Northwest Copper Announces Positive PEA FOR the Kwanika-Stardust Copper-GOLD Project, Describing a Low Capex Project with Scale
Page 1 of 23
News Release
NORTHWEST COPPER ANNOUNCES POSITIVE PEA FOR THE KWANIKA-STARDUST COPPER-GOLD
PROJECT, DESCRIBING A LOW CAPEX PROJECT WITH SCALE
Vancouver, BC – January 5, 2023 – NorthWest Copper Corp. (“NorthWest” or “the Company”) (TSX -V:
NWST) (OTCQX: NWCCF) is pleased to announce the results of the preliminary economic assessment
(“2023 PEA”), conducted by Ausenco Engineering Canada Inc. (“Ausenco”) and Mining Plus Canada
Consulting Ltd (“Mining Plus”), on its 100% owned Kwanika-Stardust Project comprising the Kwanika and
Stardust deposits (the “Project”). This represents the first technical and economic evaluation of the
combined deposits outlining a robust project with manageable initial capital cost and multiple
opportunities for project growth. NorthWest plans to continue to evaluate the possibility of further
synergies with nearby deposits and the proposed Project infrastructure, with a particular focus on the
nearby 100% owned Lorraine Project1.
The 2023 PEA outlines a project that proposes mining approximately 96 million tonnes (“Mt”) of material
in a combination of open pit and underground operations from the Company’s 100% owned Kwanika and
Stardust deposits. The 2023 PEA contemplates a 22,000 tonnes per day (“tpd”) process plant, producing
high-quality copper concentrate with significant gold and silver by-product credits.
Highlights
• The 2023 PEA describes Kwanika-Stardust as a unique project combining manageable initial
capital with a significant Cu-Au production profile:
o Peak copper equivalent (“CuEq”2) production of 152.1 million pounds of copper (“Mlbs”)
per year (year 6) and life of mine (“LOM”) CuEq average production of 90.6 Mlbs per year
over 11.9 years;
o Total LOM production of 694 Mlbs Cu, 803 koz Au, and 3,204 koz Ag (1,078 Mlbs CuEq)
o Average cash operating costs3 of US$1.58/lb CuEq (US$0.44/lb Cu on a by-product4 basis);
o Average all-in sustaining c ost (“AISC”)5 of US$2.01/lb CuEq (US$ 1.12/lb Cu on a by -
product6 basis);
o Initial capital of C$567.9 M (US$438.5 M7), with a construction period of two years;
o Attractive economics with NPV (7%) of C$440.1 M (US$339.8 M) and IRR of 17.1% pre-tax
and NPV (7%) of C$215.0 M (US$166.0 M) and IRR of 12.7% after tax8; and
1 See NI 43-101 technical report titled “Lorraine Copper -Gold Project NI 43-101 Report & Mineral Resource Estimate Omineca Mining Division, B.C,” dated
September 12, 2022 with an effective date of June 30, 2022, filed under the Company’s SEDAR profile at www.sedar.com .
2 CuEq (lbs) = Cu (lbs) + (Au (koz) * Au ($/oz)) / Cu ($/lb) /1000 + (Ag (koz) * Ag ($/oz)) / Cu ($/lb) / 1000, US$3.63 Cu, US$1,650 Au, US$21.50 Ag
3 Cash operating cost on a Co-product basis, calculated with the following formula: (Site Operating Costs) / LOM CuEq (Mlbs), Site Operating Costs = C$23.04 (per
tonne processed)*95,607 kt*0.77 (USD exchange rate).
4 Cash operating cost on a By-product basis, calculated with the following formula: (Site Operating Costs – LOM Gold Revenue – LOM Silver Revenue) / LOM Cu
(Mlbs), LOM Gold Revenue = US$1,321.55M, LOM Silver Revenue = $US 68.53M.
