Oroco Announces 22.2% After-tax IRR and $1.48 Billion NPV for its Santo Tomas Project

Economic Studies

August 20, 2024 News Release

Oroco Announces 22.2% After-tax IRR and $1.48 Billion NPV for its Santo Tomas Project

VANCOUVER, CANADA, August 20th, 202 4 – Oroco Resource Corporation. (“ Oroco” or the “ Company”)

(TSXV: OCO; OTCQB: ORRCF, BF: OR6) is pleased to announce a revised Preliminary Economic Assessment

(“PEA”) and updated Mineral Resource Estimate (“MRE”) for the North Zone and South Zone of its Santo

Tomas Porphyry Copper Project (“ Santo Tomas” or the “ Project”) in Sinaloa State, Mexico. The PEA is

based on a staged open pit mine and processing plant achieving 60,000 tonnes per day (“t/d”) production

in year 1 and expanding to 120,000 t/ d in year 8 over a 22.6-year Life of Mine (“ LOM”). Production is

preceded by two years of construction and one concurrent year of pre -stripping. The PEA has been

prepared by Ausenco Engineering USA South Inc. (“Ausenco”). The updated MRE and geologic model were

prepared by SRK Consulting (U.S.), Inc. of Denver, Colorado and SRK Consulting (Canada) Inc., Vancouver,

BC (jointly “SRK”). SRK (Canada) was responsible for geotechnical modeling. The mine planning and mine

costs components of the PEA were prepared by SRK (U.S.).

Highlights of the revised PEA include:

• NPV (8%) of US$2.64 billion pre-tax and US$1.48 billion post-tax.

• IRR of 30.3% pre-tax and 22.2% post-tax.

• Total LOM payable copper production of 4,774 M lb.

• Pre-tax payback of 2.9 years; post-tax payback of 3.8 years from first concentrate production.

• Initial capital costs estimated at US$1,103.5 million; sustaining and expansion capital costs estimated

at US$1,734.1 million.

• Annual LOM C1 Cash Cost of US$1.54/lb Cu on by-product basis.

• Average CuEq grade of 0.51% over the first 7 years of production.

• Capital efficiency ratio (NPV / Initial Capital Cost) of 1.34.

• Total mineralized material mined of 825.5 Mt.

Commenting on the updated PEA, CEO Richard Lock:

“When we completed the initial PEA in December 2023 it was clear there was additional value to be unlocked

at Santo Tomas. Upon careful analysis, a staged approach to the mine expansion and a focus on exploiting

the higher-grade near surface material in the early years of mining has unlocked a considerable increase in

value. We have established a plan that invokes a very efficient use of capital and establishes a rapid post -tax

payback of 3.8 years. The plan starts with the use of smaller equipment to provide rapid entry to the

mineralized material and maintains a higher-grade feed profile to delay the requirement of an expansion until

year 8. Copper Equivalent production in the first 7 years is forecast at 1.34 billion pounds at a Mill Feed average

grade of 0.51% Cu Eq.

Quite significantly, this work establishes Santo Tomas as one of the most capital efficient large -scale, low-

cost copper projects in the world as illustrated in Figure 1 below.

Figure 1: Santo Tomas Displays Strong Economics Compared to its Peers

Source/Notes:

FactSet. Technical reports (1) Copper equivalent production calculated using stated metal prices from each project’s latest technical

report (After-Tax NPV 8% / Total Capex (US$M). Bubble size based on annual production). The above chart is for illustration purposes

only and presents an abstract and simplified view of the NPV based on published data. The other projects presented may not take

into account individual risk profiles of each deposit depicted and may not be contemporaneous with the current NPV of the San to

Tomas update. See important metal price and study date information for projects depicted above on Oroco’s website.

