Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NUAG.TO ·

New Pacific Acquires the Carangas Silver Project, Bolivia

Mergers & Acquisitions Property Options & Staking

1

NEWS RELEASE

Trading Symbol: TSX: NUAG

OTCQX: NUPMF

NEW PACIFIC ACQUIRES THE CARANGAS SILVER PROJECT,

BOLIVIA

VANCOUVER, BRITISH COLUMBIA – APRIL 12, 2021: New Pacific Metals Corp. (“New Pacific”

or the “Company”) (TSX:NUAG; OTCQX: NUPMF) is pleased to announce that the Company has

signed an agreement with a private Bolivian company (the “Vendor”), to acquire a 98% interest in

the Carangas silver project (the “Carangas Project” or the “Project”), located in the Oruro

Department, Bolivia. New Pacific will cover 100% of the future expenditures on exploration, mining,

development, and production activities. The agreement has a term of 30 years and is renewable

for an additional 15 years. An initial discovery diamond drill program is planned to commence

upon receipt of the related permit from the local authorities.

CARANGAS PROJECT HIGHLIGHTS:

▪ Former silver mining district, located on La Ruta de la Plata (the Silver Road), containing

broad zones of outcropping silver mineralization and historically exploited high -grade

silver veins;

▪ Highlights of due diligence sampling include 30 meters (“m”) at an average grade of 101

grams per tonne (“g/t”) silver, 15 m at an average grade of 252 g/t silver, and 8 m at an

average grade of 512 g/t silver;

▪ Near surface bulk tonnage and high-grade vein targets identified;

▪ Leverages New Pacific’s exploration and project development expertise and cements the

Company’s first mover status in an under-explored silver district; and

▪ 5,000-meter discovery diamond drill program planned for 2021.

Dr. Mark Cruise, CEO of New Pacific, stated “The addition of the Carangas Project fits well with

the Company’s strategy to become a premier Latin American focused precious metal explorer

and developer. Initial field work, including target generation, positions us well for a successful drill

program and compliments our planned exploration programs at our Silverstrike Project, in addition

2

to the advanced exploration and development studies currently in progress on our flagship Silver

Sand project.”

CARANGAS PROJECT OVERVIEW

The Carangas Project consists of two exploration concessions totaling 6.25 square kilomet ers

(“km”), located approximately 180 km southwest of the city of Oruro, in southwest Bolivia (Figure

1). Situated in the Bolivian altiplano at an average elevation of 3,800 m, ac cess to the Project is

via paved Highway 12 and a municipally maintained 30 km gravel road.

Geologically, the Project lies within the South American Epithermal Belt which hosts large

precious metal deposits and operations in neighboring countries but re mains under-explored in

Bolivia. The Project is comprised of a Tertiary volcanic complex approximately 1.6 km long in

east-west direction and 1.4 km wide in north -south direction, which stands 150 m above the

surrounding fluvial plains. An ephemeral stream divides the volcanic complex into two separate

domes known as West and East Domes, respectively (Figure 2).

Figure 1: Location of the Carangas Project in the Department of Oruro, Bolivia

3

Figure 2: Satellite Imagery of the Carangas Project, Bolivia, including West and East Domes

GEOLOGY AND MINERALIZATION

West Dome consists of felsic to dacitic volcanic facies (lithic and/or ash fall tuffs ) cross-cut by

multi-phase mineralized hydrothermal and/or structural breccia bodies and rhyo-dacitic dykes.

East Dome consists of lithic tuffs cut by faults and associated minor breccia zones.

The Domes are dissected by a series of laterally extensive , steeply dipping to sub -vertical,

extensional fault and fracture zones of half meter to more than one meter wide, predominantly

striking east-west, west-northwest and northwest. Silver-rich polymetallic mineralization occurs

as millimeter to multi-meter-wide veins (which were historically exploited), veinlets and

disseminations in the matrix of the breccias and/or associated volcanic host units.

The area between the West Dome and East Dome is a flat valley, approximately 200 m wide,

filled by fluvial sediments (Figure 2).