5 AISC Co-product basis, calculated with the following formula: (Site Operating Costs + Treatment, Refining, Transport Costs+ Sustaining Capital + Closure Costs –
Salvage Value) / LOM CuEq (Mlbs), Treatment, Refining, Transport Costs = US$220.96M, Sustaining Capital = C$282.46M*0.77, Closure Costs = US$32.26M, Salvage
Value = US$1.89M.
6 AISC By-product basis, calculated with the following formula: (Site Operating Costs + Treatment, Refining, Transport, + Sustaining Capital + Closure Costs – Salvage
Value – LOM Gold Revenue – LOM Silver Revenue) / LOM Cu (Mlbs)
7 0.77 US$ per C$1.00
8 Economics calculated at US$3.63 Cu, US$1,650 Au, US$21.50 Ag
Page 2 of 23
o At spot prices economics improve, with NPV (7%) of C$665.6 M (US$513.9 M) and IRR of
21.7% pre-tax and NPV (7%) of C$363.3 M (US$280.6 M) and IRR of 16.4% after tax9;
o The 2023 PEA is preliminary in nature. It includes Inferred Mineral Resources that are
considered too speculative geologically to have the economic considerations applied to
them that would enable them to be categorized as Mineral Reserves and there is no
certainty that the 2023 PEA will be realized.
• Mineral Resources include mineralized material from four sources:
o Kwanika Central open pit:
▪ 30.7 Mt of Measured Resources (0.31% Cu, 0.31 g/t Au, 1.05 g/t Ag);
▪ 35.9 Mt Indicated Resources (0.22% Cu, 0.19 g/t Au, 0.80 g/t Ag); and
▪ 4.1 Mt Inferred Resources (0.15% Cu, 0.15 g/t Au, 0.58 g/t Ag);
o Kwanika Central underground block cave:
▪ 25.6 Mt Measured Resources (0.50% Cu, 0.61 g/t Au, 1.62 g/t Ag); and
▪ 11.3 Mt Indicated Resources (0.51 Cu%, 0.65 g/t Au, 1.56 g/t Ag);
o Kwanika South open pit:
▪ 25.4 Mt Inferred Resources (0.28 % Cu, 0.06 g/t Au, 1.68 g/t Ag);
o Stardust underground:
▪ 1.6 Mt Indicated Resources (1.49% Cu, 1.63 g/t Au, 30.1 g/t Ag); and
▪ 4.1 Mt Inferred Resources (1.00% Cu, 1.38 g/t Au, 22.8 g/t Ag);
o Mineral Resources that are not Mineral Reserves do not have demonstrated economic
viability.
• NorthWest is committed to working collaboratively with First Nations to ensure that sound
cultural and environmental practices based on sustainability and shared value are incorporated
into any mine development plans:
o NorthWest will continue to engage based on open communication and collaboration to
create benefits for First Nations;
o The Project will look to minimize the development impact by using existing infrastructure
and processing mineralized material from multiple sources in one central facility;
o The Project plans to connect to the BC Hydro electrical grid and will thereby use primarily
renewable electricity, reducing the Project’s carbon footprint; and
o The Project could contribute to British Columbia’s and Canada’s critical mineral supply by
providing copper, a much-needed element for the green energy transition.
9 Spot price economics calculated at US$3.83 Cu, US$1,840 Au, US$23.97 Ag (as at January 3, 2023)
Page 3 of 23
Table 1: Summary Project Metrics
Production Per Year AISC Economics
Cu
(Mlbs)
Au
(koz)
Ag
(koz)
CuEq10
(Mlbs)
Cu
(US$/lb)
CuEq
(US$/lb)
Initial
Capital
(C$M)
Total
Operational11
ATCF
(C$M)
After-
Tax
NPV-7
(C$M)
After-
Tax
IRR %
LOM
Average 58.31 67.43 269.12 90.56 $1.12 $2.01 $567.90 $1,324.98 $215.04 12.7%
“This study is a major step in demonstrating the value created by combining Kwanika and Stardust, the
cornerstone deposits of the NorthWest portfolio,” stated President and CEO Peter Bell. “We have been
describing a project with manageable initial capital and significant copper production to the market since
creating the Company in 2021. This PEA supports that vision. We are also now working towards advancing
the Project including exploring whether the nearby 100% owned Lorraine Project, located approximately
40 km away , can be developed with the infrastructure contemplated in the Kwanika -Stardust PEA .
