferred Mineral Resources, which
represents approximately 21% of the total Wenot MRE ounces (Figure 5). These excluded MRE ounces are
either hosted within multiple, narrow veins or are isolated zones at depth that result in a high strip ratio.
However, it is expected that at least a portion of this currently ex cluded Mineral Resource could be
incorporated in future economic scenarios upon further drilling.
OMG NEWS RELEASE 6
Figure 3. 3-D Model of Wenot and Gilt Creek Deposits, Omai Gold Property, Guyana
The Mineral Resource Estimates for Omai are presented in Table 4. Notes accompanying the 2024 MRE
are shown below the table, summarizing the economic and technical assumptions.
Table 4. 2024 (January) Mineral Resource Estimates
Indicated Resources Inferred Resources
Resource Area Mining Method Tonnes
(k)
Au
(g/t)
Au
(koz)
Tonnes
(k) Au (g/t) Au
(koz)
GILT CREEK (1.5 g/t Cut-
Off) Underground 11,123 3.22 1,151 6,186 3.35 665
WENOT (0.35 g/t Cut-Off) Open Pit 17,572 1.48 834 25,183 1.99 1,614
Total Mineral Resource Estimate 28,695 2.15 1,985 31,369 2.26 2,279
Wenot Mineral Resource Estimate by Deposit Type
WENOT
Saprolite &
Alluvium Open Pit 2,048 1.07 70 153 1.13 5
Fresh Rock
& Transition Open Pit 15,524 1.53 764 25,030 2.00 1,609
Notes to Accompany the 2024 Mineral Resource Estimate:
1. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
2. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation,
socio-political, marketing, or other relevant issues.
3. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated
Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of
the Inferred Mineral Resourc e could potentially be upgraded to an Indicated Mineral Resource with continued
exploration.
OMG NEWS RELEASE 7
4. The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and
Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices
Guidelines (2019) prepared by the CIM Standi ng Committee on Reserve Definitions and adopted by the CIM
Council.
5. Wenot wireframe constrained gold assays were composited to 1.5 metre lengths and subsequently capped between
10 to 25 g/t. Gilt Creek Wireframe constrained gold assays were composited to 1.0 metre lengths and subsequently
capped between 12 to 40 g/t.
6. The Wenot Mineral Resource Estimate incorporates 9,840 assay results from 603 diamond drill holes totalling
87,323 m within the mineralized wireframes.
The Gilt Creek Mineral Resource Estimate incorporates 7,056 assay results from 46 diamond drill holes totalling
27,997 m within the mineralized wireframes
7. Grade estimation was undertaken with ID3interpolation.
8. Wenot wireframe constrained bulk density was determined from 30 site visit samples.
Gilt wireframe constrained bulk density was determined from 28 site visit samples.
9. Wenot gold process recoveries used were 92% for Alluvium/Saprolite and 92% for Transition/Fresh Rock.
Gilt Creek gold process recovery used was 92%
10. The gold price used was US$1,850/oz
11. Wenot US$ open pit operating costs used were $2.50/t for mineralized material mining, $1.75/t for waste mining,
$10/t for Alluvium/Saprolite processing, $14/t for Transition/Fresh Rock processing and $2.50/t G&A. Gilt Creek
US$ underground operating costs used were $60/t for mining, $15/t for processing and $7/t G&A.
12. At Gilt Creek, MRE blocks were reviewed for grade and geometric continuity. Isolated/orphaned and single block
width strings of blocks were removed in order to only report Mineral Resources with a reasonable prospect of
economic extraction.
13. Wenot pit slopes were 45o.
Mining
The Project area consists of subdued topography. The area, topography, and climate are amenable to the
conventional open pit mining operations proposed for the Project, similar to historic al operations. No
underground mining is planned at this stage although the potential for development of underground mining of
the Gilt Creek Deposit will be evaluated in the future.
