Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

OGC.TO ·

Oceanagold Provides an Update to Haile Commissioning and Revised Company Guidance

Mine Development & Operations

1

MEDIA RELEASE

26 June 2017

OCEANAGOLD PROVIDES AN UPDATE TO HAILE COMMISSIONING AND REVISED

COMPANY GUIDANCE

(All financial figures in US Dollars unless otherwise stated)

(MELBOURNE) OceanaGold Corporation (TSX/ASX: OGC) (the “Company”) wishes to provide an update

on the status of commissioning activities at the Haile Gold Mine (“Haile”).

Mick Wilkes, OceanaGold President and CEO said, “ Although the Haile operation is cash flow positive and

many aspects of the operation continue to meet or exceed our expectations, we have encountered some

commissioning issues that have had an impact on overall process stability and recoveries. It is not uncommon

to encounter technical issues that need to be addressed during the commissioning phase of a new process

plant. Our highly skilled team on the ground, many of which have contributed to the timely and successful

commissioning of the Didipio and Reefton process plants, are working towar ds achieving commercial

production.”

He added, “Although disappointed with the delay, I am highly confident in the team and with their ability to

deliver this plant to meet our expectations for production and cost. The Haile Gold Mine is world-class asset

with very robust economics that will deliver significant cash flows for many years to come, as demonstrated

by the results of the optimisation study.”

Haile Commissioning

In the first quarter and early in the second quarter, plant throughput ramped -up well and we achieved

nameplate throughput several times . However, in the middle of the second quarter, some commissioning

issues surfaced leading to a shortfall in tonnes milled and recovery as compared to the ramp-up plan.

1. The primary poly -urethane liner on each of the eight Carbon-in-Leach (“CIL”) tanks partially de-

laminated due to poor application. As a result, the Company was required to take two CIL tanks at a

time off line to strip the liner completely from the tanks, which reduced the residency time in the

leaching circuit leading to lower recoveries. Re-application of the new liners , is being carried out

under warranty and by the installation contractor one tank at a time to eliminate disruption to the

plant with an expected completion in December.

2. The CIL tank inter-stage piping system was short circuiting and thereby sending some gold bearing

slurry into tailings. The Company identified that the CIL piping system was under designed and has

implemented a temporary fix while advancing the permanent solution. The Company will install a

new CIL piping system and expects this work to be completed by August. The temporary solution

2

has resolved the issue and has subsequently led to higher recoveries and increased plant stability in

recent weeks.

3. The front-end of the process plant has performed to expectation with only a minor issue related to

grate sizing of the SAG mill. The current steel discharge grate opening in the SAG mill are

inadequately sized to allow worn steel grinding media to pass through. This has resulted in excessive

amount of small grinding media in side the mill reducing its effectiveness. This in turn , has created

fluctuations in throughput and contributed to instability of the process. As part of a planned mill re -

lining scheduled for July, the Company will replace some of the current steel grate s with larger

aperture grates which will alleviate the problem.

4. The fine grinding circuit has been impacted by fluctuations in density effecting its performance. The

circuit will be converted to closed circuit grinding which will stabilise the feed to the mills and better

regulate the product size.

5. Some parts of the control systems have not performed to expectations due to lower data processing

speeds which has resulted in sub -optimal responses through some areas of the process plant. In

parallel with the process plant expansion, enhancements to the process cont rol system will be

identified and undertaken.

A summary of the commissioning issues, rectification plans and timing is summarised in Table 1.

Table 1 – List of Commissioning Focus Areas

Specific Area Issue Solution Estimated

Cost

Completion

Date

SAG Mill grate

Current steel grates in the

SAG mill holding back finer

steel grinding media causing

excessive quantity of small

grinding material resulting in

lower throughput

Replace some of the grates with

larger aperture grates allowing

the smaller steel media to pass

through the mill

$50k July 2017

Regrind inflow

Variable slurry density into

fine grinding circuit resulting in

inconsistent grinding size

Closing the feed circuit to better

control slurry density and

product size

$200k July 2017

Carbon-in-Leach

Piping System

Inadequately sized piping

system between CIL tanks

and the leach circuit

Redesign and installation of a

new CIL piping system $700k August 2017

Carbon-in-Leach

Tank Liners

Tank liners partially failing at

various times due to faulty

application on inner tank walls

Removing the current liners and

then reapplying new liners one

at a time to eliminate disruption

Nil (under

warranty) December 2017

Control system

Control system programming

and data processing has been

sub-optimal in some areas

resulting in inefficient process

control

In parallel with future upgrades

to process plant, review and

undertake potential upgrades to

control system

$2M - $3M Staged upgrades

over time

Mining operations continue to progress well as the Company has commenced mining ore at the Snake pit,

four months earlier than planned. Mining reconciliation has been in-line with expectations.

The operation is cash flow positive and operating costs are in-line with expectations. The results of the Haile

Optimisation Study have demonstrated the significant value inherent to this asset and the Company

continues to be encouraged by the exploration potential at depth and along strike at Haile and regionally.

3

Updated Company Guidance

With the updated forecast at Haile and strong operations at Didipio, the Company wishes to provide a revised

production and cost guidance. The overall gold production guidance range for the Company remains broadly

unchanged while the copper production guidance range has increased.