Conducting the necessary studies to ascertain whether Lorraine can be incorporated into the Kwanika -
Stardust project will be the main objective of the Company in 2023, as we believe that this will add further
value to the strong project we have outlined with this PEA.”
“The focus in Canada is turning to critical minerals, including copper,” continued Mr. Bell. “Our project is
extremely well located, has both meaningful scale and manageable capex, benefits from existing
infrastructure, has access to renewable power and is in a Tier 1 jurisdiction making it rare and highly
valuable. We look forward to working collaboratively with First Nations to advance the project as part of
BC and Canada’s push for critical Canadian copper production.”
The Company will host a conference call and webcast on Thursday, January 5, 2023 at 11:30 AM Eastern
time (8:30 AM Pacific time). Details to access the call can be found below.
Mineral Resources
Mineral Resources for Kwanika have been updated with parameters from the 202 3 PEA. Stardust is also
updated to reflect refined operating and capital costs. Mineral Resources at Kwanika Central are 95% in
the Measured and Indicated categories, reflecting the amount of drilling and geological data that have
been completed in this area. Kwanika South and Stardust represent areas for both further growth of
Mineral Resources as well as conversion of Inferred Resources to Measured and Indicated Resources. The
quantity of mineralized material was estimated and included in the mine plan using a Net Smelter Return
(“NSR”) threshold approach, alternately called economic cut off, rather than a copper cut-off grade.
10 CuEq (lbs) = Cu (lbs) + (Au (koz) * Au ($/oz)) / Cu ($/lb) /1000 + (Ag (koz) * Ag ($/oz)) / Cu ($/lb) / 1000, US$3.63 Cu, US$1,650 Au, US$21.50 Ag
11 Operational after tax cash flow (“ATCF”) is defined as Total Revenue – Site Operating Costs - Treatment, Refining, Transport Costs - Sustaining Capital -Growth
Capital - Closure Costs - Taxes + Salvage Value ) , Total Revenue = C$5,068.04M, Site Operating Costs = C$ 2,202.87M, Treatment, Refining, Transport Costs =
C$286.96M, Sustaining Capital = C$282.46M, Growth Capital = $493.27M, Closure Costs = C$41.90M, Taxes = C$438.06M, Salvage Value = C$2.46M.
Page 4 of 23
Table 2: Combined summary resource estimate12
Kwanika Central
Open Pit
Economic
Cut-Off US$/t Classification Tonnes (Mt) Cu (%) Au
(g/t)
Ag
(g/t)
Cu
(Mlbs)
Au
(koz)
Ag
(koz)
8.21
Measured 30.7 0.31 0.31 1.05 210.8 310.5 1,041.7
Indicated 35.9 0.22 0.19 0.80 174.9 222.0 923.9
M&I 66.6 0.26 0.25 0.92 385.7 532.5 1,965.6
Inferred 4.1 0.15 0.15 0.58 13.8 20.1 77.3
Underground
Economic
Cut-Off US$/t Classification Tonnes (Mt) Cu (%) Au
(g/t)
Ag
(g/t)
Cu
(Mlbs)
Au
(koz)
Ag
(koz)
16.41
Measured 25.6 0.50 0.61 1.62 284.4 501.3 1,332.6
Indicated 11.3 0.51 0.65 1.56 126.2 236.7 565.1
M&I 36.8 0.51 0.62 1.60 410.6 738.0 1,897.8
Inferred - - - - - - -
Kwanika South
Open Pit
Economic
Cut-Off US$/t Classification Tonnes (Mt) Cu (%) Au
(g/t)
Ag
(g/t)
Cu
(Mlbs)
Au
(koz)
Ag
(koz)
8.21 Inferred 25.4 0.28 0.06 1.68 155.0 52.4 1,373.9
Stardust
Underground
Economic
Cut-Off US$/t Class Tonnes (Mt) %Cu g/t Au g/t Ag Cu
(Mlbs)
Au
(koz)
Ag
(koz)
88.00 Indicated 1.6 1.49 1.63 30.1 52.2 83.1 1,536.4
Inferred 4.1 1.00 1.38 22.8 90.0 181.1 3,004.3
2023 PEA Summary
The 2023 PEA includes capital and operating costs for a potential Kwanika-Stardust mine; as well as
