Nevada KING Announces More Than Doubling of M&i Resource at Atlanta to 1,019,600 GOLD Ounces Averaging 1.14 G/T
NEVADA KING ANNOUNCES MORE THAN DOUBLING OF M&I RESOURCE
AT ATLANTA TO 1,019,600 GOLD OUNCES AVERAGING 1.14 G/T
VANCOUVER, BC
,
June 4, 2025
/CNW/ -
Nevada King Gold Corp.
(TSXV: NKG) (OTCQB: NKGFF) ("
Nevada King
" or the "
Company
") is pleased to report an
updated Mineral Resource Estimate ("
MRE
") for its 12,000 hectare (120km
2
), 100% owned Atlanta Gold Mine Project, located in the prolific Battle Mountain
Trend, 264km northeast of
Las Vegas
, Nevada. The MRE was prepared by RESPEC (formerly Mine Development Associates) based out of
Reno, Nevada
, a
group with unmatched experience working with Nevada-based deposits.
Atlanta Resource Highlights:
Measured and Indicated ("M&I") resources:
27.7 million tonnes (Mt) at an average gold grade of 1.14g/t for 1,019,600 ounces of contained gold,
representing a more than doubling (122% increase) of M&I resources compared to the 2020 resource estimate, highlighting the success of the Company's
Phase I & II resource definition drilling campaigns. 91% of the total gold ounces are categorized within the higher confidence M&I categories, with just 9% in
the inferred category (see Table 1).
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
M&I
27,710,300
1.14
1,019,600
9.75
8,687,400
1.20
1,069,700
Inferred
3,638,400
0.84
98,500
2.56
299,500
0.85
99,800
Table 1. Pit-constrained MRE summary for Atlanta
High-grade core
: M&I resources include a high-grade core of
524koz Au averaging 3.99g/t Au
at a 2 g/t AuEq cut-off grade ("
COG
"). This high-grade core
alone
contains
more ounces than the
2020 M
&I resource estimate and at more than triple (207% increase) the average grade.
M&I Material in All Processing in All Lithologies
COG AuEq g/t
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
0.5
15,939,900
1.77
905,700
15.16
7,768,900
1.86
952,000
0.7
12,896,500
2.06
852,500
16.91
7,012,200
2.16
894,700
1
9,968,800
2.42
776,800
19.59
6,278,800
2.54
815,000
2
4,085,900
3.99
524,100
31.93
4,194,900
4.19
550,100
4
1,577,000
6.24
316,500
41.57
2,107,700
6.50
329,500
Table 2. M&I resource sensitivities based on cut-off
Open-pit, oxide gold system:
This pit-constrained, oxide resource applies a
US$2,200
/oz gold price and assumes recoveries and processing methods from
the Company's Phase 1 metallurgical test work program, which outlines conventional Nevada oxide processing methods at
Atlanta
(link
here
).
Significant growth potential:
Today's resource covers the Atlanta Resource zone and does not incorporate mineralization encountered in the Company's
Phase III drilling, including the recent discovery of gold and silver mineralization at Silver Park. Management sees clear potential for continued resource
expansion with mineralization open to the north, south and west of the resource zone, as well as the potential for finding regional satellite deposits.
Collin Kettell
, CEO of
Nevada King
, stated: "This updated MRE was prepared by RESPEC, a highly regarded engineering firm that represents the gold standard
for Nevada projects. The results mark a major milestone at
Atlanta
, confirming a high-grade and high-confidence oxide gold system in one of the most sought-after
jurisdictions in the world. We are pleased to exceed the 1Moz Au threshold in the M&I category while maintaining the grade of oxide mineralization well above 1
g/t. Today's results highlight the success of our Phase I and II drill programs and validate our technical team's geological model and drilling since 2021. With this
MRE under our belt, we will continue our quest to unlock the full potential of the
Atlanta
district. Our fully funded, aggressive Phase III exploration drill program is
aimed at demonstrating
Atlanta's
multi-million-ounce potential."
Cal Herron
, Exploration Manager of
Nevada King
, remarked: "
Atlanta
is a unique system with multiple instances of high-grade gold deposition. These high-grade
zones, which play prominently into today's resource estimate, were a key target of our Phase II drill program.
