NexGen Announces Positive Results from Arrow Project Studies

Corporate Updates

NexGen Announces Positive Results from Arrow Project Studies  

Vancouver, BC, June 13, 2018 – NexGen Energy Ltd. (“NexGen” or the “Company”) (TSX:NXE, NYSE MKT:NXE) 

is  pleased  to  report  the  positive  results  from  Pre‐Feasibility‐stage  technical  studies  including  metallurgical, 

geotechnical, and hydrogeological assessments. These studies were conducted on the basement‐hosted Arrow 

Deposit, located on the Company’s 100% owned Rook I project in Saskatchewan’s Athabasca Basin.   

Highlights: 

Metallurgical Study 

The Bench‐Scale Metallurgical Study has demonstrated high purity yellowcake product can be produced by 

using peroxide and MgO. The final product, produced yellowcake, meeting or surpassing industry standards.  

 High recovery rates confirmed. 

o Leaching test samples representing anticipated typical mill feed resulted in 97.6% of uranium 

was recovered.  

o Optimized solvent extraction (“SX”) resulted in 99.6% of uranium extracted. 

 Strength tests meet or exceed all requirements set forth in the original design for a potential Paste‐

Backfill to be used for underground stope stability.  

o Paste‐Backfill  samples  composed  of  representative  uranium  tailings  mixed  with  binder, 

underwent  an  initial  28‐day  Unconfined  Compressive  Strength  (“UCS”)  test  with  results 

surpassing the targeted high‐strength Backfill of 1.5 MPa outlined in the initial mine design 

in the Preliminary Economic Assessment. 

Geotechnical Study 

 Conventional long‐hole stoping mining method confirmed. 

o The  geotechnical  assessment  supports the  conventional  long‐hole stoping  mining  method 

including the use of longitudinal and transverse stopes, 30 m level spacing, and the nominal 

stope  strike  length  of  15  m  to  30  m.  This  represents  an  excellent  stope  stability  range  for 

underground mining in competent conditions. 

Hydrogeological Study 

 Hydraulic conductivity consistent with that predicted in basement rocks. 

o The hydrogeological study measured hydraulic conductivity. Results were as predicted given 

mineralization  is  completely  hosted  in  the   crystalline  basement  rocks.  Conductivity  which 

measures the presence of water, decreases with depth and is expected to be lowest at depths 

associated with mine workings.  

Underground Tailings Management Facility is displayed in Figure 1 below.  

Development, Activities & Financial 

 Pre‐feasibility  staged  technical  studies  including  geotechnical  work,  hydrogeological  work,  and 

metallurgy continue in advance of the updated Mineral Resource Estimate and maiden Pre‐Feasibility 

Study scheduled for the end of Q3 / early Q4 2018. 

 A summer drilling program is in the final stages of preparation and will begin imminently. 

 The Company has cash on hand of approximately ~$145 million. 

Troy  Boisjoli,  Vice‐President,  Operations  and  Project  Development,  commented:  “Results  from  the 

metallurgical  study  demonstrate  high  recovery  of  uranium  during  the  leaching  and  optimized  solvent 

extraction process. Furthermore, positive results from Paste‐Backfill test work has confirmed proof of concept 

for potential application of an underground tailings management facility. In addition to responsible tailings 

management,  mixing  tailings  with  cement  and  depositing  it  back  underground  will  facilitate  ongoing  and 

continued reclamation while in operation. Geotechnical results have confirmed the nature of the basement‐

hosted Arrow Deposit can support conventional long‐hole stoping mining methods. The hydrogeological study 

demonstrates  hydraulic  conductivity  is  entirely  consistent  with  that  of  basement‐hosted  deposits  and  is 

favourable  for  mine  development.  With  every  stage  of  development  NexGen  continues  to  confirm  the 

robustness of the Arrow Project.”  