recovery assumptions, metal prices and a mine plan for the combined Project. The 2023 PEA was
developed in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects
(“NI 43-101”) by Ausenco and Mining Plus, using historical and the latest 2022 metallurgical testing data
performed by SGS Minerals, ALS Metallurgy, Bureau Veritas Commodities, and Base Metallurgical
Laboratories Ltd (“Base Met”), with further details on the historic data used shown in the Database section
below. The Company plans to file the complete 2023 PEA NI 43-101 technical report under the Company’s
SEDAR profile at www.sedar.com within 45 days of this news release.
The 2023 PEA will supersede the previous PEA on the Kwanika deposit13 and updates the previous Mineral
Resource estimate on the Kwanika deposit14. The 2023 PEA also updates the prev ious Mineral Resource
estimate on the Stardust deposit15. The table below summarizes the key findings of the 2023 PEA.
12 Please see end of the release for notes to the Mineral Resource Estimate . Mineral Resources that are not Mineral Reserves do not have demonstrated economic
viability
13 See NI 43-101 technical report titled “NI 43-101 Technical Report for the Kwanika Project Preliminary Economic Assessment Update 2017,” dated April 28, 2017
with an effective date of April 3, 2017, filed under the Company’s SEDAR profile at www.sedar.com.
14 See NI 43-101 technical report titled “NI 43-101 Technical Report for the Kwanika Project Resource Estimate Update 2019,” dated April 17, 2019, filed under the
Company’s SEDAR profile at www.sedar.com.
15 See NI 43-101 technical report titled “Stardust Project Updated Mineral Resource Estimate NI 43 -101 Technical Report Omineca Mining Division, British
Columbia,” dated July 2, 2021 with an effective date of May 17, 2021, filed under the Company’s SEDAR profile at www.sedar.com.
Page 5 of 23
Table 3: 2022 PEA Economic Highlights
Base Case Economics Units Pre-Tax After-tax
NPV (7%) C$M $440.10 $215.04
NPV (7%) US$M $339.83 $166.05
IRR % 17.1% 12.7%
Initial Capital C$M $567.90
Sustaining Capital C$M $282.43
Growth Capital16 C$M $493.27
Economic Assumptions Units Base Case
Copper US$/lb $3.63
Gold US$/oz $1,650.00
Silver US$/oz $21.50
Financial Metrics Units LOM
Average Annual Revenue C$M $425.70
Average Annual Operating Costs C$M $185.03
Avg. Ann. Free Cash Flow (after tax) C$M $111.29
The 2023 PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too
speculative geologically to have the economic considerations applied to them that would enable them to
be categorized as Mineral Reserves. There is no certainty that the Project described in the 2023 PEA will
be realized. Table 4 provides a summary of key operating metrics from the 2023 PEA:
Table 4: 2023 PEA Operating Highlights
Operating Statistics Units Avg. LOM
Mine Life Years 11.9
Tonnes Processed ktpa 7,967.3
Strip Ratio17 W:O 1.79
Production (per year)
Copper Mlbs 58.31
Gold koz 67.43
Silver koz 269.12
CuEq Mlbs 90.56
Recoveries – Open Pit
Copper % 84.3
Gold % 60.0
Silver % 57.8
Recoveries – Underground
16 Growth Capital is capital associated with brining new areas of mineralized material into production – namely Kwanika underground block cave and Stardust
underground
17 Strip Ratio only accounts for the mineralized material and waste mined from the Kwanika Central open pit and the Kwanika South open pit. The strip ratios
including mineralized material mined from underground is 0.91.
