Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

OM.TO ·

Osisko Metals Outlines Signficant Reduction IN Dewatering Requirements at Pine Point

Mine Development & Operations

OSISKO METALS OUTLINES SIGNFICANT REDUCTION

IN DEWATERING REQUIREMENTS AT PINE POINT

(Montreal – October 27, 2021) Osisko Metals Incorporated (the "Company" or "Osisko Metals")

(TSX-V: OM; OTCQX: OMZNF; FRANKFURT: 0B51) is pleased to provide positive results from

the ongoing hydrogeological modelling and its application to dewatering costs at the Pine Point

Project, located in the NWT, Canada. A new 3D hydrogeological model was created and has

yielded significant reductions in the estimated water inflow rates into the proposed open pit and

shallow underground mines, relative to the estimates in the July 2020 PEA study . Reduction in

dewatering costs was estimated for a portion of the project, specifically in a sub-zone of the Main

Zone known as the C1 Cluster, which includes, potentially, three open pit and two underground

production areas.

Highlights:

• New data confirms that underground water flow at Pine Point is preferentially

controlled by subvertical structural discontinuities such as fracture zones or low-

displacement faults, with little evidence for significant ground water flow from

formational aquifers in either the Sulfur Point or Pine Point Formations.

• Potential for significant reductions in Operating and Sustaining Capital

Expenditures associated to dewatering over the Life of Mine (“LOM”) in the 2020

PEA economic model for the Pine Point project.

• Q1 2022 PEA Update will incorporate the new 3D hydrogeological model ,

dewatering volume estimates and all associated cost reductions.

The cost reductions are achieved by the aggregate effect of dewatering across all six production

areas in the C1 Cluster; since dewatering in the deepest area will reduce the amount of ground

water to be extracted from adjacent production areas. The ultimate objective is to focus on a given

cluster to maximize mining efficiency and thereby reduce the volumes of water to manage. The

integrated mining and hydrogeological modelling will be an iterative process . As the 2021 field

data is being integrated into the model, the same analysis will then be applied to all ten pit clusters

on the project. The results will be included in the PEA Update scheduled for release in Q1 2022.

Robert Wares, Chairman & CEO, commented: “The 2021 hydrogeological modelling confirms that

discrete faults, and not continuous f ormational aquifers, control water inflow in the mineralized

horizon at Pine Point . This is very different from aquifer models used in the 2020 PEA, which

resulted in very expensive life-of-mine dewatering estimates. Stated simply, managing water

influx along discrete zones is much simpler and cheaper than managing an entire aquifer , and

the C1 Cluster cost analysis demonstrates this . These results hopefully eliminate, once and for

all, investor concerns that water management at Pine Point would b e unwieldy. I wish to

congratulate the technical team alongside our consultants for this significant de-risking milestone.”

Jeff Hussey, President & COO, commented: “The hydrogeological analysis required the use of

2

the Company’s project scale 3D geological modeling developed after three years of data recovery,

analysis and re-interpretation. This 3D hydrogeological modelling process is being applied for the

first time at Pine Point and we are rapidly seeing highly encouraging results . We will now refine

both the hydrogeological model and, more importantly, the mining plan. We believe we will be

able to achieve lower dewatering rates than historically experienced through better mine

sequencing using the cluster strategy within the Life-of-Mine plan that is being integrated with the

new hydrogeological modelling results.”

Details of 2021 Hydrogeological Work

A total of 25 of 31 water wells were surveyed with Profile Tracer Testing (“PTT”), consisting of

mixing a tracer in the borehole without inducing any stress, followed by monitoring the tracer

dilution within the same hole . This allows for accurate identification of water-bearing sources,

including structural discontinuities, and their flow characterization.

PTT results continue to indicate that the groundwater flow is preferentially controlled by discrete

discontinuities (i.e., faults and or fracture zones) with insignificant inflow from formational aquifers,

including the dolomitized Sulfur Point Formation that hosts most of the zinc and lead Mineral

Resources at Pine Point . Locally, high-grade mineralization within porous dolomitized rocks is

associated to inflow since Prismatic high- grade deposits are also associated to the same

structural discontinuities discussed above.

This represents a significant shift from previous interpretations of underground water flow

modelling at Pine Point, which was almost exclusively based on formational aquifer flow within

the Sulfur Point Formation and/or the underlying stratigraphy . The water is mainly associated to

fault structures, therefore localized water well emplacement around these structures will be more

effective and are a far less costly water management strategy.

The next step is to complete the same analysis for the other Clusters across the Pine Point project

and confirm the overall reduction in operating costs and sustaining CAPEX. The C1 Cluster results

remain representative of the potential cost savings but the final reduction for the entire project has

yet to be determined from ongoing work.

