Osisko Gold Reports Third Quarter 2026 Results

Financings Production Results Financials

(All dollar amounts are expressed in Canadian dollars, unless stated otherwise)

HIGHLIGHTS
Q3 2026 (at September 30, 2026)
  • Financial: ~$1,501.9 million in cash, restricted cash and marketable securities, including ~$733.7 million in cash and cash equivalents, ~$691.2 million in restricted cash and ~$77.0 million in investments and marketable securities; sold 3,162 ounces of gold from small-scale test mining activities at the Tintic Project.
  • Financing: Completed 9.250% Senior Secured Notes offering for US$600.0 million in gross proceeds and repaid and terminated agreement in respect of the Appian 2025 Financing Facility; announced US$30 million equity private placement with Trafigura.
  • Cariboo Gold Project: Announced final investment decision to proceed with formal construction of the Cariboo Gold Project, with an expected first gold pour in Q1 2029 and commercial production in H2 2029; released new drill results from surface deeps and infill exploration program, and first set of new drilling at the Proserpine greenfield target; released final results and preliminary internal reconciliation analysis of its completed infill program in the Lowhee Zone; 16 drill rigs are active across all surface and underground programs at site.
  • Corporate: Completed name change to Osisko Gold Group Inc.
Subsequent to Q3 2026
  • Corporate: Elijah Tyshynski assumed role of CFO, succeeding Alexander Dann; closed US$30 million equity private placement with Trafigura; appointed Cameron Carter as VP, Construction Operations at Barkerville Gold Mines, and announced departure of Sarah Harrison, VP, Permitting and Compliance.
  • Cariboo Gold Project: Provided construction progress update and announced new drilling results from ongoing definition infill program in the Lowhee Zone.
 
   

TORONTO, Nov. 12, 2026 (GLOBE NEWSWIRE) -- Osisko Gold Group Inc. (NYSE: OGG, TSXV: OGG) ("Osisko Gold" or the "Company") reports its financial and operating results for the three and nine months ended September 30, 2026 ("Q3 2026").