The Wenot mining operations will encompass a single large open pit with 55o hard rock inter ramp slopes
and 30o saprolite slopes that will be mined with conventional mining equipment in two pushback phases. In
order to improve mining selectivity and reduce dilution, two different bench heights and sets of mining
equipment will be used. Mineralization will be mined using a 5 m high bench height with 150 mm diameter
blast hole drills, and a fleet consisting of 5 m3 bucket excavators and 35 t rigid body haul trucks. Waste rock
and saprolite will be mined on 10 m high benches using 200 mm diameter blast hole drills, 22 m 3 bucket
hydraulic excavators, and 177 t haul trucks. Major pieces of mining equipment will be purchased v ia a lease
financing agreement. Various support equipment will be required, such as dozers, graders, water trucks,
and light vehicles for maintenance, personnel transport and mine supervision. The surficial saprolite cover,
which is anticipated to be free digging and will not require blasting, is up to 60m thick forming the upper part
of the 440 m deep open pit.
The open pit mine will have a mineralization production rate that averages 9,000 tpd over a 13- year mine
life. A total of 322.3 Mt of waste rock is planned to be mined, with 2.6 Mt of mineralization in saprolite and
38.5 Mt of mineralization in fresh rock, for a total strip ratio of 7.8:1, at an average grade of 1.51 g/t Au
containing 1.99 Moz Au. Total material mined will peak at 110,000 tpd.
Mineralization may be delivered either to the primary crusher or placed into a nearby stockpile. Waste
rock is either taken to a waste storage facility or used in tailings dam embankment construction.
OMG NEWS RELEASE 8
Figure 4. Wenot Open Pit Design (Two Phases)
Metallurgy & Processing
An average of 9,000 tpd of gold mineralized material will be treated in the Omai process plant. The process
plant will consist of a semi-autogenous grinding mill in closed circuit with a pebble crusher and ball mill in a
closed circuit with cyclones (SABC circuit). Primary crushing will consist of a gyratory crusher for hard run-
of-mine (“ROM”) feed. A gravity circuit, which precedes leaching will recover coarse gold from the cyclone
underflow, while the cyclone overflow is thickened and treated in a multi -tank carbon-in-leach (“CIL”) or
carbon-in-pulp (“CIP”) circuit. Gold will be stripped from the loaded carbon, concentrated by electrowinning
and recovered as gold bars in a gold room.
The Omai Gold process plant will be designed to be a compact facility with attached grinding media and
reagent reception. The process plant facilities will include a laboratory, a mill maintenance workshop, and
safety, personal services and management offices.
Metallurgical Data
The anticipated metallurgical performance for processing the O mai Mineral Resources has a dual base of
verification: (i) A comprehensive test program by Lakefield Research (now SGS Canada) that was completed
in 1990 on drill core representing seven mineralized zones, and (ii) The processing of 80 million tonnes of
mineralized material over 12 years by Omai Gold Mines Limited (OGML) from the Fennel and Wenot pits as
well as alluvial zones.
During operations from 1993 to 2005, the hard rock ROM feed was crushed in a gyratory crusher and ground
by a combination of SAG and ball mills (a SABC designation). Soft mineralized material was blended by a
backhoe into the crushed hard rock feed. A combination of gravity -based methods including spiral, Nelson
centrifuge and tabling was employed to recover free gold. Gold leaching was conventional with a mild
concentration of process reagents, air-sparged leaching followed by CIP gold recovery, strippi ng from the
carbon, electrowinning and electric furnace refining. The historical gold recovery ranged from 92% to 94%.
Metallurgical testing at Lakefield included grinding tests indicating that the Bond Work Index was very high
for the hard-rock composites at 19 to 25 KWh/t. As anticipated, the Work Index was very low (~6 KWh/t) for
saprolite. Gravity concentration was examined for diorite and saprolite composites and a substantial
proportion of gold (~30%) was recovered. A series of standard, 48-hour leach tests were performed on each
composite, with the effect of pre- grinding of the samples to up to 90% passing -200 mesh. The results
indicated a high gold extraction, from 92% to 97% on the hard rock samples, with only a small effect due to
grind size.