Page 6 of 23
Operating Statistics Units Avg. LOM
Copper % 89.7
Gold % 71.4
Silver % 70.3
Operating Costs
Cash Cost – Cu with by-products US$/lb $0.44
Cash Cost – CuEq US$/lb $1.58
AISC – Cu with by-products US$/lb $1.12
AISC – CuEq US$/lb $2.01
Economic Sensitivity
Tables 5 and 5a below summarizes the pre-tax and after-tax sensitivities of NPV and IRR to metal prices:
Table 5 – Economic Sensitivity to Metal Prices (C$M, pre-tax)18
Metal Prices NPV (5%) NPV (7%) NPV (10%) IRR (%)
Spot $860.83 $665.55 $439.95 21.7%
52 Week high $1,490.45 $1,207.90 $878.64 31.9%
Base Case + 20% $1,281.04 $1,027.91 $733.40 28.6%
Base Case + 10% $940.35 $734.01 $495.28 23.0%
Base Case $599.67 $440.10 $257.16 17.1%
Base Case – 10% $258.99 $146.19 $19.04 10.6%
Base Case – 20% -$81.70 -$147.72 -$219.08 3.1%
Table 5a – Economic Sensitivity to Metal Prices (C$M, after tax)
Metal Prices NPV (5%) NPV (7%) NPV (10%) IRR (%)
Spot $499.11 $363.32 $207.06 16.4%
52 Week high $904.75 $715.05 $494.60 24.7%
Base Case + 20% $769.84 $598.31 $399.37 22.0%
Base Case + 10% $550.47 $407.87 $243.51 17.5%
Base Case $329.13 $215.04 $84.88 12.7%
Base Case – 10% $104.23 $18.12 -$78.27 7.5%
Base Case – 20% -$129.04 -$187.15 -$249.39 1.9%
Sustainability
Advancement of the Kwanika -Stardust Project is aligned with supplying critical mineral production,
especially copper, in Canada. Collaboration with First Nations is a key part of our effort. The Project would
be designed to have meaningful metal production while minimizing the Project’s environmental footprint.
The Project is in an area of British Columbia with existing infrastructure, hydroelectric power and a local
workforce supporting our programs. Environmental, social and governance (ESG) performance is core to
NorthWest’s longer-term goal to contribute to sustainable econo mies and encourage and promote
18 Base Case Prices US$ 3.63 Cu, US$1,650 Au, US$21.50 Ag, Spot Prices as at January 3, 2023 (US$3.83 Cu, US$1,840 Au, US$23.97 Ag), 52 Week Cu price high
(US$4.94 Cu, US$ 1,790 Au, US$ 23.27 Ag)
Page 7 of 23
cultural and environmental stewardship. The Company has taken a step towards our goals by completing
a comprehensive 2021 ESG report 19 in 2022 , which gives NorthWest a strong baseline to track and
demonstrate ESG progress.
Development of the Project may create many opportunities to bring needed resources to meet the
demands of society and the changing economy. However, development of the Project will also impact the
environment, First Nations and local communities . There are opportunities to build on traditional and
local knowledge to manage these potential impacts and to put systems in place that support a better
understanding of the land, and to encourage and support stewardship. In addition, by working
collaboratively with First Nation communities and leadership we see opportunities to build and support
the development of stronger local economies.
NorthWest envisions a future of shared values, where partnerships with local communities drive a new
kind of mining where the rights of First Nations are recognized and stewardship of the environment and
cultural heritage form the foundation of future development. As a Company we will strive to pursue best
practices as we advance the Project beyond the 2023 PEA.
