Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NOU.TO ·

NMG Issues Results of Feasibility Study for its Integrated Ore-to-Anode- Material Model Projected to be North America’s Largest Natural Graphite Operation with Attractive Economics This news release constitutes a “designated news release” for the purposes of the

Economic Studies

NMG Issues Results of Feasibility Study for its Integrated Ore-to-Anode-

Material Model Projected to be North America’s Largest Natural Graphite

Operation with Attractive Economics

This news release constitutes a “designated news release” for the purposes of the

Company’s prospectus supplement dated January 21, 2022, to its short form base shelf

prospectus dated May 19, 2021, as amended by amendment no. 1 dated January 19, 2022.

• NMG is developing a turnkey natural graphite operation with competitive

advantages due to its privileged location, vertical integration, cost structure, ESG

credentials and experienced team.

• The Company’s Phase-2 Matawinie Mine and Bécancour Battery Material Plant

projects, located within a 150-km radius of Montréal, Québec, show attractive

economics and robust operational parameters underpinned by a large mineral

property, NMG’s proprietary technologies, and clean hydroelectricity powering its

operations.

• The Feasibility Study of NMG’s integrated operation indicates a 21% after-tax IRR

and NPV of C$ 1,581 million based on current projections of pricing prepared by a

third-party expert for high-purity flakes and advanced graphite materials.

• NMG’s integrated production flowsheet provides the flexibility to distribute

graphite concentrate per flake size and market demand in order to cater to the most

profitable segments.

• NMG’s phased approach has helped de-risk NMG’s projects while accelerating the

engineering of Phase-2 operations, generating process and cost optimization, and

supporting commercialization with potential customers.

• NMG is designing a mine of the future, targeted to be all-electric, complemented by

clean advanced beneficiation facilities in order to provide battery and EV

manufacturers with responsibly extracted, environmentally transformed, and

locally sourced green anode material.

• Shareholders and analysts are invited to attend an Investor Briefing at 10:30 a.m.

ET hosted by NMG’s Management Team via webcast:

https://us06web.zoom.us/webinar/register/WN_XA0uyzAQTBiPinZmx3pvuA

MONTRÉAL--(BUSINESS WIRE)--July 6, 2022--Developing a local, carbon-neutral and

traceable turnkey supply of advanced materials for the Western World, Nouveau Monde

Graphite Inc. (“NMG”, “Nouveau Monde” or the “Company”) (NYSE: NMG, TSXV: NOU)

releases the results of its feasibility study (the “Study”) completed in accordance with the

National Instrument 43-101 (“NI 43-101”) for its integrated business operation comprised of the

Phase-2 Matawinie Mine and Bécancour Battery Material Plant projects. The Study, conducted

by engineering firm BBA Inc. (“BBA”) with the support of various technical consultants, has

demonstrated strong economics for NMG’s model as the battery and electric vehicle (“EV”)

manufacturers seek alternatives for sourcing their graphite-based solutions amidst growing

demand and projected structural deficit of production in the next decade. The Company is ideally

positioned to cater to the North American and European markets with its large graphite deposit,

proprietary ecotechnologies, demonstrated production capacity thanks to its Phase-1 operations,

as well as preferential jurisdiction advantages including clean hydropower, flexible logistical

base and stable fiscal and political environment.

Updating resources and reserves, operational, and financial metrics of the Matawinie Mine 2018

bankable feasibility study (effective as of July 10, 2018 and issued on December 10, 2018), the

Study also layered the production and economics structure of the Bécancour Battery Material

Plant, the process and engineering optimizations generated in recent months, the latest market

pricing as per Benchmark Mineral Intelligence’s assessment, as well as capital expenditures

(“CAPEX”) and operating expenses (“OPEX”) profile amidst current economic conditions.

These combined parameters for a projected annual average production of 103,328 tonnes per

annum (“tpa”) of high-purity flake graphite concentrate at the Matawinie Mine and 42,616 tpa of

anode material plus 3,007 tpa of purified jumbo flakes at the Bécancour Battery Material Plant,

using a portion of Matawinie’s production as feedstock, indicate an after-tax net present value

(“NPV”) of C$ 1,581 million and internal rate of return (“IRR”) of 21%.