Leigh Curyer, Chief Executive Officer, commented: “Development studies continue to emphasize the unique 

technical  characteristics  of  the  Arrow  Project.   These  results  quantify  high  recovery  rates,  non‐detect 

deleterious  metals  and  competency  of  the  basement  rocks.   The  maiden  Pre‐Feasibility  Study  which  will 

incorporate an updated Mineral Resource Estimate is on schedule for release at end of Q3 or early Q4.  In the 

interim,  the  summer  2018  drilling  program  will  commence  imminently  which  will  continue  to  focus  on 

determining  the  overall  scale  of  Arrow  and  near‐Arrow  mineralization  as  well  as  further  define  site 

characterization for development.”   

Study Details:  

Bench‐Scale Metallurgical Study: 

Wood PLC (formerly AMEC Foster Wheeler) approved selected drill core samples and interpreted the results. 

The  bench‐scale  metallurgical  samples  were  analyzed  by  the  Saskatchewan  Research  Council  Laboratories 

(“SRC”), pilot‐scale metallurgical testing is ongoing.  

Thirteen  composite  samples  were  prepared  from  the  crushed  core  assay  rejects  and  used  for 

leaching/QEMSCAN/acid  generation  (PAG)/tailings  preparation  for  paste  backfill  tests.  The  samples  were 

blended and homogenized in a mixer to prepare the composite sample. 

Paste‐Backfill Testing:  

 Testing six varying compositions of representative uranium tailings combined with binder underwent 

an initial 28‐day UCS testing. The most successful of the mixtures came from sample M6, this mixture 

combined 61.01% uranium tailings with a resulting 2.15 MPa from UCS testing, surpassing the targeted 

high‐strength Backfill of 1.5 MPa.   

Modal mineralogy analysis:  

 QEMSCAN  analyses  on  the  Medium  Grade  (“MG”)  composite  and  A1  to  A5  individual  shear  zone 

samples indicate that uraninite was present as fresh and altered uraninite. No primary Mo‐bearing 

minerals  were  identified  in  any  samples,  and  all  samples  were  dominated  by  clay  minerals  with 

uraninite most commonly associated with the clay minerals  

Mill work index measurements: 

 Five composite samples were prepared from full diameter NQ core for comminution testing, including 

SAG mill work index and Bond Ball mill work index “SAGDesinTM tests”. The results categorized the 

samples as medium hardness materials which indicates standard grinding conditions. 

Leaching analysis: 

 Batch  leaching  on  the  Medium  Grade  (“MG”)  composite  sample  (50kg)  was  performed  at  baseline 

conditions to generate adequate quantity of baseline residue and pregnant leach solution (PLS) for the 

downstream tests. The MG composite sample uranium leaching recovery was 97.6%.   

Solvent extraction testing and filtration test: 

 Optimized solvent extraction (“SX”) resulted in 99.6% of U extracted with a phase separation time of 

3.1 minutes. The SX testing results on the settling filtrates, which were produced from the settling 

tests of the leaching slurry at the seven leaching conditions, support optimized leaching conditions for 

Low Grade, Medium Grade and High Grade samples. Both the U extraction rate (from 98.7% to 99.7%) 

and the phase separation time (3.7 to 5.9 minutes) were in the expected range.  

The Bench‐Scale Metallurgical Study has demonstrated high purity yellowcake product can be produced by 

using peroxide and MgO. The final product produced yellowcake, meeting or surpassing industry standards.  

Geotechnical Study: 

BGC Engineering Inc. (“BGC”) interpreted results from available geotechnical data, including geo‐mechanical 

property testing completed by SNC Lavalin (Saskatoon, SK) and Golder Associates Ltd. (Burnaby, BC).  

Six  geotechnical  diamond  drill  holes  were  completed  in  the  summer  of  2017.  The  holes  were  designed  to 

characterize the geotechnical and hydrogeological conditions in support of the envisioned Pre‐feasibility study 

(PFS) mine design, targeting: 

 Life‐of‐mine infrastructure 

 The A2 and A3 shears  

 The crown pillar 

The core was logged using the industry standard RMR76 system and Q rating system, and regular point load 

tests were performed to aid in the determination of intact rock strength. Representative core samples were 

selected from five of the drill holes and sent to SNC Lavalin (Saskatoon, SK) and Golder Associates Ltd. (Burnaby, 

BC)  for  geo‐mechanical  properties  testing.  The  testing  program  included  unconfined  compressive  strength, 

triaxial strength, and tensile strength tests on rock core samples, direct shear tests on discontinuities, index 

tests on discontinuity infills and X‐ray diffraction (XRD) tests on rock specimens. On four of the geotechnical 

holes, 39 downhole packer tests were completed to measure the hydraulic conductivity in various rock units 

and  along  structures  and  an  acoustic  televiewer  survey  was  performed  to  collect  in‐situ  structural 

measurements. Vibrating wire piezometers were installed in four of the holes to allow for long‐term monitoring 

of water pressures in specific intervals. 