4

HISTORY OF MINING AND EXPLORATION

Mining is thought to have commenced in the sixteenth century and continued intermittently until

the early twentieth century. The Project, and in particular West Dome, contains extensive surface

workings in addition to underground mine adits, shafts and ass ociated processing and smelting

infrastructure. There is no active mining at the present time.

Modern mineral exploration, by local mining interests, occurred in the early 1980’s. The first drill

program comprising of nine reverse circulation holes for a total of 1,000 m was carried out in 1995.

Written records for the program report a drill intercept (1) of 116 m at an average grade of 95 g/t

silver (from 18 m to 134 m downhole), including 16 m at 325 g/t silver (from 66 m to 82 m

downhole), including a 4-m mined-out interval in hole RC-05.

A second drill program was conducted in 2000 , also by a local Bolivian group, with six diamond

drill holes for a total of 914 m completed. The results are in line with prior exploration and include

a drill intercept (1) of 76 m at an average grade of 90 g/t silver, 0.96% lead, and 0.12% zinc (from

0 m to 76 m downhole), including 8 m at 266 g/t silver, 1.02% lead, and 0.06% zinc (from 26m to

34 m downhole) in hole DDH-01. No exploration activities were recorded after the year 2000.

Note:

(1) The drill results are historic in nature and should not be relied upon. The historical drill intercepts were not

verified by the Company as the drill cores and sample pulp/rejects are not available and there are other

inherent limitations and uncertainties. The drill intercepts are not considered as true width of mineralization

due to little knowledge of spatial morphology of mineralization at this early stage.

NEW PACIFIC DUE DILLIGENCE

New Pacific conducted reconnaissance scale geological, structural and alteration mapping and

geochemical sampling of the Project including the collection of representative characterization

(“grab”) (1) and continuous channel chip samples (2) from surface outcropping mineralization,

historical mine dumps and, where safely accessible, underground workings.

A total of 282 characterization samples and 729 continuous channel rock chip samples were

collected from surface outcrop, underground mining faces, and open pit walls. The grab samples

returned an average silver grade of 229 g/t (range of 1 g/t to 1,950 g/t); an average lead grade of

1.02% (range of 0 % to 7.33%), and an average zinc grade of 0.16% (range of 0% to 3.28%),

reflecting the presence of widespread geochemically anomalous mineralization . In general,

continuous chip samples intercepted multiple wide mineralized zones , where outcrop or

underground workings are accessible. Table 1 contains a summary of selected composite

intervals of continuous chip samples.

5

Table 1: Selected Composite Intervals of Continuous Chip Samples from the Carangas Project,

Bolivia.

Target Location From (m) To (m) Interval (m) Ag (g/t) Pb (%) Zn (%) Note

West Dome

Chip_1 0.0 30.0 30.0 101 0.77 0.03 composite

Chip_2 0.0 6.6 6.6 280 0.79 0.01 composite

Chip_3 0.0 15.3 15.3 252 1.32 0.02 composite

Chip_4 0.0 8.0 8.0 512 1.66 0.06 composite

Chip_5 2.0 80.0 78.0 65 0.98 0.21 composite

East Dome

Chip_6 14.0 68.0 54.0 52 0.30 0.14 composite

Chip_7 18.0 56.0 38.0 98 0.66 0.21 composite

Chip_8 0.0 2.0 2.0 1,100 0.62 0.25 single sample

Chip_9 0.0 1.0 1.0 1,755 0.93 0.59 single sample

At East Dome (F igure 3), mineralization occurs as fracture and fault zones cutting the lithic tuff

host unit. Continuous rock chip sampling returned broad mineralized zones, including up to 54.0

m at 52 g/t silver, 0.30% lead and 0.14% zinc, and 38.0 m at 98 g/t silver, 0.66% lead and 0.21%

zinc. Sampling also confirmed the presence of numerous high grade narrow zones of silver-rich

mineralization including up to 2.0 m at 1,100 g/t silver, 0.62% lead and 0.25% zinc, and 1.0 m at

1,755 g/t silver, 0.93% lead and 0.59% zinc.