Arne H Frandsen, Chair of NMG, said: “Market trends have accelerated in past months and

while inflation and logistics turbulences present a more challenging environment, we have

demonstrated our graphite expertise, advanced manufacturing capacity and complex project

management skills to execute our vision of an integrated green anode material production. The

successful upstream integration is designed to ensure that we have access to high-quality,

responsible feedstock for decades to come, and provides battery and EV manufacturers with the

assurance of a traceable, local, and carbon-neutral supply.”

Table 1: Economic highlights of NMG’s integrated Phase-2 graphite operations.

ECONOMIC

HIGHLIGHTS Matawinie Mine Bécancour Battery Material Plant INTEGRATED

NMG MODEL

Pre-tax NPV (8%

discount rate) C$ 986 M C$ 1,374 M C$ 2,360 M

After-tax NPV (8 %

discount rate) C$ 571 M C$ 1,010 M C$ 1,581 M

Pre-tax IRR 28.2% 22.8% 24.6%

After-tax IRR 22.2% 20.4% 21.0%

Pre-tax payback 3.2 years 4.3 years 3.9 years

After-tax payback 3.7 years 4.5 years 4.2 years

Annual average

production

103,328 tonnes of

graphite concentrate

42,616 tonnes of anode material 3,007 tonnes

of purified jumbo flakes 18,384 tonnes of by-

product fines

-

Life of mine (“LOM”) 25 years - -

Initial CAPEX C$ 481 M C$ 923 M C$ 1,404 M

Annual OPEX C$ 58 M C$ 136 M C$ 195 M

CAPEX and OPEX were established from test work results, Phase-1 operations, supplier

quotations and consultant’s in-house databases. Estimates being currently at the market's peak as

influenced by inflationary trends, NMG and its consulting firms have refined design,

engineering, and construction parameters to enable cost optimization and competitive pricing of

NMG’s production. Québec’s affordable clean hydropower underpins the Company’s

technologies, economics structure and carbon-neutrality commitment.

NMG’s integrated business model, with a secured feedstock, close-by operations at the western

market’s doorstep and operational flexibility to adapt production based on demand, represents a

stable and cost-effective structure in today’s everchanging macroeconomics.

Eric Desaulniers, Founder, President, and CEO of NMG, commented: “We have come a long

way from our initial Matawinie Mine project to develop an integrated operation tailored to the

market’s technical requirements and sourcing strategy. NMG is positioning itself as North

America’s largest, fully integrated natural graphite production to relieve battery and EV

manufacturers from their overreliance on Chinese production. With attractive economics, strong

ESG credentials, demonstrated execution capacity, and high-purity advanced materials, we are

set to provide a turnkey large-scale solution for the booming local battery value chain. Our

significant forecasted incremental annual operating profit potential is a testimony that it is

possible to embrace sustainable development and profitability to the benefit of all stakeholders.”

Product Offering and Market

The integrated material flowsheet developed by NMG is designed to leverage the distribution of

graphite concentrate flake sizes to be produced at the Phase-2 Matawinie Mine by catering to the

most profitable market segments. Jumbo to coarse flakes will be destined to high-purity, high-

margin specialty and traditional markets at a LOM average price of C$ 2,135 per tonne. While

fine to intermediate flakes will be transformed into coated spherical purified graphite (“CSPG”)

at the Phase-2 Bécancour Battery Material Plant for sales as anode material for lithium-ion

battery applications at a LOM average price of C$ 11,540 per tonne. A portion of jumbo flakes

will also undergo refinement at the Bécancour Battery Material Plant to produce purified jumbo

flakes for niche applications such as heat dissipators in 5G technologies and bipolar plates in

hydrogen fuel cells. By-products from this facility will also be sold to optimize the Bécancour

basket price.

Selling prices were calculated using forecasts provided by Benchmark Mineral Intelligence, an

IOSCO-regulated price reporting agency and market intelligence publisher for the lithium-ion

battery to EV supply chain. They were estimated for the North American market where the

Company is expected to have competitive advantages over international producers, namely its

carbon-neutral footprint, multimodal logistical base, stable political jurisdiction and exclusion

from U.S. import tariffs on graphite.

Pressure caused by gigafactories development across the world, limited production capacity

impacted by Chinese pandemic measures and turbulent logistics is reflected in the year-over-year

flake graphite price increase of 37% (Benchmark Mineral Intelligence, May 2022). The global

lithium-ion battery production capacity pipeline to 2031 now reaches 6,660 GWh, driving

associated projections for graphite demand to 7,993,000 tpa, the largest of all battery metals.