In addition to the 2017 data, NexGen provided BGC with a geotechnical data set that was collected using the 

RMR89  system  (termed  RMR’)  and  consists  of  178  drill  holes  within  or  proximal  to  the  Arrow  Deposit.  BGC 

interpreted the available data and proposed eight geotechnical domains: 

1. Overburden (sand, cobbles, boulders) 

2. Cretaceous (siltstone/mudstone/sandstone/coal seams) 

3. Devonian (sandstone) 

4. Athabasca (sandstone) 

5. Paleoweathered basement (gneiss) 

6. Faults and shear zones (gneiss, altered gneiss, +/‐ mineralization) 

7. Unaltered basement (gneiss) 

8. Altered basement (altered gneiss, +/‐ mineralization) 

Using a 30 m level height, BGC recommends that transverse stopes have a span of 10 m to 15 m, at a stope 

strike  length  of  (15  to  30  m)  (check  this  is  consistent  with  the  bullet  point  in  highlights,  respectively.  For 

longitudinal stopes, stope length is limited by the unsupported walls (minimal level of ground support) ranging 

from 20 m to 30 m, dependant on location. Stope lengths greater than 20 m to 30 m would utilize cable bolt 

support in the walls.  

Hydrogeological Study: 

BGC Engineering Inc. (“BGC”) interpreted results from data collected on site by NexGen Energy personnel. 

BGC estimated the hydraulic conductivity of the crystalline basement rock from data obtained from the 31 

packer tests performed on the geotechnical diamond drill holes. 

The hydrogeological investigation indicates the Arrow Deposit has basement hydraulic conductivity values 

ranging from 5.2x10‐10 to 1.7x10‐6 m/s. These values are typical of metaphoric, crystalline basement rock. 

Figure 1: Underground Tailings Management Facility (RPA 2017) 

About NexGen 

NexGen  is  a  British  Columbia  corporation  with  a  focus  on  the  acquisition,  exploration  and  development  of 

Canadian uranium projects. NexGen has a highly experienced team of uranium industry professionals with a 

successful track record in the discovery of uranium deposits and in developing projects through discovery to 

production. 

NexGen owns a portfolio of prospective uranium exploration assets in the Athabasca Basin, Saskatchewan, 

Canada, including a 100% interest in Rook I, location of the Arrow Deposit in February 2014, the Bow discovery 

in March 2015, the Harpoon discovery in August 2016 and the Arrow South discovery in July 2017. The Arrow 

deposit's  updated  mineral resource  estimate  with  an  effective  date  of  December  20,  2016  was  released  in 

March 2017, and comprised 179.5 M lbs U3O8 contained in 1.18 M tonnes grading 6.88% U3O8 in the Indicated 

Mineral Resource category and an additional 122.1 M lbs U3O8 contained in 4.25 M tonnes grading 1.30% 

U3O8 in the Inferred Mineral Resource category. 

Leigh Curyer 

Chief Executive Officer 

NexGen Energy Ltd. 

+1 604 428 4112  

[email protected] 

www.nexgenenergy.ca 

Travis McPherson 

Vice President Corporate Development 

NexGen Energy Ltd. 

+1 604 428 4112 

[email protected]   

http://www.nexgenenergy.ca 

For Media Inquiries: 

Jonathan Goldberg 

KCSA Strategic Communications 

+1 212 896 1282 

[email protected] 

Technical Information 

Natural gamma radiation in drill core reported in this news release was measured in counts per second (cps) 

using  a  Radiation  Solutions  Inc.  RS‐120  gamma‐ray  scintillometer.  The  reader  is  cautioned  that  total  count 

gamma readings may not be directly or uniformly related to uranium grades of the rock sample measured; they 

should be used only as a preliminary indication of the presence of radioactive minerals. 