PEA Overview

The Santo Tomas property comprises 9,034 ha of mineral concessions encompassing significant porphyry

copper mineralization in northern Sinaloa and southwest Chihuahua, Mexico. The Project is located in the

Santo Tomas Porphyry District, which extends from Santo Tomas northward to the Jinchuan Group’s

Bahuerachi Project located approximately 14 km to the north -northeast. The PEA was conducted using

data (including 27,382 Cu assays) from 68 diamond drill holes ( 43,063 m) drilled by the Company and 90

legacy reverse circulation and diamond drill holes (21,075 m, for a total of 64,138 m in 158 drill holes ) in

the Project’s North Zone and South Zone . The data from the seven exploration diamond drill holes in

Brasiles Zone and the single geotechnical hole (GT001) drilled by the Company were excluded from

consideration in the MRE and PEA . Oroco’s entire updated drill hole database ( including PEA excluded

holes) contains 166 new and legacy drill holes totaling 69,556 m with lithological logging data and 29,992

Cu assays.

The commodity price assumptions for the Discounted Cash Flow (“ DCF”) analysis are presented in Table

1. Key results from the DCF analysis prepared by Ausenco are presented in Tables 2 & 3.

Table 1: DCF Price Assumptions

Commodity Unit Price*

Cu US $ / lb 4.00

Mo US $ / lb 15.00

Au US $ / t.oz 1,900

Ag US $ / t.oz 24.00

*Cash flow model assumptions only.

Cautionary Note to Investors

The reader is cautioned that the PEA is preliminary in nature, and that it includes inferred mineral resources

that are considered too speculative geologically to have the economic considerations applied to them that

would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary

economic assessment will be realized.

Table 2: Mining and Production – Key Results

Key Assumptions Unit LOM

Exchange Rate MXN / US$ 19.76

Fuel Price MXN / L 20.41 (US$1.03)

Production Profile Unit LOM

Total Open Pit Tonnage Mt 1,964.9

Total Open Pit Mineralized Material Mined Mt 825.5

Open Pit Strip Ratio Waste : mill feed 1.38

Daily Throughput (Year 1 // Year 8 on) kt/d 60 // 120

LOM (concentrate production) Years 22.6

Copper in Mill Feed M lb 5,916

Molybdenum in Mill Feed M lb 138.7

Gold in Mill Feed koz 753.4

Silver in Mill Feed koz 55,200

LOM mill feed (Indicated // Inferred) Mt 388 // 460

Average Cu payable / year – LOM M lb 207.5

Average Cu payable / year – First 5 Years (1) M lb 167.5

Payable (2) Copper LOM (in concentrate) M lb 4,774

Payable Molybdenum LOM (in concentrate) M lb 80.8

Payable Silver LOM (min 30 g/t payable in Cu Concentrate) koz 26,673

Payable Gold LOM (min 1 g/t payable in Cu Concentrate) koz 300.2

Operating Costs (US$/lb.) Unit LOM

C1 Cash Costs Copper (By-Product Basis) (3) US$/lb 1.54

C3 Cash Costs Copper (By-Product Basis) (4) US$/lb 2.00

Capital Expenditures (5) Unit LOM

Initial Capital (6) US$M 1,103.5

Sustaining and Expansion Capital (6, 7) US$M 1,734.1

Closure Costs (5 years, year 22 - 27) US$M 209.2

Estimated Salvage Value US$M 0

Notes: (1) First 5 Years at full production, starting year 2. (2) Payable metals consider mining dilution, concentrator recoveries and

Treatment Charges/Refining Charges (TC/RC) . (3) C1 Cash Costs consist of mining costs, processing costs, mine -level G&A and

transportation costs net of by -product credits. (4) C3 Cash Costs includes C1 Cash Costs plus sustaining and expansion capital,

royalties, and closure costs. (5) All capital expenditures are inclusive of contingency provisions to allow for uncertain cost elements,

which are predicted to occur but are not included in the cost estimate. (6) Net of leasing capital deferment and leasing costs. (7) Sum

of expansion and sustaining capital.