Next Steps
With completion of the 2023 PEA, NorthWest intends to continue to advance its portfolio of projects. Key
next steps are expected to include:
• Conducting the necessary studies at both Kwanika-Stardust and Lorraine to ascertain whether the
projects could potentially be combined. This will require further work, including metallurgical test
work, transportation studies, general engineering and geological modeling before the Lorraine
Project could be considered for combination with the Project . The Company anticipates
completing metallurgical test work on both the Kwanika-Stardust and Lorraine projects, including:
o Work at Kwanika -Stardust to optimize recovery with a focus on improving recovery of
gold and silver; and
o Work at the nearby Lorraine Project will focus on determining recovery and exploring the
possibility of processing mineralized material from Lorraine at the proposed Kwanika -
Stardust process facility;
• Exploration with a focus on Lorraine, including areas around the current resource area and on the
larger property;
• Exploration at Kwanika-Stardust to test high-grade drill targets;
• NorthWest will continue to proactively engage with First Nations in our geographic area in support
of the responsible development of the Project;
• Develop plans:
o For baseline environmental testing and scoping work in advance of a potential future
environmental assessment (EA) submission; and
o To conduct an energy audit to ensure that the Project is employing current available
technologies and best practices to drive lower carbon emissions. Items studied are
19 The Company’s 2021 ESG Report can be found here: https://northwestcopper.ca/investors/annual-esg-report/
Page 8 of 23
expected to include electrification of the mine fleet and equipment, alternative methods
of haulage and more energy efficient process plant operation.
Opportunities
In addition, to the next steps noted above, the Company is actively exploring several additional
opportunities which the Company hopes will enhance Project value. These include:
• Potentially adding additional mineralized material to the mine plan at Kwanika-Stardust through
additional exploration and drilling;
• Further metallurgical test work on mineralized material from Kwanika -Stardust to optimize
metallurgical recoveries;
• Further engineering and trade -off studies on Kwanika -Stardust to reduce capital and operating
costs and improve operating efficiency;
• Further analysis with respect to optimizing shipping and transportation costs;
• The Company anticipates relying, to the extent feasible, on clean electricity . Further studies
exploring the potential for a ‘net-zero’ emissions mine at Kwanika -Stardust, resulting in a
differentiated project with regulators, investors and local stakeholders;
• Molybdenum is present at Kwanika South at elevated concentrations20. Further study is required
to determine if the addition of a molybdenum circuit could add value to the Project.
Webcast Details
The Company will host a conference call on Thursday, January 5, 2023 at 11:30 AM Eastern time (8:30 AM
Pacific time).
• Via telephone, by calling 1-604-638-5340 or 1-800-319-4610
• Via webcast at: https://services.choruscall.ca/links/northwestcopper202301.html
The webcast will be archived for 90 days following the call at the above-noted link.
Mining
Preliminary mine designs have been developed for the Project based upon the Mineral R esource
estimates for Kwanika-Stardust. Resource models were imported to Minesight® mine planning software
where a Lerch Grossman algorithm was applied to a NSR model to determine possible open pit limits.
The mine plan was developed to mine 95.6 Mt of mineralized material and 86.9 Mt of waste over the LOM
(shown in Figure 1). Mineralized material will be mined from four areas: Kwanika Central open pit (years
1-4), Stardust underground (years 4-9), Kwanika Central underground block cave (years 4-12) and Kwanika
South open pit (years 9-12). Further detail on the Kwanika Central open pit and underground is shown in
Figures 2 and 3, the underground development plan at Stardust is shown in Figure 4, and detail on the
Kwanika South open pit is shown in Figure 5.
20 See NI 43-101 technical report titled “NI 43-101 Technical Report for the Kwanika Project Res ource Estimate Update 2019,” dated April 17, 2019, filed under the
Company’s SEDAR profile at www.sedar.com.