Osisko Development Reports Fourth Quarter and Year-End 2024 Results

Financings Financials

ODV NYSE TSXV News Release

www.osiskodev.com Page 1 of 6

OSISKO DEVELOPMENT REPORTS FOURTH QUARTER AND YEAR-END 2024

RESULTS

(All dollar amounts are expressed in Canadian dollars, unless stated otherwise)

Montreal, Québec, March 28, 202 5 – Osisko Development Corp. (NYSE: ODV, TSXV: ODV)

("Osisko Development" or the "Company") reports its financial and operating results for the three

and twelve months ended December 31, 2024 ("Q4 2024").

Q4 2024 HIGHLIGHTS

Operating, Financial and Corporate Updates:

• As of December 31, 2024, the Company had approximately $ 106.7 million in cash and cash

equivalents. Approximately $36.0 million (US$25.0 million) was outstanding as of the end of Q4

2024 under the delayed draw term loan with National Bank of Canada, which matures on October

31, 2025.

• The Company completed a non-brokered private placement of units pursuant to which it issued

an aggregate of 19,163,410 units at a price of US$1.80 per unit for gross proceeds of

approximately US$34.5 million (the "2024 Non-Brokered Private Placement"). The 2024

Non-Brokered Private Placement was completed in two tranches comprised of the issuance of

(i) 13,426,589 units at a price of US$1.80 per unit for gross proceeds of approximately US$24.2

million, which tranche closed on October 1, 2024, and (ii) 5,736,821 units at a price of US$1.80

per unit for gross proceeds of approximately US$10.3 million, which tranche closed on October

11, 2024. Each unit was comprised of one Common Share and one Common Share purchase

warrant of the Company entitling the holder thereof to purchase one Common Share at a price

of US$3.00 on or prior to October 1, 2029.

• On November 12, 2024, the Company completed a brokered private placement pursuant to

which it issued an aggregate of 31,946,366 units at a price of US$1.80 per unit for aggregate

gross proceeds of approximately US$57.5 million, including the exercise in full of the option

granted to the agents (the "2024 Brokered Private Placement"). Each unit was comprised

of one Common Share and one Common Share purchase warrant of the Company entitling the

holder thereof to purchase one Common Share at a price of US$3.00 on or prior to October 1,

2029. In connection with the 2024 Brokered Private Placement, the agents were paid a cash

commission equal to 4.5% of the aggregate gross proceeds.

• On December 5, 2024, Mr. Stephen Quin was appointed as independent director to the

Company's board of directors and , in connection thereof , was subsequently granted 80,000

deferred share units of the Company on December 19, 2024.

• On December 12, 2024, Ms. Marina Katusa resigned from the Company's board of directors.

Cariboo Gold Project – British Columbia, Canada (100%-owned)

• Fully Permitted Status. On November 20, 2024, the Company was granted permits pursuant

to the Mines Act (British Columbia) for its Cariboo Gold Project. Subsequently, on December 12,

2024, the Company was granted permits pursuant to the Environmental Management Act

(British Columbia) for the Cariboo Gold Project. Together with the Mines Act (British Columbia)

permits, these approvals mark the successful completion of the permitting process for key

approvals, solidifying the Cariboo Gold Project's shovel-ready status.

o The Mines Act (British Columbia) permits grant the Company the ability to proceed with

the construction, operation and reclamation activities on each of the sites outlined within

www.osiskodev.com Page 2 of 6

the scope of the Project. The Environmental Management Act (British Columbia) permits

pertain to any project-related discharges to the environment, including water and air,

and the framework and limitations thereof, within the areas outside of the immediate

mine site boundaries.

o Work is ongoing with the Ministry of Water, Land and Resource Stewardship and the

Ministry of Forests on obtaining all necessary approvals for the construction of the

transmission line.

o On November 7, 2024, the Company announced that , while it had yet to reach an

agreement with the Xatśūll First Nation, it remained committed to ongoing engagement

and consultation.

• Project Financing. The Company is actively engaged in ongoing discussions on various funding

options, including a comprehensive project construction financing package, for the development

of the Cariboo Gold Project.

• Pre-Construction Activities. During Q1 2024, under an existing provincial permit, the

Company commenced an underground development drift from the existing Cow Portal into the

Cariboo Gold Project's Lowhee Zone to extract a bulk sample of up to 10,000 tonnes of

mineralized material.

o 100% of the underground development has been s uccessfully completed , totalling

approximately 1,172 m, to access the target area.

o The extraction, sampling, assaying, and analysis of mineralized material from the target

zone is currently ongoing. Approximately 7,400 tonnes of material has been extracted

to date. Lengthy timeframes for receipt of assay s and analysis of the results have

extended completion of the bulk sampling program into Q2 2025. Once all information

is available, a reconciliation process to compare the bulk sample results with the

predicted tonnes and grade will be undertaken.