Table 3: Key Financial Results and Costs

Economics Unit LOM

NPV at 8% (pre-tax // post-tax) US$M 2,640.5 // 1,475.4

IRR (pre-tax // post-tax) % 30.3 // 22.2

Payback (pre-tax // post-tax) Years 2.9 // 3.8

Revenue over LOM US$M 21,517

Initial Capital

Mining Pre-Stripping (Capitalized OPEX) US$M 75.5

Mining Capital Equipment (1) US$M 89.4

Total Mining (1) US$M 164.9

Processing US$M 938.7

Total Initial Capital (1) US$M 1,103.6

Sustaining Capital

Mining Equipment US$M 952.4

Processing US$M 94.6

Total Sustaining Capital US$M 1,047.0

Expansion Capital – Processing (year 7) US$M 687.2

Average LOM Operating Costs

Mining Cost per tonne mined (2) US$ / t 2.04

Mining Cost per tonne milled (2) US$ / t 4.78

Mining Equipment Leasing Cost per tonne milled US$ / t 0.06

Processing Cost per tonne milled US$ / t 4.04

G&A Cost per tonne milled US$ / t 0.65

Total Operating Cost per tonne milled (2) US$ / t 9.53

Notes: ( 1) Includes leasing costs and deferral of capital associated with lease payments. Supplier -sourced leasing terms from

October 2023 are used in the mine fleet cost calculations that include a 5-year lease period with 10.3% interest, 0.5% upfront fee, and

no residual payment. (2) Excludes leasing costs.

Economic Sensitivities

Project economics and cash flows are most sensitive to changes in the price of copper (Figure 2) providing

the highest potential for change in economics. However, mined grade and recovery sensitivity are also high

and future studies will seek to optimize these parameters.

Figure 2: Post-Tax NPV and IRR Sensitivity Plots

Source: Ausenco 2024

Mineral Resource Estimate

The MRE was prepared in accordance with the Canadian Institute of Mining, Metallurgy, and Petroleum

(“CIM”) Definition Standards (the “CIM Standards ”) incorporated by reference in National Instrument 43 -

101 (“NI 43-101”), with an effective date of July 23, 2024. The Technical Report will be released by the

Company and available at www.orocoresourcecorp.com and on SEDAR (www.sedarplus .ca) under the

Company’s profile shortly.

The MRE includes the two primary mineralization zones identified at Santo Tomas : North Zone and South

Zone. These zones display similar mineralization styles but are physically separated by localized post-

mineralization faults and material currently defined as waste due to a lack of drilling . Consistent with the

previous study, the MRE is not constrained by the location of the Huites Reservoir . Mineral resources are

reported above an effective cut-off grade (CoG) of 0.15% Cu and constrained by an economic pit shell (see

Table 4).

Table 4: Mineral Resource Statement for the Santo Tomas Project, effective July 23, 2024.

Category Zone Tonnes

Mt

Average Grade In-situ Metal3

CuEq10 Cu Mo Au Ag CuEq10 Cu 11 Mo 11 Au 11 Ag 11

% % % g/t g/t M lb M lb M lb koz koz

Indicated

North Zone pit

- sulphide 540.6 0.37 0.33 0.008 0.028 2.1 4,465 3,976 95.4 483.4 36,524

Total Indicated 540.6 0.37 0.33 0.008 0.028 2.1 4,465 3,976 95.4 483.4 36,524

Inferred

North Zone pit

- sulphide 90.0 0.34 0.31 0.005 0.021 1.7 679 620 10.2 61.4 4,949

North Zone pit

- oxide 4.4 0.31 0.31 0.002 0.053 1.6 29 29 0.2 7.4 228

South Zone pit

- sulphide 399.2 0.36 0.32 0.008 0.023 2.0 3,132 2,789 71.2 294.4 26,200

South Zone pit

- oxide 36.7 0.27 0.27 0.004 0.020 1.6 218 218 2.8 23.8 1,851

Total Inferred 530.3 0.35 0.31 0.007 0.023 1.9 4,058 3,657 84.4 387.1 33,229

Notes:

(1) Mineral resources are not mineral reserves and do not have demonstrated economic viability.

(2) Abbreviations used in the table above include: Mt = million metric tonnes, % = percent, g/t = grams per metric tonne, M lb =

million pounds, and k oz = thousand troy ounces.

(3) All figures are rounded to reflect the relative accuracy of the estimates. Totals in Table may not sum or recalculate from

related values in the table due to rounding of values in the table, reflecting fewer significant digits than were carried in the

original calculations.

