Nuinsco Announces Assay Results Grading up to 35.5 g/t from the El Sid Gold Project

Drill Results

Nuinsco Announces Assay Results Grading up to 35.5 g/t from the El Sid Gold Project 

Positive Analytical Results Increase Confidence in Potential to Quickly Move to Gold Production 

Toronto, March 4, 2019 – Nuinsco Resources Limited (“Nu insco” or the “Company”) (CSE:  NWI) today announced 

positive  analytical  results  from  sampling  at  the  El  Sid  gold  project  in  Egypt,  with  assays  grading  up  to  35.50  g/t 

gold. The average grade of all 239 samples taken from the waste  dump at the past‐producing El Sid gold mine is 

4.47g/t gold. 

“These results are as expected and confirm the wide distributio n of gold mineralization within waste dumps at El 

Sid,” said Paul Jones, CEO. “Given that the waste pile has alre ady been mined, is on surface and has been partially 

processed, the average gold grade is very encouraging from the perspective of economic viability. The Company is 

in  the  process  of  evaluating  gold  recovery  from  the  El  Sid  proj ect  using  conventional,  low‐cost  processing 

m e t h o d s  t o  q u i c k l y  g e n e r a t e  c a s h  f l o w  t o  p r o v i d e  n o n ‐ d i l u t i v e  funding  for  Nuinsco’s  Prairie  Lake  and  Sunbeam 

projects and for the evaluation of potential new project acquisitions.” 

Through its Egyptian subsidiary Z‐Gold Resources Inc., Nuinsco  won a competitive bid for the right to evaluate the 

viability  of  gold  production  from  waste  dumps  and  tailings  at  the  p ast ‐ p r oduc i n g E l S i d m in e  i n Eg y p t ’s E ast e r n 

Desert. Located approximately 90km west of the town of Quseir o n the Red Sea coast, El Sid is easily accessible 

via a paved road that passes through the project site. Three pa st producing gold mines are located on the project 

– the largest of which is the El Sid Mine which operated primar ily between 1947 and 1957 and was Egypt’s largest 

gold producer. 

Site  evaluation,  processing  equipment  selection  and  metallurgy  are  continuing,  and  the  Company  is  rapidly 

moving  toward  a  production  decision.    If  the  project  proves  to  be  economically  viable  the  timeline  to  gold 

production is short – measured in months. 

In addition to the 239 samples co llected from the  El Sid mine  w aste dumps for analysis, an additional 20 blank 

and standard samples were inserted into the sample stream for Q A/QC purposes. The sampling program included 

the  use  of  a  backhoe  to  excavate  trenches  and  pits  into  the  wast e  p i l e  i n  o r d e r  t o  a s c e r t a i n  g r a d e s  o t h e r  t h a n  

from the surface of the pile. The waste dump attains a maximum  thickness of 15m, maximum trench depth was 

4m while pits were excavated at between 10m and 15m below the u pper surface of the waste dump.  All analyses 

were conducted by ALS Limited at their analytical laboratory in Izmir, Turkey. 

Laura  Giroux,  M.Sc.,  P.  Geo.  is  a  qualified  person  as  defined  by  NI  43‐101  and  has  reviewed  and  approved  the 

technical contents of this press release regarding the El Sid Project. 

About Nuinsco Resources Limited 

Nuinsco Resources has over 45 years of exploration success and  is a growth oriented, multi‐commodity mineral 

exploration  and  development  company  focused  on  prospective  oppo rtunities  in  Canada  and  internationally. 

Currently the Company has two properties in Ontario – the high‐ grade Sunbeam gold prospect near Atikokan and 

the large, multi‐commodity (rare‐earths, niobium, tantalum, phosphorus) Prairie Lake project near Terrace Bay. In 

addition, Nuinsco has recently completed an agreement for gold  exploitation at the El Sid project in the Eastern 

Desert of Egypt – a project with the potential to provide near‐term revenue. 

Forward‐Looking Statements 

This  news  release  contains  certain  "forward‐looking  statements."  All  statements,  other  than  statements  of  historic  fact,  that address  activities,  events  or 

developments that Nuinsco believes, expects or anticipates will  or may occur in the future are forward‐looking statements. For ward‐looking statements are 

often, but not always, identified by the use of words such as " seek," "anticipate," "believe," "plan," "estimate, “expect," an d "intend" and statements that an 

event  or  result  "may,"  "will,"  "can,"  "should,"  "could,"  or  "might"  occur  or  be  achieved  and  other  similar  expressions.  These forward‐looking  statements 

reflect  the  current  expectations  or  beliefs  of  Nuinsco  based  on  information  currently  available  to  Nuinsco.  Forward‐looking  sta t e m e n t s  a r e  s u b j e c t  t o  a  

number of risks and uncertainties that may cause the actual res ults of Nuinsco to differ materially from those discussed in th e forward‐looking statements, 

2

and even if such actual results are realized or substantially r ealized, there can be no assurance that they will have the expe cted consequences to, or effects on 

Nuinsco. Factors that could cause actual results or events to d iffer materially from current expectations include, among other  things, failure to successfully 

complete financings, capital and other costs varying significan tly from estimates, production ra tes varying from estimates, ch anges in world copper and/or 

gold markets, changes in equity markets, uncertainties relating  to the availability and costs of financing needed in the futur e, equipment failure, unexpected 

geological  conditions,  imprecision  in  resource  estimates,  succe ss  of  future  development  initiatives,  competition,  operating  pe rformance  of  facilities, 

environmental and safety risks, delays in obtaining or failure  to obtain tenure to properties and/or necessary permits and app rovals, and other development 

and operating risks. Any forward‐looking statement speaks only  as of the date on which it is made and, except as may be requir ed by applicable securities 

laws, Nuinsco disclaims any intent or obligation to update any  forward‐looking statement, whether as a result of new informati on, future events or results or 

otherwise. Although Nuinsco believes that the assumptions inher ent in the forward‐looking statements are reasonable, forward‐l ooking statements are not 

guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein. 

El  Sid  Project  sample  location  distribution  –  239  samples  collected  from  the  surface  of  the  waste 

dump and from trenches and pits excavated by back‐hoe. 

To learn more, please contact:     

Paul Jones, CEO  Sean Stokes, Executive VP  Cathy Hume, Consultant  Website: 

www.nuinsco.ca 

[email protected]   [email protected]    [email protected]   Twitter: 

@NWIResources 

416 626‐0470 x 229  416 626‐0470  x 224  416 868‐1079 x 231   

3

Distribution of gold grade for the 239 samples collected from the El Sid waste pile.  

Average=4.47g/t