Mineral Resource and Reserves

The mining property (the “Mining Property” or the “Tony Block”) presently consists of 159

contiguous map-designated claims totalling 8,266.42 hectares (“ha”) wholly owned (100%) by

NMG. The Matawinie Mine project lies within the municipality of Saint-Michel-des-Saints,

Québec, Canada, approximately 120 km as the crow flies north of Montréal.

Exploration work on the Mining Property targeted graphite mineralization and consists to date of

airborne geophysics, prospecting, ground TDEM surveying, trenching/channel sampling and

core drilling. Surface and core samples were also collected for metallurgical and geomechanical

tests. Exploration work uncovered significant crystalline flake graphite mineralization ultimately

leading to the identification of Mineral Resources and Reserves.

Mineral Resources have been estimated for the West Zone of the Mining Property. These

Mineral Resources are based on 8,274 assay intervals collected from 27,888.24 m of core drilling

and three (3) surface trenches providing 207 channel samples. Proper quality control measures,

including the insertion of duplicate, blank and standard samples, were used throughout the

exploration programs and returned within acceptable limits.

Table 2: Current Pit-Constrained Mineral Resource Estimate for the West Zone1

Mineral Resource Category2 Current Resource (May 20, 2022) 7

Tonnage (Mt)5,6 Grade (% Cg)3 Contained Graphite (Mt)

Measured 28.5 4.28 1.22

Indicated 101.8 4.26 4.33

Measured + Indicated 130.3 4.26 5.55

Inferred4 23.0 4.28 0.98

1. The Mineral Resources provided in this table were estimated by Yann Camus, P.Eng. SGS of Canada Inc. -

Geological Services (“SGS Geological Services”) using current Canadian Institute of Mining, Metallurgy

and Petroleum (“CIM”) Standards on Mineral Resources and Reserves, Definitions and Guidelines.

2. Mineral Resources that are not Mineral Reserves have not demonstrated economic viability. Additional

trenching and/or drilling will be required to convert Inferred and Indicated Mineral Resources to Measured

Mineral Resources. There is no certainty that any part of a Mineral Resource will ever be converted into

Reserves.

3. All analyses used for the Resource Estimates were performed by ALS Minerals Laboratories and delivered

as graphitic carbon (“% Cg”), internal analytical code C-IR18.

4. Inferred Mineral Resources represent material that is considered too speculative to be included in economic

evaluations. Additional trenching and/or drilling will be required to convert Inferred Mineral Resources to

Indicated or Measured Mineral Resources. It cannot be assumed that all or any part of the inferred

resources will ever be upgraded to a higher resource category.

5. Current Resource effective May 20, 2022.

6. Mineral Resources are stated at a cut-off grade of 1.78 % Cg.

7. Standards used for this resource update are the same standards produced over the course of the 2018

Feasibility Study (effective as of July 10, 2018 and issued on December 10, 2018) and the Resource

Update (results published March 19, 2020). The difference comes mainly from a newly accessible land

package along the Hydro-Québec power line.

A combined Mineral Resource of the South-East and South-West zones is also present on the

Mining Property. While these deposits are part of the Property, they have not been studied to be

integrated in the Mineral Reserves or the mine plan.

The table below presents the Mineral Reserves which have been estimated for the West Zone of

the Matawinie Deposit.

Table 3: Matawinie Mineral Reserves for the West Zone

Category Tonnage (Mt) Grade (% Cg) Contained Graphite (Mt)

Proven 17.3 4.16 0.7

Probable 44.3 4.26 1.9

Proven & Probable 61.7 4.23 2.6

The Qualified Person for the Mineral Reserve Estimate is Jeffrey Cassoff, P.Eng., of BBA Inc.

The effective date of the estimate is July 6, 2022.

Mineral Reserves were estimated using a graphite concentrate average selling price of C$2,135/tonne, and consider

a 2% royalty, and selling costs of C$47.92/tonne. An average grade of 97% was considered for the graphite

concentrate.

A metallurgical recovery of 93% was used.

A cut-off grade of 2.20% Cg was used.

The strip ratio for the open pit is 1.16 to 1.

The Mineral Reserves are inclusive of mining dilution and ore loss.

The reference point for the Mineral Reserves is the primary crusher.

Totals may not add due to rounding.

