Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NICU.V ·

Magna Mining Completes Updated Preliminary Economic Assessment of the Crean Hill Project Study Demonstrates 13 Year Mine Life, Modest Pre-Production Capital and Short Payback Period

Economic Studies

Magna Mining Completes Updated Preliminary

Economic Assessment of the Crean Hill

Project

Study Demonstrates 13 Year Mine Life, Modest Pre-Production

Capital and Short Payback Period

Sudbury, Ontario--(Newsfile Corp. - September 17, 2024) - Magna Mining Inc. (TSXV: NICU) (OTCQB:

MGMNF) (FSE: 8YD) ("Magna" or the "Company") is pleased to announce the successful completion of

its Updated Preliminary Economic Assessment ("PEA") by SGS Geological Services (SGS) on its

100% owned Crean Hill Project (the "Project") located in Sudbury, Ontario, Canada.

The PEA envisions an underground only mining operation, with Life of Mine ("LOM") potentially mineable

resource being sold to a third-party existing mill in Sudbury. Underground mining would be initiated with

a 15-month Advanced Exploration ("AdEx") program followed by a 12-month pre-production ramp-up

period and 13 years of commercial production.

Initial mining will be done with ramp access via a new

surface portal with the eventual rehabilitation and re-establishment of the historic #2 shaft for personnel

access and hoisting as mining progresses deeper.

Note: All dollar values are reported in Canadian Dollars unless otherwise stated.

2024 PEA Highlights

Low pre-production capital cost of $27.7M following AdEx period;

Payback of pre-production period capital within the first year of commercial production,

and payback of all capital including AdEx period capital within the second year of

commercial production;

Underground average production rate of 2,200 tonnes per day ("tpd") consisting of 1,650

tpd of higher-margin primary feed and 550 tpd of lower grade, incremental feed;

Pre-tax NPV (8%) of $265.3 million and an Internal Rate of Return ("IRR") of 142% at

conservative metal prices.

Magna Mining COO Jeff Huffman commented: "This updated Preliminary Economic Assessment

focuses efforts on a high margin, underground-only mine plan.

A low capital approach of establishing a

new surface portal will provide quick access to the resource, allowing us to offset capital costs with early

revenues. This PEA also benefits from increased certainty on third party processing terms. The project

timeline has been derisked by having environmental permits approved and in-hand, as well as more

detailed stope planning and sequence optimization.

The PEA metal pricing assumptions have been

updated to reflect a more conservative long term nickel price. We are excited and encouraged by the

results of this PEA and look forward to continuing to advance the Crean Hill Project".

The primary feed is designed to ensure rapid payback and minimize upfront capital requirements while

simultaneously mitigating the potential impact of low metal prices.

The lower cut-off grade of incremental

material allows more complete extraction of the resource and the two-pronged nature of the mining

sequence facilitates lower-cost extraction of the incremental material.

Financial Analysis

The Crean Hill PEA uses metal prices of US$ 8.50/lb nickel, US$ 4.00/lb copper, US$ 13.00/lb cobalt,

US$ 900/oz platinum, US$ 1000/oz Palladium, US$ 2,150/oz gold, and a 1.35 C$/US$ exchange rate

as outlined in Table 2.

The Base Case generates a pre-tax NPV (8%) of $265.3 million and an Internal Rate of Return ("IRR") of

142%, after-tax NPV (8%) is $194.1 million, with an IRR of 129%.

See Table 1 for a summary of PEA results.

Table 1: PEA Summary

Units

Total

Total Resource Mined

tonnes

10,688,606

Mine Life

years

13

Average Production Rate

tpd

2,193

Operating Cost

$/tonne

158

Advanced Exploration Bulk Sample*

$M

32.1

Pre-Production Capital

$M

27.7

Sustaining Capital

$M

212.8

Ni in Resource Sold

M lbs

195.5

Cu in Resource Sold

M lbs

169.5

Co in Resource Sold

M lbs

6.8

Pt in Resource Sold

koz

313

Pd in Resource Sold

koz

359

Au in Resource Sold

koz

117

Average NSR

$/tonne

240

Average Annual Pre-Tax Cash Flow

$M

40.5

Payback Period (overall)

years

1.5

Pre-Tax NPV (8%)

$M

265.3

Pre-Tax IRR

%

142

Post Tax NPV (8%)

$M

194.1

Post Tax IRR

%

129

Note: AdEx Bulk Sample revenue is not included in PEA economics.

Table 2: Metal Prices and Exchange Rates

Item

Units

Base Case Pricing

Nickel

$US/lb

8.50

Copper

$US/lb

4.00

Cobalt

$US/lb

13.00

Platinum

$US/oz

900

Palladium

$US/oz

1000

Gold

$US/oz

2150

Exchange Rate

CAD:USD

1.35

USD:CAD

0.74

Capital and Operating Costs

The Study was prepared in accordance with National Instrument 43-101 of the Canadian Securities

Administrators (NI 43-101). The capital and operating cost estimates for the Advance Exploration, Pre-

Production and Production phases of the Project are summarized below in Tables 3-5. Capital costs are

based on planned development of a ramp from surface to the bottom of the orebody and the rehab of #2

shaft to the mid-shaft loading pocket. The company is planning on commencing an AdEx bulk sample

underground to confirm resource grade, continuity and dilution impacts in an effort to de-risk the project.

