Osisko Metals Intersects 9.15% Zinc + Lead and 0.54% Copper Over 10.0 Metres at Titan Zone, Key Anacon
Osisko Metals Intersects 9.15% Zinc + Lead and 0.54% Copper Over 10.0
Metres at Titan Zone, Key Anacon
MONTREAL, Feb. 12, 2019 -- Osisko Metals Incorporated (the “ Company” or “Osisko Metals”) (TSX-V: OM; FRANKFURT:
0B5) is pleased to announce results from 6 drill holes at the Titan Zone on its wholly owned Key Anacon project located 20 km
south of the city of Bathurst, New Brunswick.
Drill hole KAT-18-11 intersected 10.0 metres of massive sulphides grading 6.69% zinc, 2.46% lead, 0.54% copper and
58.79 g/t silver within a wider zone of mineralization (38.03 metres grading 5.06% zinc, 1.68% lead, 0.51% copper
and 44.45 g/t silver) , in an area 70 metres up plunge and southeast from drill hole KAT-18-08 that intersected 13.16% zinc
plus lead over 8.0 metres (see news release of November 13, 2018 and the Titan Zone Longitudinal Section and Table 1).
Additionally, drill hole KAT-18-23 intersected a copper-rich zone 25.00 metres below surface that graded 2.93%
copper, 4.83% zinc, 1.70% lead and 34.16 g/t silver over 4.75 metres also within a wider mineralized zone . Finally,
drill hole KAT-18-20 intersected a wide copper-rich zone of 0.97% copper, 0.42% zinc, 0.07% lead and 6.25 g/t silver
over 35.00 metres.
Table 1: Highlights of Significant Zinc-Lead and Copper intercepts; full details in Tables 2 and 3.
KEY ANACON - HIGHLIGHTS
Hole Name From To Width Zn Pb Cu Ag Zn+Pb
(m) (m) (m) % % % g/t %
KAT-18-11 149.80 187.83 38.03 5.06 1.68 0.51 44.45 6.74
including 166.00 176.00 10.00 6.69 2.46 0.54 58.79 9.15
KAT-18-16 285.00 294.05 9.05 0.68 0.24 1.46 11.28 0.92
KAT-18-20 553.00 588.00 35.00 0.42 0.07 0.97 6.25 0.49
KAT-18-21 588.50 614.00 25.50 0.05 0.02 0.81 3.10 0.07
KAT-18-23 22.00 38.25 16.25 1.95 0.73 1.30 19.97 2.68
including 31.50 36.25 4.75 4.83 1.70 2.93 34.16 6.53
Jeff Hussey, President and CEO of Osisko Metals, commented: "The Titan Zone continues to deliver impressive grades and
widths within 500 metres of surface. Not only does the Titan Zone contain zinc and lead massive sulphide mineralization, there
is also significant copper credits locally. Additionally, there is a parallel Copper Rich Zone that is worthy of follow up. To date,
the deepest intersection in the Titan Zone is 75 meters of massive sulphides at a vertical depth of 1,100 metres. We are eager
to further unlock the potential of both deposits at depth and along strike. None of the past, nor current Titan Zone results have
been used for estimating resources and we look forward to releasing a National Instrument 43-101 compliant Mineral Resource
Estimate on both deposits within the Key Anacon project in the next weeks."
About Key Anacon
The Key Anacon project is located approximately 20 km south of the town of Bathurst, New Brunswick and 16 km southeast
of the former Brunswick No.12 mine. It is accessible by paved roads. The property contains two known Bathurst-type
volcanogenic massive sulphide deposits containing zinc, lead, copper and silver. The Key Anacon Main Zone and Titan
Zone deposits are situated at the same stratigraphic horizon that hosted the Brunswick No. 12 & No. 6 mines. The
property covers approximately 12 kilometres of favorable Nepisiguit Falls stratigraphy that also extends onto the surrounding
claims held 100% by Osisko Metals.