Matawinie Mine

The Matawinie Mine will leverage the West Zone deposit with an average production of 103,328

tpa of high-purity graphite concentrate over the LOM. The project demonstrates exceptional

potential due to its significant high-purity Mineral Reserves and low-cost operational model,

coupled with a skilled workforce, high-quality infrastructure, including paved roads and

hydroelectricity, as well as the dynamic regional business ecosystem.

The deposit will be mined using conventional open-pit mining methods consisting of drilling,

blasting, loading, and hauling. Estimation of the Mineral Reserves included pit optimization, pit

design, mine scheduling, and the application of modifying factors to the Measured and Indicated

Mineral Resources. To maximize the NPV, mining phases have been designed and incorporated

into the mining sequence to defer waste rock stripping and provide a balanced blended feed

grade for the concentrator over the LOM. The mine plan is successful at achieving the targeted

concentrate production with a strip ratio of 1.16:1 and an average grade of 4.23% Cg over the

25-year LOM.

A concentrator will be built adjacent to the pit. The concentrator was designed based on the

results from the metallurgical testing at NMG’s Phase-1 mineral processing facility plant and at

external labs. Through crushing, milling, flotation, cleaning, and drying, the ore is concentrated

to attain 97% Cg and classified per flake size. Water recycling is maximized throughout the

process.

Table 4: Graphite Concentrate Size Fraction Proportion

Graphite Concentrate Flakes Size Fraction Proportion

Jumbo (+50 mesh) 14.8%

Coarse (-50+80 mesh) 33.4%

Intermediate (-80+150 mesh) 27.7%

Fine (-150 mesh) 24.1%

Tailings produced by the concentrator will be separated into non-acid generating (“NAG”) and

potentially-acid generating (“PAG”) for co-disposal with waste rock. A co-deposition storage

facility will be located at surface and as of Year 8, tailings will be returned to the pit using the

co-disposal system. The deposit will be mined from south to north to ensure adequate space is

available for in-pit backfilling. See Environmental Design & Carbon Neutrality Commitment

section for additional information.

As part of its electrification strategy, NMG is committed to having both heavy equipment used

for mining operations and ore concentration and processing activities become fully electric

within the first five years of production. NMG’s electrification plan is not presented in this Study

as active planning and development are ongoing with Caterpillar Inc., which is expected to

supply the equipment using their Job Site Solution service model. With this model, NMG would

pay for machine use on an hourly basis which includes machine supply and maintenance (parts

and service) and a fleet management system. Electrical trucks and equipment would be

introduced into the mining fleet as they become available. Projected to be the world’s first all-

electric open-pit mine, the Matawinie Mine could reduce CO2 emissions by over 300,000 tonnes

over the mine’s lifespan.

Table 5: Operational and Economic Highlights of the Matawinie Mine

Parameters

LOM 25 years

Nominal annual processing rate 2.55 M tonnes

Stripping ratio (LOM) 1.16:1

Average grade (LOM) 4.23% Cg

Average recovery 93%

Average annual graphite concentrate production (LOM) 103,328 tonnes

Finished product purity 97% Cg

CAPEX C$ 481 M

Annual OPEX C$ 58 M

OPEX cost per tonne of graphite concentrate C$ 565/tonne

Matawinie average basket price (LOM) C$ 2,135/tonne

All governmental permits and municipal authorizations pertaining to exploration, geotechnical,

hydrogeological, and early preparatory works to date have been obtained. The ministerial decree

authorizing the Matawinie Mine (Decree # 47-2021) was granted by the Québec Government on

January 20, 2021; the latest operational parameters will be presented to governmental authorities

for adjustment.

Early works for the Matawinie Mine started in Q2-2021 with activities related to tree clearing,

construction of the nearly 8-km access road, preparation of the industrial pad, and civil works for

environmental infrastructure.

In striving to limit potential impacts and plan beyond the LOM, the Company has developed the

Matawinie Mine with environmental and social considerations at the forefront. NMG has and

continues to actively engage with the local community and the Atikamekw First Nation. NMG

has signed a collaboration and benefit-sharing agreement with the Municipality of Saint-Michel-

des-Saints (2020) as well as a framework agreement (2018) and a pre-development agreement

(2019) with the Atikamekw First Nation. The Company is actively progressing towards the

elaboration of the impact and benefit agreement with the Atikamekw First Nation for the Phase-2

Matawinie Mine to maximize opportunities for Indigenous workers, contractors, and the

community.