Hydro-Ressources Inc. (“HRI”) started working on the model in Q1 2021, defining the

hydrogeology at Pine Point, using the Company’s 3D g eological model, LIDAR topographical

data, and GIS database to target hydrogeological testing and investigations to better characterize

water flow at Pine Point. Historical holes are also being used for testing where possible. The

testing methodologies include state- of-the-art measurement systems, such as Profile Tracer

Tests, slug tests, injection tests, velocity flow profiles, water samples and chemistry profiles, and

pump test analyses, among others.

Initially, the Company and HRI compiled existing hydrogeological reports, reference papers, and

used the 3D Geological model interpreted from historical and recent drill logs to define the

stratigraphic boundaries, including the Sulfur Point Formation, the main host of Tabular

mineralization at Pine Point. A structural analysis using drone surveys of Cominco Ltd. era open

pits was also used to interpret lineaments from different data sources (Magnetic survey, LIDAR,

aerial photographs, etc.) and these suggest where the structural discontinuities may be located.

3

C1 Cluster Dewatering Overview

Within the 6X6 kilometre area used for the C1 Cluster model domain, there are 4 historical open

pits with measured historical water inflow rates based on Stevenson (1984). The first step was to

calibrate the new hydrogeological model to simulate the inflow rates into the historical open pits

listed below.

Table 1: Hydrogeological model calibration results

Historical

Open Pit ID

Historical Inflows

(m3/d)

Simulated Inflows

(m3/d)

Simulated K Values

(m/s)

J69/70 78,823 83,067 6.4e-5

K62 38,246 35,796 4.3e-5

R61 50,287 49,541 4.3e-5

T58 51,617 50,776 5.8e-5

The model was calibrated using retro-engineering techniques to estimate historical inflow

measurements to enable more precise forecasting. These simulated K values are quite similar

to the observed K values in surrounding test holes that were recently measured (K Values

ranged from 2.3e-5 to 5.9e-5).

Once the calibration was completed, inflow rates were simulated in steady state conditions for all

open pits individually within Cluster C1, with no interference from the other pits. The following

table illustrates the results compared to the previous individual inflow rate analysis done in 2020.

Table 2: Hydrogeological open pit flow rates

Open Pit ID Individual Inflows

2020 (m3/d)

Inflows Current HRI Study

(m3/d)

M67 100,000 103,860

J68 235,000 72,879

K68 290,304 96,950

L65UG 110,000 129,390

Total 735,304 403,079

The total inflow into individual mining areas was estimated in 2020 at 735,304 m3/d, while the

current study estimates 403,079 m3/d. This represents a reduction of 46% of the estimated inflow

rates for open pits and underground mines included in Cluster C1.

A three year mine plan was prepared by Osisko Development and used by HRI for the

hydrogeological modelling of Cluster C1 . Monthly production rates were provided to simulate

inflow rates while maintaining water levels at 15m below the operational bench elevations. The

4

evolution of the inflow per mine is illustrated in the graph below.

Figure 1: Flow Rates versus Time for Cluster C1

The peak of in flow occurs in Month 28 with an inflow of 174, 000 m3/d. The average inflow is

estimated at 150,000 m3/d during operations for the period modelled versus 400,000 m3/d using

the 2020 PEA mine schedule. M67 and LG65(UG) are the main contributors of water, affecting

the piezometric surfaces in the surrounding environment, reduc ing inflow in the other proposed

open pit mines in the Cluster C1 domain model.

This new C1 Cluster mining strategy combined with the updated hydrogeological model

reduced the estimated inflow rates by an aggregate 63 % when compared to mining them

individually. This illustrates the importance of the Cluster strategy for mining open pits together

as a group to reduce dewatering volumes during mining operations by using appropriate field data

acquisition and simulation methods.

Considering that the inflow rate is estimated to be 10,800m3/d per well, it is possible to define the

number of wells to be installed for each open pit within Cluster C1. The following graph shows the

number of required wells over time for the C1 Cluster:

5

Figure 2: Estimated number of dewatering wells for Cluster C1 over time

Based on this analysis, dewatering efforts will be initially focused around the M67 pit with a total

of 16 strategically located operating wells being required during the 3-year Cluster 1 production

period. This compares to 66 wells used in the 2020 PEA for dewatering demand for production

from the same sources.

The M67 pit is located at an elevation of 215m amsl, and the bottom of the open pit is at 130m

amsl where an additional 15m margin was applied. The maximum required head is 100m (140psi)

for free discharge to surface. At 70% pumping efficiency, 250HP pumps would be used in each

400m diameter well.

Hydrogeological modelling enhancements will be an iterative process going forward using the

Feflow Version 7 software. This ongoing modelling will help to optimize the Company’s strategy

to pump less water and use less energy.