Q3 2026 HIGHLIGHTS

Operating, Financial and Corporate Updates

  • As at September 30, 2026, the Company had approximately $1,501.9 million in cash, restricted cash and investments, including $733.7 million in cash and cash equivalents, $691.2 million in restricted cash and $77.0 million in investments and marketable securities. Restricted cash comprises amounts held in segregated accounts established under the Senior Secured Notes (as defined herein) available for disbursement upon satisfaction of applicable conditions, and subscription proceeds received in advance of closing of the Trafigura Equity Investment (as defined herein). Upon closing of the Senior Secured Notes, the Company had US$900 million aggregate principal amount of notes outstanding, comprising (i) US$300 million under the 4.125% convertible senior notes due June 15, 2031 (the "Convertible Notes"), and (ii) US$600 million under the 9.250% senior secured notes due October 1, 2031 (the "Senior Secured Notes").
  • The Company generated $19.3 million in revenues ($4.4 million in Q3 2025) and $9.9 million in cost of sales ($3.0 million in Q3 2025) from the sale of 3,162 gold ounces from small-scale test mining activities and direct shipping of mineralized material at the Tintic Project, generating an operating income of $3.8 million ($33.2 million loss in Q3 2025), after deducting other operating and general administrative costs.
  • On July 8, 2026, the Company announced new drill results from 11 surface diamond drill holes totaling 8,971 metres completed between December 2025 and April 2026 as part of an ongoing Cariboo Deeps and near mine gap infill exploration program at the Cariboo Gold Project. Approximately 65% of drilling transected areas outside the current footprint of the Cariboo Gold deposit, and results confirmed the presence of high-grade mineralization to a maximum vertical depth of 718 metres below surface in hole IM-26-001.
  • On July 14, 2026, the Company's name change to "Osisko Gold Group Inc." became effective and, on July 20, 2026, the Common Shares began trading under the new symbol "OGG" on each of the TSXV and the NYSE. The trading symbols for the Company's listed warrants also changed effective July 20, 2026: (i) warrants trading under "ODVWZ" on the Nasdaq Stock Market and "ODV.WT.U" on the TSXV changed to "OGGWZ" and "OGG.WT.U", respectively; and (ii) warrants trading on the TSXV under "ODV.WT.A" and "ODV.WT.V" changed to "OGG.WT.A" and "OGG.WT.V", respectively.
  • On July 22, 2026, the Company announced that, through its subsidiary Barkerville, it entered into a Support and Benefits Agreement (the "Support Agreement") with the District of Wells, British Columbia, effective July 21, 2026, to support social and economic initiatives within the District of Wells in respect of the Cariboo Gold Project. Over its three-year term, the Support Agreement contemplates voluntary financial contributions by the Company of up to $3.0 million in aggregate, subject to the Company's sole discretion and continued participation under the Support Agreement.
  • On July 23, 2026, the Company announced final results and preliminary internal reconciliation analysis of its previously completed infill drilling program in the Lowhee Zone of the Cariboo Gold Project. The preliminary internal reconciliation analysis of two localized areas, comprising an aggregate total of 17,072 metres of infill drilling in 185 diamond drill holes, illustrated deposit variability consistent with expectations, and is subject to ongoing evaluation and modelling.
  • On August 5, 2026, the Company announced the first set of new drilling results from 14 surface diamond drill holes totaling 6,463 metres completed between February and May 2026 as part of an ongoing exploration program on the Proserpine regional greenfield target, located within the broader Cariboo Gold Project property boundary. Results to date confirm the presence of an emerging gold mineralized system comprising high-grade structures and broader zones of lower-grade mineralization that may indicate potential for bulk mining methods.
  • On August 20, 2026, Barkerville entered into an amended and restated credit agreement with funds advised by Appian Capital Advisory Limited in respect of the US$450 million 2025 Financing Facility for the Cariboo Gold Project. The amendment provided more favourable covenants, lowered the overall cost of capital, and extended by 12 months the Company's option to settle accrued interest in kind. The 2025 Financing Facility was repaid and terminated on September 30, 2026, using proceeds from the Senior Secured Notes offering.
  • On August 25, 2026, the Company announced that Alexander Dann had advised the Company of his intention to retire and would be stepping down from his role as Chief Financial Officer ("CFO") and Vice President, Finance. As part of the Company's planned leadership succession process, Elijah Tyshynski was subsequently appointed CFO and joined the senior leadership team following a period of transition, bringing extensive financial and capital markets experience as the Company enters its next stage of growth.
  • On September 14, 2026, the Board of Directors made a formal positive construction decision on the Cariboo Gold Project, with an expected first gold pour in Q1 2029 and commercial production in H2 2029. The Company also announced a go-forward capital obligation estimate update of $990 million (US$717 million) from August 1, 2026, supported by total available and proposed estimated sources of capital of up to $1,637 million.
  • On September 14, 2026, the Company and Barkerville entered into agreements with Trafigura Canada Limited ("Trafigura") and Urion Investments Holdings Limited ("Urion"), an affiliate of Trafigura, comprising: (i) a subscription agreement for 9,554,141 Common Shares at US$3.14 per Common Share for gross proceeds of approximately US$30 million (the "Trafigura Equity Investment"); (ii) offtake agreements for 100% of the gold concentrate (or until 80,000 dry metric tons are delivered) and gold doré for the first four years of production at the Cariboo Gold Project (the "Offtake Agreements"); and (iii) non-binding terms and an exclusivity period in respect of a potential subordinated gold prepayment facility of up to US$120 million and a further six years of offtake (the "Prepay Facility").
  • On September 23, 2026, the Company priced an upsized offering of US$600 million (from US$500 million) aggregate principal amount of 9.250% Senior Secured Notes due 2031, and on September 30, 2026, closed the offering. Net proceeds of approximately US$577.0 million were used to repay all amounts outstanding and terminate all commitments under the 2025 Financing Facility with Appian (totaling approximately US$120.8 million), fund a segregated interest reserve account equal to the first five interest payments on the Senior Secured Notes, and fund segregated disbursement accounts to advance the Cariboo Gold Project.

Cariboo Gold Project – British Columbia, Canada (100%-owned)

Construction Activities

On September 14, 2026, the Company announced the positive final investment decision ("FID") to proceed with the formal construction of the Cariboo Gold Project (the "Project") and provided a go-forward capital obligation estimate ("COE") update for the Project. The Company remains focused on continuing to advance detailed engineering, procurement, and construction activities, as well as completing certain exploration and infill conversion drilling activities, as previously disclosed, toward achieving first gold pour in the first quarter of 2029 and commercial production in the second half of 2029.