• Optimized Feasibility Study. The Company is in advanced stages of completing an optimized

feasibility study ("OFS") for the Cariboo Gold Project. The OFS will incorporate opportunities to

enhance and streamline mine development and the process flowsheet, supporting an accelerated

development timeline to reach 4,900 tonnes per day throughput earlier than previously

contemplated. It will also reflect updated metal price and foreign exchange assumptions .

Additionally, t he OFS will integrate updated operating a nd capital cost estimates , while

considering ways to reduce and mitigate any potential capital and operating cost pressures. The

OFS base case will remain aligned with the existing permitting framework.

Figure 1: Cariboo Gold Project – Permitting Timeline Summary

www.osiskodev.com Page 3 of 6

Tintic Project – Utah, U.S.A. (100%-owned)

• Phase I Regional Drilling. In 2024, the Company completed t wo surface diamond drill holes

totalling approximately 2,920 m (9,581 ft) at the Big Hill target area testing for copper -gold-

molybdenum porphyry mineralization potential. Based on the geological information from these

drill holes, the Company identified several high-priority targets for a next phase of the porphyry

exploration program.

• Phase II Regional Drilling. As part of the ongoing Phase II regional drilling program initiated

in December 2024, the Company is advancing the completion of two drill holes on the Big Hill

West and Zuma porphyry targets, expected to be completed in the coming months.

San Antonio Gold Project – Sonora State, Mexico (100%-owned)

• The San Antonio Gold Project remains in care and maintenance.

• The Company is awaiting further guidance from the Mexican government regarding the

permitting process and the status of open-pit mining in the country.

• The Company continues to conduct a strategic review of the project and engaged a financial

advisor in connection thereof. The strategic review includes, among others, exploring the

potential for a financial or strategic partner in the asset or a full or partial sale of the asset.

KEY UPCOMING MILESTONES

Key Project

Milestones

Expected Timing

of Completion

Anticipated

Remaining Costs*

Cariboo Gold Project(1)

Permitting Completed – Q4 2024 $nil

Electrical and Communication Q1 2025 $0.7 million

Bulk Sample Q2 2025 $6.4 million

CGP Underground Development Q2 2025 $8.7 million

Updated CGP Feasibility Q2 2025 $2.5 million

Environmental, other pre-construction work & roadheader Q2 2025 $7.2 million

Water and Waste Management Q4 2025 $7.5 million

Tintic Project

Regional Drilling – Phase I Completed – Q2 2024 $nil

Regional Drilling – Phase II Q2 2025 $5.0 million

*as at December 31, 2024

Notes:

(1) The expenditures disclosed in this table include amounts approved by the Board of Directors up until the end of June 2025.

Additional expenditures will be required to complete certain of the milestones and are subject to approval by the Board of

Directors.

SUBSEQUENT TO Q4 2024

• On January 9, 2025, the Company announced that Mr. David Rouleau was appointed as Vice

President, Project Development, and Mr. Éric Tremblay resigned from his position as Chief

Operating Officer of the Company.

• On February 3, 2025, the Company released drilling results from its 2024 initial exploration and

historic data validation infill drill campaign at its Quesnel River Mine Prospect located within the

Company's wider Cariboo Gold Project.

• On March 26, 2025, the Company appointed Philip Rabenok as Vice President, Investor

Relations. Mr. Rabenok joined Osisko Development in November 2022 as Director, Investor

Relations.

www.osiskodev.com Page 4 of 6

2024 Year-End Disclosure Documents

The Company's annual information form (" AIF") for the year ended December 31, 2024 , audited

consolidated financial statements (the "Financial Statements") and related management's discussion

and analysis ("MD&A") for the three and twelve months ended December 31, 2024 have been filed with

Canadian securities regulatory authorities. Osisko Development has also filed its Annual Report Form

40-F consisting of its AIF, Financial Statements and MD&A for the year ended December 31, 2024 with

the U.S. Securities and Exchange Commission.

These filings are available on the Company's website at www.osiskodev.com, on SEDAR+

(www.sedarplus.ca) and on EDGAR ( www.sec.gov) under Osisko Development's issuer profile. Hard

copies of these documents will be provided to shareholders of the Company upon written request to the

Company's Investor Relations department, 1100, Av. des Canadiens-de-Montreal, Suite 300, Montreal,

Quebec, Canada H3B 2S2 or to [email protected].