(4) Metal assays are capped where appropriate. At this stage of the project, it is the Company’s opinion that all the elements

included in the metal equivalents calculation have a reasonable potential to be recovered and sold.

(5) All dollar amounts are presented in US dollars.

(6) Bulk density is estimated on a block basis using specific gravity data collected on diamond drill core.

(7) Economic pit constrained resource with reasonable prospects of eventual economic extraction (“RPEEE”) were based on a

copper price of $4.00/lb, molybdenum price of $13.50/lb, a gold price of $1,700/oz, and a silver price of $22.50/oz. Metal

recovery factors of 83.7% for copper, 66% for molybdenum, 53% for gold and 53% for silver have been applied. Selling costs

are $0.56/lb copper, $1.69/lb molybdenum, $191.71/oz gold and $2.94/oz silver. Slope angles varied by pit sector and

range from 40 degrees to 49 degrees.

(8) The in-situ economic copper (CoG) was calculated resulting in a 0.15% Cu CoG.

(9) CoG assumptions include: a copper price of $4.00/lb, molybdenum price of $13.50/lb, gold price of $1,700/oz, and silver

price of $22.50/oz. Suitable benchmarked technical and economic parameters for open pit mining, including a 98% mining

recovery and cost s of mining at $2.40/t, processing at $4.79/t, G&A at $0.67/t, with Private Royalties at 1.5% for

molybdenum, gold, silver, and copper, have been applied in consideration of the RPEEE. Recoveries are applied as listed in

Note 7.

(10) Equivalent Copper (CuEq) percent is calculated with the formula CuEq% = ((Cu grade * Cu recovery [83.7% sulphide or 75.0%

oxide] * Cu price) + (Mo grade * Mo recovery [59%] * Mo price) + (Au grade * Au recovery [53%] * Au price) + (Ag grade * Ag

recovery [53%] * Ag price)) / (Cu price * Cu recovery [83.7% sulphide or 75.0% oxide]). It assumed that the Santo Tomás

Project will produce a conventional (flotation) copper concentrate product based on metal recoveries at 83.7% Cu (sulphide)

or 75% Cu (oxide), 59% Mo, 53% Au, and 53% Ag based on initial preliminary metallurgical test work.

(11) Reported contained individual metals in Table represent in -situ metal, calculated on a 100% recovery basis, except for

CuEq% (see Note 10).

The mineral resource estimation process includes updated structural, lithologic, and mineralization models

not materially changed from the previous study, effective April 27, 2023. No additional drilling has been

added and the estimation methodology remains unchanged from the methodology used in the. Differences

in the MRE shown in Table 4 from the previous MRE are due to: 1) inclusion of oxidized mineralization in

the North Zone pit (the “North Pit”) and South Zone pit (the “ South Pit”); and 2) updated economic and pit

slope assumptions based on the updated PEA study. The resource estimation methodology involved the

following procedures:

• Database compilation and verification,

• Construction of wireframe models for the major structures, lithotypes, and controls on mineralization,

• Definition of resource domains using a combination of lithotypes, structure, oxidation, and

mineralization grade shells,

• Data conditioning (compositing and capping) for statistical and geostatistical analyses,

• Determination of spatial continuity through variography within the estimation domains,

• Block modeling and grade interpolation for all key economic variables (Cu, Mo, Ag, Au, and Sulfur [S])

and secondary variables (arsenic [As], calcium [Ca], potassium [K], lead [Pb], and zinc [Zn]),

• Block model validation,

• Resource classification,

• Assessment of “reasonable prospects for eventual economic extraction” (“RPEEE”) using a

constraining economic pit shell and selection of an effective cut- off grade (“CoG”), and

• Preparation of the updated mineral resource statement.