On October 27, 2026, the Company provided a construction activities progress update on the Project (refer to news release entitled "Osisko Gold Provides Construction Progress Update on the Cariboo Gold Project"), with key highlights noted below:

Table 1: Cariboo Gold Project Progress Highlights1,7
Costs Incurred2
(to September 30, 2026)
Remaining
Go-Forward COE3
(September 30, 2026)
Estimated Project
Completion
4
(based on costs incurred)
Detailed Engineering | Procurement Status5
(September 30, 2026)
Anticipated
Q4 2026 Spend6
~$355 million ~$907 million ~28% ~42% | >50% $183 million
  1. Refer to the Q3 2026 MD&A for more detail.
  2. Including indirects and owners' costs, of which approximately $83 million was incurred from August 1 to September 30, 2026.
  3. As of September 30, 2026, the estimated remaining cost to complete construction is approximately $907 million on an incurred basis, net of costs incurred to date, leases and estimated pre-production revenue. The estimate is calculated from the Company's updated go-forward COE of approximately $990 million as at July 31, 2026, less the approximately $83 million of costs incurred from August 1 to September 30, 2026.
  4. Based on cumulative costs incurred through September 30, 2026, relative to the go-forward capital obligation estimate and incurred pre-construction costs as at July 31, 2026, and announced on September 14, 2026.
  5. Detailed engineering is approximately 42% complete. Over 50% of procurement packages have been awarded, with principal long-lead items largely secured and remaining contract packages being awarded or in progress, representing approximately $360 million in commitments project-to-date.
  6. The anticipated Project spend for the balance of 2026 is above the initial guidance of 10% of the total estimated project costs provided at FID, and is primarily attributable to the accelerated procurement of certain long-lead time items related to surface infrastructure items, as well as mining fleet components, which were originally contemplated to be expended later in the Project construction period. The Company expects to provide updated guidance on the expected expenditures breakdown over the remaining construction period in Q1 2027, along with its regular Project progress update.
  7. On September 14, 2026, the Company announced a formal construction decision for the Cariboo Gold Project, with an updated go-forward capital expenditures estimate. Management considered whether these updates, together with other factors such as gold prices and mineral reserves, constituted indicators of impairment as at September 30, 2026. Management concluded that no indicators of impairment existed and no impairment test was performed as at September 30, 2026. Refer to Note 5 of the unaudited condensed interim consolidated financial statements for further detail.

Project Virtual Site Tour

To view a 360-degree virtual site tour showcasing construction progress at the Cariboo Gold Project as of October 2026, please visit the Company's profile on the VRIFY platform: https://vrify.com/decks/24611.

Exploration & Resource Conversion

The Cariboo Gold Project has three primary areas of exploration drilling activity currently underway:

Table 2: Drilling Activity as at September 30, 2026
Drilling activity Targets 3 months
(metres drilled)
9 months
(metres drilled)
Regional exploration: This program seeks to identify and define new prospective potential mineral resource targets within the broader Cariboo regional land package. Proserpine, Yanks Peak, QR Regional 9,936 16,401
Underground conversion & exploration: To support the availability of sufficient mineable stopes to meet the contemplated mill throughput, the Company is undertaking conversion drilling in and around the existing mine plan, with the objective of upgrading these areas to higher levels of geological confidence, in advance of commercial production. Where access is available, this drilling is being conducted from underground drill stations, using existing development infrastructure. Lowhee Infill, Lowhee Exploration, Cow Infill 8,709 21,454
Surface conversion & exploration: Consistent with the objectives of the underground conversion & exploration program, the Company is also conducting surface drilling to target certain areas of interest that are not yet accessible from existing underground infrastructure. CGP Deep, Gap and Surface, and QR Mine 14,177 27,811
Total Drilling Activity1   32,822 65,666
  1. To date, full assay results have been released for approximately 25,000 metres of aggregate drilling completed, with results for the remaining completed drilling pending.

Development of the Cow drill gallery continues, with infill drilling to support mineral resource conversion from this area expected to commence in Q4 2026. A total of sixteen drill rigs are currently active at site, with seven focused on infill drilling and near-mine mineral resource expansion at the Cariboo Gold Project. Nine drill rigs are currently testing regional exploration targets across the broader property, and are expected to complete these activities by the end of 2026. By year-end 2026, the Company expects to have completed approximately half of the planned 160,000 metres of drilling at the Project, along with approximately 50,000 metres on regional targets.

FIGURE 1: Cariboo Gold Project underground development; completed (grey) and planned near-term (blue).


Project Construction Photos

FIGURE 2: Mine Site Complex overview.


FIGURE 3: Valley portal excavation at the Mine Site Complex – Final bench nearing completion.


FIGURE 4: Main water treatment plant foundation works continue at the Mine Site Complex.


FIGURE 5: Bonanza Ledge overview.