Qualified Persons

The scientific and technical information contained in this news release has been reviewed and approved

by Daniel Downton, P.Geo., Chief Resource Geologist of Osisko Development, a "qualified person" within

the meaning of National Instrument 43 -101 – Standards of Disclosure for Mineral Projects ("NI 43-

101").

Technical Reports

Information relating to the Cariboo Gold Project and the current feasibility on the Cariboo Gold Project

is supported by the technical report titled "Feasibility Study for the Cariboo Gold Project, District of Well,

British Columbia, Canada", dated January 10, 2023 (amended January 12, 2023) with an effective date

of December 30, 2022 (the "Cariboo Technical Report").

Information relating to the Tintic Project and the current mineral resource estimate for the Trixie deposit

(the "2024 Trixie MRE") is supported by the technical report titled "NI 43-101 Technical Report, Mineral

Resource Estimate for the Trixie Deposit, Tintic Project, Utah, United States of America" dated April 25,

2024 (with an effective date of March 14, 2024) (the "Tintic Technical Report").

Information relating to San Antonio Gold Project is supported by the technical report titled " NI 43-101

Technical Report for the 2022 Mineral Resource Estimate on the San Antonio Project, Sonora, Mexico ",

dated July 12, 2022 (with an effective date of June 24, 2022) (the " San Antonio Technical Report",

collectively, with the T intic Technical Report and the Cariboo Technical Report, the " Technical

Reports").

For readers to fully understand the information in the Technical Reports, reference should be made to

the full text of the Technical Reports in their entirety, including all assumptions, qualifications and

limitations thereof. The Technical Reports are intended to be read as a whole, and sections should not

be read or relied upon out of context. The Technical Reports were prepared in accordance with NI 43 -

101 and are available electronically on SEDAR+ ( www.sedarplus.ca) and on EDGAR ( www.sec.gov)

under Osisko Development's issuer profile and on the Company's website at www.osiskodev.com.

End Notes (excluding tables)

1. In this news release the Company uses certain abbreviations, including: meters ("m"); feet ("ft").

www.osiskodev.com Page 5 of 6

ABOUT OSISKO DEVELOPMENT CORP.

Osisko Development Corp. is a North American gold development company focused on past -producing

mining camps located in mining friendly jurisdictions with district scale potential. The Company's

objective is to become an intermediate gold producer by advancing its flagship fully permitted 10 0%-

owned Cariboo Gold Project, located in central B.C., Canada. Its project pipeline is complemented by

the Tintic Project in the historic East Tintic mining district in Utah, U.S.A., and the San Antonio Gold

Project in Sonora, Mexico —brownfield properties with significant exploration potential, extensive

historical mining data, access to existing infrastructure and skilled labour. The Company's strategy is to

develop attractive, long-life, socially and environmentally responsible mining assets, while minim izing

exposure to development risk and growing mineral resources.

For further information, visit our website at www.osiskodev.com or contact:

Sean Roosen Philip Rabenok

Chairman and CEO Vice President, Investor Relations

Email: [email protected] Email: [email protected]

Tel: +1 (514) 940-0685 Tel: +1 (437) 423-3644

CAUTIONARY STATEMENTS

Cautionary Statement Regarding Estimates of Mineral Resources

This news release uses the terms measured, indicated and inferred mineral resources as a relative measure of the level of confidence

in the resource estimate. Readers are cautioned that mineral resources are not mineral reserves and that the economic viabi lity of

resources that are not mineral reserves has not been demonstrated. The mineral resource estimate disclosed in this news relea se

may be materially affected by geology, environmental, permitting, legal, title, socio-political, marketing or other relevant issues. The

mineral resource estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum's "CIM Definition

Standards on Mineral Resources and Mineral Reserves" incorporated by reference into NI 43-101. Under NI 43 -101, estimates of

inferred mineral resources may not form the basis of feasibility or pre -feasibility studies or economic studies except for preliminary

economic assessments. Readers are cautioned not to assume that further work on the stated resources will lead to mineral reserves

that can be mined economically.