"When we began our work at
Atlanta
, the resource totaled
460,000 M
&I ounces averaging 1.30 g/t. Today's resource update more than doubles that figure and
includes significantly more high-grade material, which is largely the result of thicker, higher-grade intercepts within the West Atlanta Graben Zone. We see clear
potential for expansion of this zone to the south, north and west with the possibility of finding additional elevated high-grade zones.
"The Company's unwavering support behind its technical team coupled with its commitment to seeing the exploration program completed made it possible to boost
a modest deposit into a high-grade, +1 Moz deposit – a rare achievement for open pit oxide deposits in safe jurisdictions. That same tenacity is still at play today,
pushing our Phase III exploration forward throughout the
Atlanta
District in search of new deposits."
2025 Mineral Resource Estimate
Open pit oxide resources to be processed at a mill are estimated at 14.5Mt grading 1.72g/t Au for 803koz of contained gold in the M&I category, while 1.0Mt
grading 2.24g/t for 70koz of contained gold are in the Inferred category.
Open pit oxide resources to be processed via a heap leach are estimated at 13.2Mt grading 0.51g/t Au for 216koz of contained gold in the M&I category,
while 2.7Mt grading 0.34g/t for 29koz of contained gold are in the Inferred category.
Material
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
Measured Heap Leach
1,246,000
0.60
24,200
3.16
126,500
0.61
24,500
Measured Mill
80,700
4.43
11,500
15.56
40,400
4.55
11,800
Measured Mill Breccia
2,103,400
2.00
135,100
25.19
1,703,300
2.15
145,700
Measured
3,430,100
1.55
170,800
16.96
1,870,200
1.65
182,000
Indicated Heap Leach
11,921,000
0.50
192,100
3.05
1,167,800
0.51
195,200
Indicated Mill
397,000
4.66
59,500
11.66
148,800
4.75
60,700
Indicated Mill Breccia
11,962,200
1.55
597,200
14.30
5,500,600
1.64
631,800
Indicated
24,280,200
1.09
848,800
8.73
6,817,200
1.14
887,700
M&I
27,710,300
1.14
1,019,600
9.75
8,687,400
1.20
1,069,700
Inferred Heap Leach
167,600
0.49
2,600
0.02
100
0.49
2,600
Inferred Mill
1,000
3.19
100
2.87
100
3.21
100
Inferred Mill Breccia
965,700
2.24
69,600
2.86
88,800
2.25
69,900
Inferred Heap Leach (Dump/Pad)
2,504,100
0.33
26,200
2.61
210,500
0.34
27,200
Inferred
3,638,400
0.84
98,500
2.56
299,500
0.85
99,800
Table 3. Mineral resource estimate by lithology and processing method
1
.
The Mineral Resources have been prepared by Jeff Bickel, C.P.G of RESPEC (formerly Mine Development Associates) in conformity with CIM "Estimation of
Mineral Resource and Mineral Reserves Best Practices" guidelines and are reported in accordance with the Canadian Securities Administrators National
Instrument 43-101 ("
NI 43-101
"). Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that
all Mineral Resources will be converted into Mineral Reserves.
2
.
The project mineral resources are estimated using a variable gold equivalent (AuEq) cut-off grade. Gold Equivalent (AuEq) equation: AuEq = (
US$2,200
/oz
Au /
US$25
/oz Ag) * (Gold Recovery / Silver Recovery). Gold and Silver Recoveries were variable based on grade and material type (See table below for
recovery equations).
3
.
Heap leach material cut-off grade of 0.14 g/t AuEq, heap leach dump/pad material cut-off grade of 0.14 g/t AuEq, mill material cross over-grade of 2.34 g/t
AuEq, and mill breccia material cut-off grade of 0.33 g/t AuEq within an optimized pit.
4
.
Mineral Resources within the optimized pit with a slope angle of 45 degrees.
5
.
Additional inputs for Whittle pit-optimization include: mining costs of
US$2.17
/tonne mined; remining costs of
US$1.63
/tonne mined for dump/pad material;
heap leach costs of
US$3.28
/tonne processed, milling costs of
US$13.53
/tonne processed, and general and administrative costs of
US$0.96
/tonne
processed.
6
.
The reported MRE have been constrained within optimized pit shells using a gold price of
US$2,200
/oz Au and a silver price of
US$23.91
/oz Ag. These metal
prices, as well as the metal recoveries summarized below, were used to calculate cut-off grades and contained ounces.