Tintic Project – Utah, U.S.A. (100%-owned)

  • Trixie Small-Scale Test Mining Activities: In the third quarter, the Company continued small-scale test mining activities and direct shipping of mineralized material which generated sales of 3,162 ounces of gold. In the nine months ended September 30, 2026, test mining and processing activities generated the sale of an estimated 8,980 gold ounces, including direct shipping of 7,923 tonnes at an estimated average grade of 39.15 grams per tonne of gold with an expected average payability factor of 89.5%. Test mining is anticipated to continue in Q4 2026, into 2027 and 2028.
  • Eureka Standard Project and Drilling Activities: In Q3 2026, the Company commenced the Eureka Standard project, an underground ramp intended to provide access to the historic Eureka Standard mine for further underground exploration. The project's budget is expected to be approximately US$14.0 million, with works to be carried out through 2027. In Q3 2026, the Company entered into a drilling services agreement for two diamond drill rigs, which provides for a minimum drilling program of 16,400 feet (4,999 metres): 10,400 feet (3,170 metres) of underground infill drilling at the Trixie test mine and 6,000 feet (1,829 metres) of surface drilling at Eureka Standard. Underground infill drilling at Trixie began in late August 2026, and 738 feet (225 metres) had been drilled as at September 30, 2026. The surface program at Eureka Standard is expected to commence in Q4 2026. The remaining minimum drilling program is expected to be completed within the next twelve months at an estimated cost of approximately US$5.0 million. All planned activities associated with the Eureka Standard ramp project and related drilling are expected to be funded internally from gold sales generated from test mining and direct shipping of mineralized material.
  • While management continues to evaluate options for next steps at the Tintic Project, activities are expected to focus on continued test mining at Trixie, including potential additional direct shipping of mineralized material from the Trixie test mine, the underground infill drilling program at Trixie, the surface drilling program at Eureka Standard and development of the Eureka Standard ramp.

SUBSEQUENT TO Q3 2026

  • On October 1, 2026, Elijah Tyshynski assumed the role of Chief Financial Officer of the Company, succeeding Alexander Dann.
  • On October 5, 2026, the Company announced new results from its ongoing definition infill drilling program on 10-15 m target spacing totaling 3,933 m in 36 holes drilled from the 1290 m level in the Lowhee Zone of the Project.
  • On October 9, 2026, the Company closed the Trafigura Equity Investment, issuing 9,554,141 Common Shares to Urion at a price of US$3.14 per Common Share for gross proceeds of approximately US$30 million ($42.3 million), which will be used for the development of the Cariboo Gold Project. Urion entered into a voting support agreement with the Company containing customary standstill and lock-up provisions. Negotiations toward a definitive agreement for the Prepay Facility remain ongoing, with definitive agreements expected to be finalized in Q4 2026.
  • On October 27, 2026, the Company provided a construction update on progress made at the Project, which continues to advance on schedule toward first gold pour targeted in Q1 2029 and commercial production expected in H2 2029.
  • On November 2, 2026, the Company announced the appointment of Mr. Cameron Carter as Vice President, Construction Operations of Barkerville Gold Mines Ltd., the Company's wholly-owned subsidiary. The Company also announced that Sarah Harrison, Vice President, Permitting and Compliance, departed the Company to pursue other opportunities. Greenwood Environmental Inc. has assumed responsibility for permitting and compliance matters, and Ms. Harrison will remain available in an advisory capacity.

Consolidated Financial Statements

The Company's unaudited condensed interim consolidated financial statements (the "Financial Statements") and related management's discussion and analysis ("MD&A") for the three and nine months ended September 30, 2026 have been filed with Canadian securities regulatory authorities and the U.S. Securities and Exchange Commission. These filings are available on the Company's website at www.osiskogold.ca, on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov) under Osisko Gold's issuer profile.

Qualified Persons

The scientific and technical information contained in this news release has been reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Gold, a "qualified person" within the meaning of NI 43-101. Verification includes core photo and three-dimensional review of logged drillhole data and assays consistent with the Company's standard procedures.

The exploration results disclosed in this news release are based on incomplete data and are preliminary in nature. There are no known drilling, sampling, recovery, or other factors that could materially affect the accuracy or reliability of the data; however, readers are cautioned that additional drilling and sampling may result in materially different results than those presented herein.

Technical Reports

Scientific and technical information relating to the Cariboo Gold Project and the 2025 feasibility study on the Cariboo Gold Project is supported by the technical report, titled "NI 43-101 Technical Report, Feasibility Study for the Cariboo Gold Project, District of Wells, British Columbia, Canada" dated June 11, 2025 (with an effective date of April 25, 2025) (the "Cariboo Technical Report").

Scientific and technical information relating to the Tintic Project and the current mineral resource estimate for the Trixie deposit (the "2024 Trixie MRE") is supported by the technical report titled "NI 43-101 Technical Report, Mineral Resource Estimate for the Trixie Deposit, Tintic Project, Utah, United States of America" dated April 25, 2024 (with an effective date of March 14, 2024) (the "Tintic Technical Report" and, together with the Cariboo Technical Report, the "Technical Reports").