Cautionary Statement Regarding Financing Risks

The Company's development and exploration activities are subject to financing risks. At the present time, the Company has

exploration and development assets which may generate periodic revenues through test mining, but has no mines in the commercial

production stage that generate positive cash flows. The Company cautions that test mining at its operations could be suspended at

any time. The Company's ability to explore for and discover potential economic projects, and then to bring them into production, is

highly dependent upon its ability to raise equity and debt capital in the financial markets. Any projects that the Company de velops

will require significant capital expenditures. To obtain such funds, the Company may sell additional securities including, but not limited

to, the Company's shares or some form of convertible security, the effect of which may result in a substantial dilution of the equity

interests of the Company's Shareholders. Alternatively, the Company may also sell a part of its interest in an asset in order to raise

capital. There is no assurance that the Company will be able to raise the funds required to continue its exploration programs and

finance the development of any potentially economic deposit that is identified on acceptable terms or at all. The failure to obtain the

necessary financing(s) could have a material adverse effect on the Company 's growth strategy, results of operations, financial

condition and project scheduling.

Cautionary Statement Regarding Test Mining Without Feasibility Study

The Company cautions that its prior decision to commence small -scale underground mining activities and batch vat leaching at the

Trixie test mine was made without the benefit of a feasibility study, or reported mineral resources or mineral reserves, demonstrating

economic and technical viability, and, as a result there may be increased uncertainty of achieving any particular level o f recovery of

material or the cost of such recovery. The Company cautions that historically, such projects have a much higher risk of economic and

technical failure. Small scale test -mining at Trixie was suspended in December 2022 , resumed in the second qu arter of 2023, and

suspended once again in December 2023 . If and when small-scale test-mining recommences at Trixie, there is no guarantee that

production will continue as anticipated or at all or that anticipated production costs will be achieved. The failure to continue production

may have a material adverse impact on the Company's ability to generate revenu e and cash flow to fund operations. Failure to

achieve the anticipated production costs may have a material adverse impact on the Company's cash flow and potential profitability.

In continuing operations at Trixie after closing, the Company has not based its decision to continue such operations on a feasibility

study, or reported mineral resources or mineral reserves demonstrating economic and technical viability.

Cautionary Statement to U.S. Investors

The Company is subject to the reporting requirements of the applicable Canadian securities laws and as a result reports infor mation

regarding mineral properties, mineralization and estimates of mineral reserves and mineral resources, including the information in its

technical reports, financial statements, MD&A and this news release, in accordance with Canadian reporting requirements, whic h are

governed by NI 43-101. As such, such information concerning mineral properties, mineralization and estimates of mi neral reserves

and mineral resources, including the information in its technical reports, financial statements, MD&A and this news release, is not

comparable to similar information made public by U.S. companies subject to the reporting and disclosure requi rements of the U.S.

Securities and Exchange Commission ("SEC").

www.osiskodev.com Page 6 of 6

CAUTION REGARDING FORWARD LOOKING STATEMENTS

Certain statements contained in this news release may be deemed "forward-looking statements" within the meaning of the United

States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable Canadian

securities legislation (together, "forward -looking statements"). These forward -looking statements, by their nature, require Osisko

Development to make certain assumptions and necessarily involve known and unknown risks and uncertainties that could cause

actual results to differ materially from those expressed or implied in these forward-looking statements. Forward-looking statements

are not guarantees of performance. Words such as "may", "will", "would", "could", "expect", "believe", "plan", "anticipate", "intend",

"estimate", "continue", or the negative or comparable terminology, as well as terms usually used in the future and the conditional,

are intended to identify forward -looking statements. Information contained in forward -looking statements is based upon certain

material assumptions that were applied in drawing a conclusion or making a forecast or projection, including the assumptions,

qualifications and limitations relating to the Cariboo Gold Project being fully permitted and shovel ready; the ability of the Company

to obtain project finance for the development of the Cariboo Gold Project; proposed pre -construction activities; the results of the

OFS, including assumptions relating to updated metal prices and foreign exchange assumptions; Phase I and II regional drilling at

Tintic and related priority targets; th e long-term prospects of San Antonio, including the permitting process, status on care and

maintenance and status of the strategic review; the significance of target drilling; the ability of the Company to complete a follow -

up targeted geophysical survey and the exploration success thereof (if any); the potential impact of tariffs and other trade restrictions

(if any); the Company being construction and operation ready; unlocking Cariboo's potential for shareholders, Indigenous nations

and other stakeholders; the ability of the Company to complete the optimized feasibility study and the scope, results and timing of

thereof; progress and timing in respect of pre-construction activities at Cariboo including bulk sample and underground development

work; category conversion; the timing and status of permitting; the future development and operations at the Cariboo Gold Project;

the results of ongoing stakeholder engagement; the capital resources available to the Company; the ability of the Company to

execute its planned activities, including as a result of its ability to seek additional funding or to reduce planned expenditures; the

ability of the Company to obtain future financing and the terms of such financing including a fully -funded solution for the Cariboo