These results will then be included in a Site Wide Water model that will include surface water

models and will be used for Environmental Assessment purposes as well as the Q1 2022 PEA

Update and the upcoming Feasibility Study.

Osisko Development Corporation is also supporting the project as the Company’s internal design

engineers that will integrate the hydrogeological results into the new LOM plan that will be

qualified for the Q1 2022 PEA Update.

Qualified Person

Mr. Michael Verreault P.Eng. MSc, will be acting as the Qualified Person for Osisko Metals

regarding hydrogeological work. He is a Professional Geological Engineer with a Master’s degree

in Hydrogeology, and he is responsible for the technical data reported in this news release.

6

About Osisko Metals

Osisko Metals Incorporated is a Canadian exploration and development company creating value

in the base metal spac e. The Company controls one of Canada’s premier past -producing zinc

mining camps, the Pine Point Project, located in the Northwest Territories for which the 2020 PEA

has indicated an after -tax NPV of $500M and an IRR of 29.6%. T he Pine Point Project PEA is

based on current Mineral R esource Estimates that are amenable to open pit and shallow

underground mining and consist of 12.9Mt grading 6.29% ZnEq of Indicated Mineral Resources

and 37.6Mt grading 6.80% ZnEq of Inferred Mineral Resources . Please refer to the technical

report entitled “Preliminary Economic Assessment, Pine Point Project, Hay River, North West

Territories, Canada” dated July 30, which has been filed on SEDAR. The Pine Point Project is

located on the south shore of Great Slave Lake in the Northwest Territories, near infrastructure,

paved highway access , and has an electrical substat ion as well as 100 kilometres of viable

haulage roads already in place.

The current Mineral Resources mentioned in this press release conform to NI43- 101 standards

and were prepared by independent qualified persons, as defined by NI43- 101 guidelines. The

abovementioned Mineral Resources are not Mineral Reserves as they do not have demonstrated

economic viability. The quantity and grade of the reported Inferred Mineral Resources are

conceptual in nature and are estimated based on limited geological evidence and sampling.

Geological evidence is sufficient to imply but not verify geological grade and/or qualit y of

continuity. Zinc equivalency percentages are calculated using metal prices, forecasted metal

recoveries, concentrate grades, transport costs, smelter payable metals and charges (see

respective technical reports for details).

For further information on this press release, visit www.osiskometals.com or contact:

Robert Wares, CEO

Osisko Metals Incorporated

Email: [email protected]

www.osiskometals.com

Cautionary Statement on Forward-Looking Information

This news release contains "forward- looking information" within the meaning of applicable Canadian

securities legislation based on expectations, estimates and projections as at the date of this news release.

Any statement that involves predictions, expectations, interpretations, beliefs, plans, projections, objectives,

assumptions, future events or performance are not statements of historical fact and constitute forward-

looking information. This news release may contain forward-looking information pertaining to the Pine Point

Project, including, among other things , the results of the PEA and the IRR, NPV and estimated costs,

production, production rate and mine life; the expectation that the Pine Point Project will be an robust

operation and profitable at a variety of prices and assumptions; the expected high quality of the Pine Point

concentrates; the potential impact of the Pine Point Project in the Northwest Territories, including but not

limited to the potential generation of tax revenue and contribution of jobs; and the Pine Point Project having

the potential for minera l resource expansion and new discoveries. Forward- looking information is not a

guarantee of future performance and is based upon a number of estimates and assumptions of

7

management, in light of management’s experience and perception of trends, current conditions and

expected developments, as well as other factors that management believes to be relevant and reasonable

in the circumstances, including, without limitation, assumptions about: favourable equity and debt capital

markets; the ability to raise addit ional capital on reasonable terms to advance the development of its

projects and pursue planned exploration; future prices of zinc and lead; the timing and results of exploration

and drilling programs; the accuracy of mineral resource estimates; production costs; operating conditions

being favourable; political and regulatory stability; the receipt of governmental and third party approvals;

licences and permits being received on favourable terms; sustained labour stability; stability in financial and

capital markets; availability of equipment; and positive relations with local groups. Forward- looking

information involves risks, uncertainties and other factors that could cause actual events, results,

performance, prospects and opportunities to differ materia lly from those expressed or implied by such

forward-looking information. Factors that could cause actual results to differ materially from such forward-

looking information are set out in the Company’s public documents filed at www.sedar.com . Although the

Company believes that the assumptions and factors used in preparing the forward- looking information in

this news release are reasonable, undue reliance should not be placed on such information, which only

applies as of the date of this news release, and no assurance can be given that such ev ents will occur in

the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise

any forward-looking information, whether as a result of new information, future events or otherwise, other

than as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release.