Table 2 – REVISED 2017 Production and Cost Guidance

Didipio Waihi Macraes Haile (1) Consolidated

Gold

Production ‘000 oz

150 – 160

(was 110 – 130)

110 – 120

(unchanged)

180 – 190

(unchanged)

110 – 130

(was 150 – 170)

550 – 600

(was 550 - 610)

Copper

Production ‘000 t

18 – 19

(was 15 – 17)

– – –

18 – 19

(was 15 – 17)

All-In

Sustaining

Costs(2)

$ / oz

$70 – $120

(was $130 – $180)

$740 – $790

(unchanged)

$950 – $1,000

(unchanged)

$600 – $650

(was $500 – $550)

$600 – $650

(unchanged)

Notes:

1. Haile guidance reflects full year expected production and cost guidance. Production and costs prior to declaration of commerc ial production will be

capitalised and reflected on the balance sheet.

2. AISC calculation conforms to the methodology outlined by the World Gold Council. It includes all cash costs, corporate G&A, maintenance capital

expenditures, capitalised mining expenditures and exploration. It excludes growth capital such as additional development such as the plant

expansion at the Haile Gold Mine and Didipio Underground.

Economic Assumptions

 NZD:USD exchange rate of 0.70, Copper price: $2.50 / lb on average for full year.

On the revised guidance for the Haile and Didipio operations this year, Mick Wilkes stated “ Operating a

diversified multi-mine business provides us the flexibility to offset production from one asset against another

to achieve our overall business results, as increased production now expected at Didipio will partially offset

the decrease in production from Haile this year.”

- ENDS -

For further information please contact:

Investor Relations

Sam Pazuki

Tel: +1 416 915 3123

Jeffrey Sansom

Tel: +61 3 9656 5300

[email protected] | www.oceanagold.com | Twitter: @OceanaGold

About OceanaGold

OceanaGold Corporation is a mid -tier, high-margin, multinational gold producer with assets located in the

Philippines, New Zealand and the United States. The Company’s assets encompass its flagship operation,

the Didipio Gold-Copper Mine located on the isl and of Luzon in the Philippines. On the North Island of New

4

Zealand, the Company operates the high-grade Waihi Gold Mine while on the South Island of New Zealand,

the Company operates the largest gold mine in the country at the Macraes Goldfield which is m ade up of a

series of open pit mines and the Frasers underground mine. In the United States, the Company is currently

commissioning the Haile Gold Mine, a top -tier asset located in South Carolina. OceanaGold also has a

significant pipeline of organic growth and exploration opportunities in the Americas and Asia-Pacific regions.

OceanaGold has operated sustainably over the past 27 years with a proven track -record for environmental

management and community and social engagement. The Company has a strong soci al license to operate

and works collaboratively with its valued stakeholders to identify and invest in social programs that are

designed to build capacity and not dependency.

In 2017, the Company expects to produce 550,000 to 600,000 ounces of gold and 18, 000 to 19,000 tonnes

of copper with sector leading All-In Sustaining Costs that range from $600 to $650 per ounce sold.

Cautionary Statement for Public Release

Certain information contained in this public release may be deemed “forward-looking” within the meaning of

applicable securities laws. Forward -looking statements and information relate to future performance and

reflect the Company’s expectations regarding the generation of free cash flow, execution of business

strategy, future growth, future producti on, estimated costs, results of operations, business prospects and

opportunities of OceanaGold Corporation and its related subsidiaries. Any statements that express or involve

discussions with respect to predictions, expectations, beliefs, plans, projectio ns, objectives, assumptions or

future events or performance (often, but not always, using words or phrases such as "expects" or "does not

expect", "is expected", "anticipates" or "does not anticipate", "plans", "estimates" or "intends", or stating that

certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved) are

not statements of historical fact and may be forward -looking statements. Forward -looking statements are

subject to a variety of risks and uncerta inties which could cause actual events or results to differ materially

from those expressed in the forward -looking statements and information. They include, among others, the

accuracy of mineral reserve and resource estimates and related assumptions, inher ent operating risks ,

sovereign risks, risk of suspension and those risk factors identified in the Company’s most recent Annual

Information Form prepared and filed with securities regulators which is available on SEDAR at

www.sedar.com under the Company’s name. There are no assurances the Company can fulfil forward -

looking statements and information. Such forward -looking statements and information are only predictions

based on current information available to management as of the date that such predictions are made; actual

events or results may differ materially as a result of risks facing the Company, some of which are beyond the

Company's control. Although the Company believes that any forward -looking statements and information

contained in this press release is based on reasonable assumptions, readers cannot be assured that actual

outcomes or results will be consistent with such statements. Accordingly, readers should not place undue

reliance on forward-looking statements and information. The Company expressly disclaims any intention or

obligation to update or revise any forward -looking statements and information, whether as a result of new

information, events or otherwise, except as required by applicable securities laws. The information contained

in this release is not investment or financial product advice.

5

NOT FOR DISSEMINATION OR DISTRIBUTION IN THE UNITED STATES AND NOT FOR DISTRIBUTION

TO US NEWSWIRE SERVICES.