7
.
The MRE is based on
93,461.5m
in 468 drill holes, with
76,933.8m
in 407 holes drilled by
Nevada King
from 2020-2024 and the remainder by previous
operators between 1997-2015.
8
.
A technical report on the MRE will be prepared in accordance with NI 43-101 and will be filed within 45 days of this news release on
Nevada King's
issuer
profile on SEDAR+ at
www.sedarplus.ca
.
9
.
This MRE has an effective date of
September 6, 2024
.
10
.
Rounding may result in apparent discrepancies between tonnes, grade, and contained metal content.
11
.
Gold and Silver recovery equations summarized by material type in table below:
Heap Leach Au
IF(au_c.G>0.40,3.981*LOG(au_c.G)+72.851,7.165*LOG(au_c.G)+75.224)/100
Mill Au
IF(au_c.G>0.40,1.678*LOG(au_c.G)+86.519,4.068*LOG(au_c.G)+88.504)/100
Mill Breccia Au
IF(au_c.G>0.40,3.074*LOG(au_c.G)+82.642,6.594*LOG(au_c.G)+85.399)/100
Heap Leach Ag
IF(ag_c.G>8.00,(0.846*LOG(ag_c.G)+12.932)/100,(1.229*LOG(ag_c.G)+12.183)/100)
Mill Ag
IF(ag_c.G>8.00,(7.012*LOG(ag_c.G)+33.209)/100,(13.043*LOG(ag_c.G)+20.046)/100)
Mill Breccia Ag
IF(ag_c.G>8.00,(1.266*LOG(ag_c.G)+40.846)/100,(1.957*LOG(ag_c.G)+39.479)/100)
2025
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
M&I
27,710,300
1.14
1,019,600
9.75
8,687,400
1.20
1,069,700
Inferred
3,638,400
0.84
98,500
2.56
299,500
0.85
99,800
2020
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
M&I
11,040,000
1.30
460,000
11.89
4,220,000
1.43
505,864
Inferred
5,310,000
0.83
142,000
7.30
1,240,000
0.91
155,477
% change
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
M&I
151 %
-12 %
122 %
-18 %
106 %
-16 %
111 %
Inferred
-31 %
1 %
-31 %
-65 %
-76 %
-6 %
-36 %
Table 4. Mineral resource estimate changes from 2020 to 2025
MRE Methods
The effective date of the MRE is
September 6
, 2024. RESPEC (formerly Mine Development Associates) worked with
Nevada King
to create three-dimensional
geological models based on original cross-sections supplied by
Nevada King
which were the basis for the interpretation of mineralization of the deposit leading to
the MRE. Gold and silver mineral resources were modeled and estimated as follows:
Define mineral domains based on the
Atlanta
geological model and geostatistical analysis of drillhole data.
Create polygons of explicitly modeled cross-sectional interpretations of constrained low-, medium- and high-grade mineral-domains for both gold and silver
snapped to drillholes. The grade domains were guided by the geological model and integrated other relevant geological information.
Rectified the cross-sections on evenly spaced long-section polygons which has plane locations coinciding with the resource block model centroids along y-
axis columns.
Coded a block model to the gold and silver domains using the mineral-domain long-section polygons.
Composited drill hole assay sample data within the mineralized domains into
1.5 m
length composites.
Analyzed the modelled mineralization geostatistically to aid in the establishment of estimation and classification parameters, and
Interpolated grades into block models using the gold and silver mineral domains to explicitly constrain the grade estimations. RESPEC utilized Inverse
Distance Squared (ID2) interpolation for the estimation to obtain a localizing effect in the mid- and high-grade domains to best represent the spatial
distribution of mineralization in the deposit. All estimates are based on a block dimension of
1.5 m
by
1.5 m
by
1.5 m
.
Resource sensitivity at various cut-offs
The following table considers average cut-off within the optimized pit for the purposes of demonstrating overall sensitivities.