Bécancour Battery Material Plant

NMG’s advanced manufacturing operations will be regrouped at its Phase-2 Bécancour Battery

Material Plant located in Bécancour, Québec, approximately 150 km northeast of Montréal, on

the Saint Lawrence River. The robust local infrastructure provides the Company with a direct

supply of required chemicals in addition to affordable hydroelectricity, a skilled workforce, and a

multi-modal logistical base that includes a major international port in proximity to U.S. and

European markets. Bécancour is rapidly attracting important industrial players in the battery

materials and cell manufacturing space, supported by the Québec Government’s battery hub

strategy. Twenty industrial and commercial projects are planned or under study, including

BASF, GM-Posco, Vale and Nemaska Lithium.

In 2021, NMG purchased a 200,000-m² land in the Bécancour industrial park, adjacent to its

chlorine supplier’s facility – Olin Corporation, to build its integrated manufacturing facility of

anode material for lithium-ion batteries. The property presents no environmental limitations for

construction. It offers all necessary infrastructure to have a safe and direct pipeline of chemical

supply from Olin as well as quick access to rail, port, and road for both importing raw materials

and exporting final products throughout North America and Europe.

Regrouping onsite all beneficiation units, the Bécancour Battery Material Plant is designed to

receive approximately 63,775 tpa of graphite concentrate from the Matawinie Mine to be

transformed into 42,616 tpa of CSPG, 3,007 tpa of purified flakes and 18,384 tpa of by-product

fines, a valuable graphite material.

For CSPG production, the finest flake size fraction graphite concentrate will undergo

micronization and spheronization (“shaping”), purification and coating. A portion of the jumbo

flake production from the Matawinie Mine will be treated onsite through purification only to

produce purified jumbo flakes.

The shaping process, essentially a mechanical transformation, reduces the flake size

(micronization) to D50 of approximately 10 to 20 microns and rounds graphite material

(spheronization) to increase the density of the spherical graphite for battery use. Shaping will

also generate by-product fines to be sold as carbon riser.

NMG’s proprietary carbochlorination purification process elevates graphite materials to

≥99.95% Cg while respecting purity specifications of end-users. The carbochlorination process

involves the injection of chlorine gas into furnaces at high temperatures to remove impurities

contained in the graphite. Leveraging Québec’s abundant, clean, and affordable hydropower, the

Company’s technology avoids using hydrofluoric acid in favor of high temperatures and the

addition of chlor-based reagent, hence providing a greener and more sustainable alternative to

that currently used in traditional anode material production. Production at NMG’s Phase-1

purification facility has demonstrated the performance of this ecotechnology with large-scale

samples produced at 99.99% purity. Piloting is ongoing and set to continue over H2-2022 to

finalize the scope of the purification sector of the plant.

The ultimate beneficiation step, coating is instrumental to battery technology. By applying a

nanometric layer of amorphous carbon on the surface of spheronized purified graphite, coating

helps create a stable electrolyte interface layer in the battery system and increase initial

coulombic efficiency and discharge capacity, thus extending the battery performance over time.

NMG’s coating technology is projected to reduce the energy consumption of this process up to

25% compared to the dominant manufacturing operations, with a minimal environmental

footprint thanks to the Company’s access to clean hydropower and its strong ESG operational

parameters. The module built at NMG’s Phase-1 plant will be replicated and scaled up for the

Phase-2 Bécancour Battery Material Plant. The technology provides versatility for the use of

different precursors as research and development (“R&D”) advances.

Piloting of all Phase-1 battery material modules is ongoing to produce large samples for battery

manufacturers in order to accelerate the commercial qualification of the battery-grade

commercial products.

Table 6: Operational and Economic Highlights of the Bécancour Battery Material Plant

Parameters

Annual throughput 63,775 tonnes

CSPG yield ≥70%

Annual CSPG production 42,616 tonnes

Annual purified jumbo flake production 3,007 tonnes

Annual by-product fines production 18,384 tonnes

Finished product purity ≥99.95%

CAPEX C$ 923 M

Annual OPEX C$ 136 M

OPEX cost per tonne of CSPG throughput 1 C$ 2,249/tonne

Bécancour average basket price C$ 8,172/tonne

1. Excludes costs for the Matawinie Mine graphite concentrate feedstock

The Bécancour Battery Material Plant will be organized by process sectors, with dedicated

facilities for shaping, purification, and coating, plus support services. This modular facility is

designed with a capacity to expand as demand increases in battery and specialty markets.

Environmental Design & Carbon Neutrality Commitment