Split  core  samples  will  be  taken  systematically,  and  intervals  will  be  submitted  to  SRC  Geoanalytical 

Laboratories (an SCC ISO/IEC 17025: 2005 Accredited Facility) of Saskatoon for analysis. All samples sent to SRC 

will be analyzed using ICP‐MS for trace elements on partial and total digestions, ICP‐OES for major and minor 

elements on a total digestion, and fusion solution of boron by ICP‐OES. Mineralized samples are analyzed for 

U3O8 by ICP‐OES and select samples for gold by fire assay. Assay results will be released when received and 

after stringent internal QA/QC protocols are passed. 

All scientific and technical information in this news release has been prepared by or reviewed and approved 

by Mr. Troy Boisjoli, Geoscientist Licensee, Vice President – Operations & Project Development for NexGen. 

Mr. Boisjoli is a qualified person for the purposes of National Instrument 43‐101 Standards of Disclosure for 

Mineral  Projects  ("NI  43‐101"),  and  has  verified  the  sampling,  analytical,  and  test  data  underlying  the 

information or opinions contained herein by reviewing original data certificates and monitoring all of the data 

collection protocols. 

For details of the Rook I Project including the quality assurance program and quality control measures applied 

and  key  assumptions,  parameters  and  methods  used  to  estimate  the  mineral  resource  please  refer  to  the 

technical  report  entitled  "Technical  Report  on  the  Preliminary  Economic  Assessment  of  the Arrow  Deposit, 

Rook 1 Property, Province of Saskatchewan, Canada" dated effective September 1, 2017 (the "Rook 1 Technical 

Report") prepared by Jason J. Cox, David M. Robson, Mark B. Mathisen, David A. Ross, Val Coetzee and Mark 

Wittrup, each of whom is a "qualified person" under NI 43‐101. The Rook I Technical Report is available for 

review under the Company's profile on SEDAR at www.sedar.com. 

U.S. investors are advised that while the terms "indicated resources" and "inferred resources" are recognized 

and required by Canadian regulations, the U.S. Securities and Exchange Commission does not recognize these 

terms. U.S. investors are cautioned not to assume that any part or all of the material in these categories will 

ever be converted into mineral reserves. 

Forward‐Looking Information 

The  information  contained  herein  contains  "forward‐looking  statements"  within  the  meaning  of  the  United 

States Private Securities Litigation Reform Act of 1995 and "forward‐looking information" within the meaning 

of  applicable  Canadian  securities  legislation.  "Forward‐looking  information"  includes,  but  is  not  limited  to, 

statements with respect to the activities, events or developments that the Company expects or anticipates will 

or  may  occur  in  the  future.  Generally,  but  not  always,  forward‐looking  information  and  statements  can  be 

identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", 

"forecasts",  "intends",  "anticipates",  or  "believes"  or the  negative  connotation  thereof  or  variations  of  such 

words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be 

taken", "occur" or "be achieved" or the negative connotation thereof. 

Forward‐looking information and statements are based on the then current expectations, beliefs, assumptions, 

estimates and forecasts about NexGen's business and the industry and markets in which it operates. Forward‐

looking information and statements are made based upon numerous assumptions, including among others, 

that the proposed transaction will be completed, the results of planned exploration activities are as anticipated, 

the price of uranium, the cost of planned exploration activities, that financing will be available if and when 

needed and on reasonable terms, that third party contractors, equipment, supplies and governmental and other 

approvals required to conduct NexGen's planned exploration activities will be available on reasonable terms 

and in a timely manner and that general business and economic conditions will not change in a material adverse 

manner. Although the assumptions made by the Company in providing forward looking information or making 

forward looking statements are considered reasonable by management at the time, there can be no assurance 

that such assumptions will prove to be accurate. 

Forward‐looking  information  and  statements  also  involve  known  and  unknown  risks  and  uncertainties  and 

other factors, which may cause actual results, performances and achievements of NexGen to differ materially