M&I Material in All Processing in All Lithology
COG AuEq g/t
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
0.5
15,939,900
1.77
905,700
15.16
7,768,900
1.86
952,000
0.7
12,896,500
2.06
852,500
16.91
7,012,200
2.16
894,700
1
9,968,800
2.42
776,800
19.59
6,278,800
2.54
815,000
2
4,085,900
3.99
524,100
31.93
4,194,900
4.19
550,100
4
1,577,000
6.24
316,500
41.57
2,107,700
6.50
329,500
Inferred Material in All Processing in All Lithology
COG AuEq g/t
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
0.5
1,264,500
1.94
78,800
5.42
220,200
1.97
80,100
0.7
1,085,300
2.16
75,500
5.73
199,800
2.20
76,700
1
921,500
2.40
71,100
5.84
173,000
2.44
72,300
2
408,300
3.50
45,900
10.20
133,900
3.58
46,900
4
139,100
5.30
23,700
13.44
60,100
5.40
24,200
Table 4. Mineral resource estimate sensitivities based on cut-off.
1. This table is only included to demonstrate the sensitivity of changes in cut-off grade and the values should be considered a subset of existing mineral resources.
2. Rounding as required by reporting guidelines may result in apparent discrepancies between tonnes, grade, and contained metal content.
Next Steps
Exploration continues with the Company's ongoing Phase III drill program, which was recently expanded to
30,000m
from
20,000m
and is fully funded. The Phase
III program is focused on regional drilling and with gold and silver mineralization identified at Silver Park, Atlanta South, and Atlanta North exploration targets,
these areas will continue to be the focus of the exploration program with potential to further increase the drill program through the rest of the year. In addition to
continued exploration, the company will also continue to de-risk the project through further metallurgical test work, geotechnical work, environmental studies, and
permit planning.
QA/QC Protocols
All Reverse Circulation (RC) samples from the Atlanta Project are split at the drill site and placed in cloth and plastic bags utilizing a nominal 2kg sample weight.
CRF standards, blanks, and duplicates are inserted into the sample stream on-site on a one-in-twenty sample basis, meaning all three inserts are included in each
20-sample group. Samples are shipped by a local contractor in large sample shipping crates directly to American Assay Lab in
Reno, Nevada
, with full custody
being maintained at all times. At American Assay Lab, samples were weighted then crushed to 75% passing 2mm and pulverized to 85% passing 75 microns to
produce a 300g pulverized split. Prepared samples are initially run using a four acid + boric acid digestion process and conventional multi-element ICP-OES
analysis. Gold assays are initially run using 30-gram samples by lead fire assay with an OES finish to a 0.003 ppm detection limit, with samples greater than 10
ppm finished gravimetrically. Every sample is also run through a cyanide leach for gold with an ICP-OES finish. The QA/QC procedure involves regular submission
of Certified Analytical Standards and property-specific duplicates.
The PQ-diameter core was sampled in the Company's warehouse in Winnemucca, Nevada, with whole core samples being placed in heavy canvas bags and sent
to American Assay Lab in Reno, Nevada, in heavy shipping bags by a Company contractor with full custody being always maintained. CRF standards and coarse
blanks were inserted into the sample stream on a one-in-twenty sample basis, meaning both inserts are included in each 20-sample group. At American Assay
Lab, samples were weighted, and then completely crushed to -1 inch. The coarse-crushed sample was quarter-split, and one quarter was reduced to 75%
passing 2mm. A 300g split was subsequently pulverized to 85% passing 75 microns. Prepared samples are initially run using a four acid + boric acid digestion
process and conventional multi-element ICP-OES analysis. Gold assays are initially run using 30-gram samples by lead fire assay with an OES finish to a 0.003
ppm detection limit, with samples greater than 10 ppm finished gravimetrically. Every sample is also run through a cyanide leach for gold with an ICP-OES finish.
The QA/QC procedure involves regular submission of Certified Analytical Standards and property-specific duplicates.
Qualified Person
The MRE for
Atlanta
was prepared under the supervision of
Jeffrey Bickel
, CPG, an employee of RESPEC. Mr. Bickel has reviewed and approved the technical
contents relating to the MRE in this news release.
Mr. Bickel has reviewed the sampling, assaying, and security procedures used at the Atlanta Project and it is his opinion that they follow industry standard
procedures and are adequate for the estimation of the MRE and for use in preparing the Technical Report.
Mr. Bickel completed audits of the databases provided by
Nevada King
, performed a site visit, and reviewed quality assurance and quality control data and
procedures. After performing his review, he considers the assay data to be adequate for the estimation of the MRE and for use in preparing the Technical Report.