No mineral resource estimates have been calculated under NI43-101 guidelines. Except for exploration programs conducted in
1992-1993 and 2000, almost all of the drilling was completed in the 1950’s and 60’s, prior to currently required standards for
quality assurance and quality control. The earlier drilling led to the establishment of a 460-metre-deep shaft, a ventilation raise,
eight levels and three sub-levels at the Main Zone. The Government of New Brunswick, Department of Energy and Resource
Development, Energy and Mines Division reports the Main Zone deposit as having a historical resource (Non-NI 43-101
compliant) of 1.87 million tonnes grading 6.93% Zn, 2.63% Pb, 0.16% Cu, and 84 g/t Ag (R. Irrinki, 1988, unpublished) in
multiple folded lenses. The deposit is open at depth and along strike.
Exploration potential at Key Anacon and the Company’s adjacent properties is considered to be excellent on the basis of the
presence of the Brunswick Horizon stratigraphy and the expansive zones of mineralization and alteration. Both the Titan Zone
and Main Zone are open at depth and along strike. Exploration and development in the 1950’s and 1960’s were terminated due
to the pullback of the zinc commodity price at that time. Since then, only two minor exploration programs were conducted by
major mining companies.
Osisko Metals would like to thank the New Brunswick government for the financial grant awarded through the New Brunswick
Junior Mining Assistance Program (NBJMAP). Through their continued support of the industry, Osisko Metals has used the
grant for work at Key Anacon to develop this premier asset in the Bathurst Mining Camp.
Table 2: Drill hole composite assay intervals.
Hole Name From To Drilled
Width
True
Width Zinc Lead Copper Silver Lead + Zinc
(metres) (metres) (metres) (metres) % % % g/t %
KAT-18-11 149.80 187.83 38.03 29.13 5.06 1.68 0.51 44.45 6.74
including 166.00 176.00 10.00 7.66 6.69 2.46 0.54 58.79 9.15
KAT-18-16 273.30 276.50 3.20 1.60 0.32 0.07 2.21 5.69 0.39
KAT-18-16 285.00 294.05 9.05 4.53 0.68 0.24 1.46 11.28 0.92
KAT-18-20 536.30 545.00 8.70 7.53 3.86 2.02 0.34 46.88 5.88
KAT-18-20 553.00 588.00 35.00 30.31 0.42 0.07 0.97 6.25 0.49
KAT-18-21 588.50 614.00 25.50 20.89 0.05 0.02 0.81 3.10 0.07
KAT-18-23* 22.00 38.25 16.25 14.07 1.95 0.73 1.30 19.97 2.68
including 31.50 36.25 4.75 4.11 4.83 1.70 2.93 34.16 6.53
KAT-18-24* 12.00 16.00 4.00 3.46 0.13 1.27 0.50 17.53 1.40
Note: Estimated True Widths are based on local geometry of mineralization adjacent to each drill hole.
Note: * Intensely weathered interval
Table 3: Drill hole information and location in New Brunswick Double Stereographic Projection (NBS).
Hole Name Area Easting Northing Elevation Azimuth Dip Depth
(metres)
KAT-18-11 Titan Zone 2,561,471 7,605,394 65.2 059 -53 326
KAT-18-16 Titan Zone 2,561,390 7,605,487 65.2 047 -70 404
KAT-18-20 Titan Zone 2,561,197 7,605,265 64.1 056 -61 635
KAT-18-21 Titan Zone 2,561,196 7,605,264 64.2 060 -65 680
KAT-18-23 Titan Zone 2,561,496 7,605,565 63.7 060 -43 101
KAT-18-24 Titan Zone 2,561,526 7,605,532 63.8 056 -44 101
Note regarding historical resource and Qualified Person
The above-mentioned historical resources do not conform to National Instrument 43-101 standards. The Company is reporting
the historical estimates for reference purposes only. Neither Osisko Metals nor its consultants have completed sufficient work
to verify the historical estimates and these should not be relied upon for investment purposes. A Qualified Person has not done
sufficient work to classify the historical estimates as NI43-101 compliant mineral resources and there is no guarantee that
such work will allow conversion of such historical resources.