Gold Project; management's perceptions of historical trends, current conditions and expected future developments; the utility a nd

significance of historic data, including the significance of the district hosting past producing mines; future mining activit ies; the

potential of high grade gold mineralization on Trixie and Cariboo; the ability and timing for Cariboo to reach commercial pro duction

(if at all); sustainability and environmental impacts of operations at the Company's properties; the results (if any) of further

exploration work to define and expand mineral resources; the ability of exploration work (including drilling) to accurately p redict

mineralization; the ability to generate additional drill targets; the ability of management to understand the geology and potential of

the Company's properties; the ability of the Company to expand mineral resources beyond current mineral resource estimates; t he

ability of the Company to complete its exploration and development objectives for its projects in the timing contemplated and within

expected costs (if at all); the ongoing advancement of the deposits on the Company's properties; the impact of permitting del ays

at San Antonio Gold Project; the outcome of the strategic review of the San Antonio Gold Project; sustainability and environmental

impacts of operations at the Company's properties; the ability and timing for Cariboo to reach commercial production (if at all); the

ability to adapt to changes in gold prices, estimates of costs, estimates of planned explo ration and development expenditures; the

ability of the Company to obtain further capital on reasonable terms; the profitability (if at all) of the Company's operations; as well

as other considerations that are believed to be appropriate in the circumstanc es, and any other information herein that is not a

historical fact may be "forward looking information". Material assumptions also include, management's perceptions of historic al

trends, management's understanding of the permitting process and status there of, the ability of exploration (including drilling and

chip sampling assays, and face sampling) to accurately predict mineralization, budget constraints and access to capital on te rms

acceptable to the Company, current conditions and expected future develo pments, regulatory framework remaining defined and

understood, results of further exploration work to define or expand any mineral resources, as well as other considerations th at are

believed to be appropriate in the circumstances. Osisko Development consi ders its assumptions to be reasonable based on

information currently available, but cautions the reader that their assumptions regarding future events, many of which are be yond

the control of Osisko Development, may ultimately prove to be incorrect since they are subject to risks and uncertainties that affect

Osisko Development and its business. Such risks and uncertainties include, among others, risks relating to third -party approvals,

including the issuance of permits by the government, capital market conditions and the Company's ability to access capital on terms

acceptable to the Company for the contemplated exploration and development at the Company's properties; the ability to contin ue

current operations and exploration; regulatory framework and presen ce of laws and regulations that may impose restrictions on

mining; the ability of exploration activities (including drill results and chip sampling, and face sampling results) to accurately predict

mineralization; errors in management's geological modellin g; the ability to expand operations or complete further exploration

activities; the timing and ability of the Company to obtain required approvals and permits; the results of exploration activities; risks

relating to exploration, development and mining act ivities; the global economic climate; metal and commodity prices; fluctuations

in the currency markets; dilution; environmental risks; and community, non-governmental and governmental actions and the impact

of stakeholder actions. Osisko Development is con fident a robust consultation process was followed in relation to its received BC

Mines Act and Environmental Management Act permits for the Cariboo Gold Project and continues to actively consult and engage

with Indigenous nations and stakeholders. While an y party may seek to have the decision related to the BC Mines Act and/or

Environmental Management Act permits reviewed by the courts, the Company does not expect that such a review will impact its

ability to proceed with the construction and operation of the Cariboo Gold Project in accordance with the approved BC Mines Act and

Environmental Management Act permits. Readers are urged to consult the disclosure provided under the heading "Risk Factors" i n

the Company's annual information form for the year ended December 31, 2024 as well as the financial statements and MD&A for

the year ended December 31, 2024, which have been filed on SEDAR+ ( www.sedarplus.ca) under Osisko Development's issuer

profile and on the SEC's EDGAR website ( www.sec.gov), for further information regarding the risks and other factors facing the

Company, its business and operations. Although the Company's believes the expectations conveyed by the forward -looking

statements are reasonable based on information available as o f the date hereof, no assurances can be given as to future results,

levels of activity and achievements. The Company disclaims any obligation to update any forward-looking statements, whether as a

result of new information, future events or results or othe rwise, except as required by law. Forward -looking statements are not

guarantees of performance and there can be no assurance that these forward-looking statements will prove to be accurate, as actual

results and future events could differ materially from t hose anticipated in such statements. Accordingly, readers should not place

undue reliance on forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange,

securities commission or other regulatory authority has approved or disapproved the information contained herein.