The scientific and technical information in this news release has been reviewed and approved by
Calvin R. Herron
, P.Geo., who is a Qualified Person as defined
by NI 43-101, and he supervises all of the Company's exploration activities.
About Nevada King Gold Corp.
Nevada King
is focused on advancing and growing its 100% owned, past producing, 120km
2
Atlanta Gold Mine project located along the
Battle Mountain
trend in
southeast Nevada. The project hosts an NI 43-101 compliant pit-constrained oxide resource of 1,020koz Au in the measured and indicated category (
27.7M
tonnes at 1.14 g/t) plus an inferred resource of 98.5koz Au (
3.6M
tonnes at 0.84 g/t and replaces the Gustavson 2020 resource summarized below (see the NI
43-101 Technical Report on Resources titled "Atlanta Property,
Lincoln County, NV
" with an effective date of
October 6, 2020
, and a report date of
December 22,
2020
, as prepared by Gustavson Associates and filed under the Company's profile on SEDAR+
www.sedarplus.ca
).
Previous NI 43-101 Mineral Resources at the Atlanta Mine by Gustavson 2020
Resource
Category
Tonnes
(000's)
Au Grade
(ppm)
Contained Au
Oz
Ag Grade
(ppm)
Contained Ag
Oz
Measured
4,130
1.51
200,000
14.0
1,860,000
Indicated
6,910
1.17
260,000
10.6
2,360,000
M&I
11,000
1.30
460,000
11.9
4,220,000
Inferred
5,310
0.83
142,000
7.3
1,240,000
NI 43-101 Mineral Resources at the Atlanta Mine by RESPEC 2025
Tonnes
Au g/t
Au oz
Ag g/t
Ag oz
AuEq g/t
AuEq oz
Measured
3,430,100
1.55
170,800
16.96
1,870,200
1.65
182,000
Indicated
24,280,200
1.09
848,800
8.73
6,817,200
1.14
887,700
M&I
27,710,300
1.14
1,019,600
9.75
8,687,400
1.20
1,069,700
Inferred
3,638,400
0.84
98,500
2.56
299,500
0.85
99,800
Please see the Company's website at
www.nevadaking.ca
.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts
responsibility for the adequacy or accuracy of this release.
Cautionary Statements Regarding Forward Looking Information
This news release contains certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the
meaning of applicable securities legislation. All statements, other than statements of historical fact, included herein, without limitation, statements relating to the
future operations and activities of
Nevada King
, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words
such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible", and similar expressions, or statements that events, conditions, or
results "will", "may", "could", or "should" occur or be achieved. Forward-looking statements in this news release relate to, among other things, further
exploration activities at
Atlanta
, including the potential for continued resource expansion and locating regional satellite deposits, and derisking the Atlanta
Project
through further metallurgical test work, geotechnical work, environmental studies, and permit planning.
There can be no assurance that such statements
will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements
reflect beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while
considered reasonable by
Nevada King
, are inherently subject to significant business, economic, competitive, political and social uncertainties and
contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results,
performance or achievements that are or may be expressed or implied by such forward-looking statements and the parties have made assumptions and
estimates based on or related to many of these factors. Such factors include, without limitation, the ability to complete proposed exploration work, the results of
exploration, continued availability of capital, and changes in general economic, market and business conditions. Readers should not place undue reliance on
the forward-looking statements and information contained in this news release concerning these items. Readers are urged to refer to the Company's filings on
SEDAR+ at
www.sedarplus.com
for a more complete discussion of such risk factors and their potential effects.
Nevada King
does not assume any obligation to
update forward-looking statements should beliefs, opinions, projections, or other factors, change, except as required by applicable securities laws.
View original content to download multimedia:
https://www.prnewswire.com/news-releases/nevada-king-announces-more-than-doubling-of-mi-resource-at-atlanta-to-1-019-600-gold-ounces-averaging-1-14-gt-302472747.html
SOURCE
Nevada King Gold Corp.
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/June2025/04/c1710.html
%SEDAR: 00015775E
For further information:
For more information, contact Collin Kettell at [email protected] or (845) 535-1486.
CO: Nevada King Gold Corp.
CNW 06:30e 04-JUN-25