At West Dome (Figure 4), channel chip sampling confirmed the presence of multiple mineralized

zones including up to 30.0 m at 101 g/t silver and 0.77% lead, 6.6 m at 280 g/t silver and 0.79%

lead, and 15.0 m at 252 g/t silver and 1.32% lead. Encouraging intervals of continuous rock chip

sampling from underground include 8.0 m at 512 g/t silver and 1.66% lead, and 78.0 m at 65 g/t

silver, 0.98% lead and 0.21% zinc. All channel chip samples were collected from mineralized

hydrothermal breccias, which are cut by mineralized fractures and faults.

Notes:

(1) Grab samples are selective in nature and are not representative of the average in-situ mineralization.

(2) Rock chip samples were taken across mineralized structures from surface outcrops and underground faces.

Sample interval is close to true width of mineralization.

6

Figure 3: Geology Map of East Dome, Carangas Project, Bolivia, including Sample Results

7

Figure 4: Geology Map of West Dome, Carangas Project, Bolivia, including Sample Results

NEAR-TERM STRATEGY AND NEXT STEPS

Based on the historical mining activities evidenced by widespread mine dumps and numerous

surface and underground mining workings, historical exploration results, and the results of the

Company’s initial exploration programs, the Company believes that the Carangas Project has the

potential to host near surface bulk tonnage mineralization and high -grade mineralization ,

controlled by narrow structures, at relatively shallow depths.

8

Permitting is in progress and the Company plans an initial discovery diamond drill program of up

to 5,000 m in 2021. Upon completion of the program, New Pacific will provide an update on the

results. Contingent on these drill results, additional drilling may be conducted to expand upon and

define any new discoveries.

QUALITY ASSURANCE AND QUALITY CONTROL

All samples in respect of the exploration program at the Carangas Project, conducted by the

Company and discussed in this news release, were shipped in securely -sealed bags by New

Pacific staff in the Company’s vehicles, directly from the field to ALS Global in Oruro, Bolivia for

preparation, and ALS Global in Lima, Peru for geochemical analysis. ALS Global is an ISO 17025

accredited laboratory independent from New Pacific. All samples are first analyzed by a multi-

element ICP package (ALS code ME -MS41) with ore grade over specified limits for silver, lead

and zinc further analyzed using ALS code OG46. Further silver samples over specified limits are

analyzed by gravimetric analysis (ALS code of GRA21).

The assay results of the grab samples are used for reconnaissance purpose and, therefore, no

certified reference materials and blank materials were inserted to the normal sample sequence in

the field. Internal Quality Assurance/Quality Control (“ QAQC”) results from ALS Global did not

show any significant bias of analysis or contamination during sample preparation. For rock chip

samples, certified reference materials, blank samples and field duplicate samples were inserted

to normal sample sequences prior to delivery to the laboratory for preparation and analysis. The

results of QAQC samples did not show any significant bias of analysis or contamination during

sample preparation.

QUALIFIED PERSON

The scientific and t echnical information contained in this news r elease has been reviewed and

approved by Alex Zhang, P. Geo., Vice President of Exploration, who is a Qualified Person for

the purposes of National Instrument 43-101 — Standards of Disclosure for Mineral Projects (“NI

43- 101”). The Qualified Person ha s verified the information disclosed herein, including the

sampling, preparation, security and analytical procedures underlying such information, and is not

aware of any significant risks and uncertainties that could be expected to affect the reliability or

confidence in the information discussed herein.

ABOUT NEW PACIFIC

New Pacific is a Canadian exploration and development company, which owns the flagship Silver

Sand Project, located in the Potos i Department of Bolivia, the Silverstrike Project, in the La Paz

Department of Bolivia and the Carangas Project in the Oruro Department of Bolivia. The Company

is focused on progressing the development of its flagship project, while growing Mineral

Resources through the exploration and acquisition of properties in the Americas.

For further information, please contact:

Stacey Pavlova, CFA