SRK undertook the geological modeling and mineral resource estimate using Seequent Leapfrog Geo and

Leapfrog Edge, respectively. The procedure involved construction of wireframe models for structural

geology controls, key geological and mineralization domains, data conditioning (compositing and capping)

for statistical analysis, variography, block modeling and grade interpolation followed by block model

validation. Grade was estimated using a combination of ordinary kriging and inverse distance weighting

cubed estimates for copper, molybdenum, gold, and silver. Sulfur grades are estimated using inverse

distance weighting squared (“ IDW2”) and bulk density is estimated using a combination of simple kriging

and IDW2. Grade estimation was based on block dimensions of 50 m x 50 m x 10 m for the PEA model

(unchanged from previous studies). The block size reflects current data spacing across the Project while

considering a likely open pit mining method. Classification of mineral resources considers the geological

complexity (structure, lithology, alteration, and mineralization), spatial continuity of mineralization, data

quality, and spatial distribution of drilling conducted at the Project.

The MRE is supported by 64,138 m of drilling in 158 holes. The drilling data represents a combination of

holes completed by Oroco from 2021 to 2023 and historical drill holes but excludes drilling at Brasiles Zone

(outside current project scope) and one geotechnical hole (due to lack of assay data).

Mineralization has been identified outside the current economic pit shell. The PEA highlights the potential

to define additional mineral resources on the property . There is identified exploration potential for

additional mineralization in the southeastern and southwestern portions of the South Zone based on

observations from drilling and surface outcrops in the area.

Mine Design

The mine design re-worked previous phase designs to increase the number of pit phases from 4 to 20.

Initial phases are smaller to reduce waste stripping and allow for faster access to higher grade mill feed ,

resulting in an average 0.51% CuEq ore grade for the first 7 years of production. These smaller phases have

narrower access roads that require the use of small-scale haul trucks (72 t capacity). Later in the mine life,

the pit phases are typically larger and will allow for the use of large-scale haul trucks (240 t capacity). Over

the life of the project, including the pre-production waste mining year, 80% of the tonnes mined will be with

the large-scale equipment fleet.

The final pit design ensures no incursion upon the Huites Reservoir, remaining outside of CONAGUA’s

(Mexican water authority) jurisdiction boundary (the “ CONAGUA limit”). Slope constraints derived from

geotechnical domains were defined from Phase 1 drilling on the Project.

Table 5 shows mineral inventory within the ultimate pit design for this PEA.

Table 5: Pit Constrained Resource

Mill Feed Waste Material Strip Ratio Total Material

Tonnes

(Mt)

Cu

(%)

Mo

(%)

Au

(g/t)

Ag

(g/t)

CuEq

(%)

Tonnes

(Mt) Waste/Mill Tonnes

(Mt)

825.5 0.325 0.008 0.028 2.080 0.365 1,139.4 1.38 1,964.9

The proposed mining method is conventional open pit truck and shovel operation with 10 -meter bench

intervals. Haul trucks will be used for hauling mineralized material to the crushing plant, long-term stockpile

facilities, and waste to the waste rock storage facilities (“WRSFs”).

The mine production plan contains 825.5 M tonnes of mineralized sulfide material with an average grade

of 0.37% CuEq , and 1,139.4 M tonnes of waste material (including mineralized oxide), resulting in a strip

ratio of 1.38 over the LOM. CuEq is calculated using the methodology described in the footnotes to Table

4.

Mining operations will be carried out on a 24-hour per day, 365 days per year schedule. Total mined tonnes

will start at 27.2M tonnes mined during the pre -stripping year and eventually ramp up to a maximum of

116M tonnes per annum (Mt/a) in Year 13. The Project has a total life of 23.5 years, which includes 1 year

of pre-stripping and one final year of stockpile rehandling to the mill. Project expansion (Phase II) starts in

Year 8 of operation.

The mining sequence consists of 20 phases (10 in the North P it and 10 in the South Pit), which vary in

minimum mining width according to the type of equipment to be used. Early years focus on mining the

North Pit, while transitioning to larger equipment to be used once the South P it has opened up to wider

benches.

Mined tonnes, Mill Feed tonnes and Mineral Inventory classification are shown in Figures 3 , 4 and 5.

Figure 3: Mine Production Schedule – Mineralized Material/Waste

Figure 4: Mill Production Schedule

Figure 5: Classification of Mineral Inventory