Mr. Charles Kodors is the Qualified Person responsible for the technical data reported in this news release. He is a
Professional Geologist registered in New Brunswick and is the Exploration Manager for the Bathurst Mining Camp for Osisko
Metals Incorporated.
Quality Assurance / Quality Control
Osisko Metals adheres to a strict Quality Assurance and Quality Control program with regard to core handling, sampling,
transportation of samples and lab analyses. Drill core from Osisko Metals Bathurst Camp projects is securely transported to
its core facility in Bathurst, NB where it is logged and sampled. Samples selected for assay were shipped via secure
transportation to the Actlabs preparation facility in Fredericton, NB. Pulps were analyzed at Actlabs facility in Ancaster
Ontario. Zinc, lead and copper were analyzed by assay grade peroxide fusion (total digestion) with ICP-AES finish. Silver was
analyzed by gravimetric fire assay and gold by fire assay-atomic absorption.
About Osisko Metals
Osisko Metals is a Canadian exploration and development company creating value in the base metal space with a focus on
zinc mineral assets. The Company controls Canada’s two premier zinc mining camps. The Company’s flagship, the Pine Point
Mining Camp (“PPMC”), located in the Northwest Territories, has an Inferred Mineral Resource of 38.4 Mt grading 4.58% zinc
and 1.85% lead, making it the largest high grade, pit constrained zinc deposit in Canada (please refer to the Amended
Technical Report for further information). Within the Bathurst Mining Camp (“BMC”), located in northern New Brunswick, the
Company is focused on drilling and developing the Key Anacon Project, which previously had only sporadic exploration work
since the 1960’s. In 2019, the Company will continue to diligently develop and explore in order to confirm and grow both
projects. In Québec, the Company owns 42,000 hectares that cover 12 grass-root zinc targets that will be selectively advanced
through exploration.
For further information on Osisko Metals, visit www.osiskometals.com or contact:
Jeff Hussey Christina Lalli
President & CEO
Osisko Metals Incorporated
(514) 861-4441
Email: [email protected]
www.osiskometals.com
Director, Investor Relations
Osisko Metals Incorporated
(438) 399-8665
Email: [email protected]
www.osiskometals.com
Cautionary Note Regarding Forward-Looking Information
This news release contains "forward-looking information" within the meaning of applicable Canadian securities legislation
based on expectations, estimates and projections as at the date of this news release. Forward-looking information involves
risks, uncertainties and other factors that could cause actual events, results, performance, prospects and opportunities to
differ materially from those expressed or implied by such forward-looking information. Forward-looking information in this news
release includes, but is not limited to, the use of proceeds of the Offering; the timing and ability of the Corporation, if at all, to
obtain final approval of the Offering from the TSX Venture Exchange; an exemption being available under MI 61-101 and
Policy 5.9 of the TSX Venture Exchange from the minority shareholder approval and valuation requirements for each related
party transaction; objectives, goals or future plans; statements regarding exploration results and exploration plans. Factors
that could cause actual results to differ materially from such forward-looking information include, but are not limited to, capital
and operating costs varying significantly from estimates; the preliminary nature of metallurgical test results; delays in
obtaining or failures to obtain required governmental, environmental or other project approvals; uncertainties relating to the
availability and costs of financing needed in the future; changes in equity markets; inflation; fluctuations in commodity prices;
delays in the development of projects; the other risks involved in the mineral exploration and development industry; and those
risks set out in the Corporation's public documents filed on SEDAR at www.sedar.com. Although the Corporation believes that
the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue
reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance
can be given that such events will occur in the disclosed time frames or at all. The Corporation disclaims any intention or
obligation to update or revise any forward-looking information, whether as a result of new information, future events or
otherwise, other than as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities
commission or other regulatory authority has approved or disapproved the information contained herein.
A photo accompanying this announcement is available at http://www.globenewswire.com/NewsRoom/AttachmentNg/3572ac4e
-96e4-4976-b27f-830f72aac138