It is envisioned that positive results from this program will lead to a pre-feasibility study and continued

development of the Crean Hill Project.

Table 3: AdEx and Pre-Production Cost and Revenue Summary

Item

Units

AdEx

Pre-Production

Capital Cost

$M

48.5

27.7

Operating Cost

$M

-

62.9

Revenue

$M

16.4

78.3

Total Cost Net Revenue

$M

32.1

12.3

Table 4: Capital Costs by Period - Detail

Item

Units

Pre-Production

(Initial Capital)

Production

(Sustaining Capital)

Total Capital Cost

Development

$M

12.8

143.5

156.3

Infrastructure

$M

14.5

58.7

73.1

G&A and Indirects

$M

0.4

4.8

5.2

Closure

$M

-

5.8

5.8

Total Capital Cost

$M

27.7

212.8

240.5

Table 5: Operating Costs by Period - Detail

Item

Units

Pre-Production

Production

Average Operating Cost Per

Resource Tonne Mined ($/t)

Mining

$M

40.3

894.7

$87.47

Crushing, Haulage and Processing

$M

17.3

635.7

$61.09

G&A

$M

5.3

92.9

$9.19

Total Operating Costs

$M

62.9

1623.3

$157.75

Figure 1: Life of Mine Pre-Tax Cash Flow

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/8002/223536_ff141bcd34c969fb_001full.jpg

Mining and Infrastructure

Previous mining activity at the Crean Hill site makes this project particularly favorable for revitalization.

The site is located near the Trans-Canada Highway, approximately 35km from Sudbury with access to a

well-established supply and service sector focused on the mining industry. The PEA is based on

underground mining only. A new ramp will allow rapid access to initial, near-surface, mining areas and

dewatering will be carried out from the historic #2 shaft.

As mining proceeds beyond 700m depth,

rehabilitation of the existing shaft and key infrastructure will be completed.

This capital expenditure will

allow hoisting and personnel access via the #2 shaft and will enable ramp-access mining to continue at

depth.

Operating costs assumptions are based on use of a mining contractor during the advanced

exploration phase, and owner operated equipment during the pre-production and operation phase for all

mine development and production.

Underground production mining will be completed utilizing conventional longhole stoping methodology

with hydraulic backfill. Power lines capable of supporting mining activities are in close proximity to the

project and heating requirements will be met using propane.

On-site crushing and sampling activities will

occur before the ore is shipped to the local processing facility. Water treatment will be managed through

a service agreement with the existing third-party treatment facility.

Figure 2 illustrates the historical mining and PEA mine plan. Figure 3 illustrates the LOM production

profile and Table 6 summarizes the mine production statistics.

Figure 2: Crean Hill Mine Longitudinal Section Showing Historic Mining, Planned Development

and Future Stoping

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/8002/223536_ff141bcd34c969fb_002full.jpg

Table 6: PEA Production Statistics

Item

Units

Primary

Incremental

Base Case

Resource Mined

tonnes

7,996,761

2,691,845

10,688,606

Average NSR

$/tonne

258

148

240

NiEq Cut-off Grade

%

1.20

0.90

-

Ni Grade

%

0.92

0.56

0.83

Cu Grade

%

0.79

0.50

0.72

Co Grade

%

0.03

0.02

0.03

Pt Grade

g/t

1.01

0.63

0.91

Pd Grade

g/t

1.16

0.70

1.04

Au Grade

g/t

0.38

0.21

0.34

Figure 3: Life of Mine Production Profile

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/8002/223536_ff141bcd34c969fb_003full.jpg

Permitting

The Crean Hill project is a brownfield site with an existing footprint and a Closure Plan that has been filed

by Vale. Vale retains surface rights to the property and holds key permits including an Air Environmental

Compliance Approval (ECA) for air emissions and a Sewage ECA for the wastewater management

system. Additional surface infrastructure for new operations will be authorized by an amended Closure

Plan. Other permits that would be required for mine development are an amended Air ECA, amended

Sewage ECA, amended Permit to Take Water for mine dewatering and an additional sewage ECA for

a domestic sewage system. There are no requirements for a federal or provincial environmental

assessment. Permits for the commencement of AdEx at Crean Hill have been received.

Mineral Resources

The PEA potentially mineable resources are a subset of the current Crean Hill Mineral Resource

Inventory (Table 7). Appropriate mining dilution and recoveries were applied to the design stopes

depending on mining method used. Allan Armitage, Ph.D., P. Geo. of SGS Geological Services is an

independent Qualified Person as defined by NI 43-101 and is responsible for the current Crean Hill

MRE.

Table 7: Crean Hill Project Underground Mineral Resource Estimate, April 15, 2024

Classification

Cut-off

Grade

Tonnes

Cu (%)

Ni (%)

Co (%)

Pt (g/t)

Pd (g/t)

Au (g/t)

NiEq %

Indicated

1.1% NiEq

18,444,000

0.87

1.01

0.035

0.98

1.12

0.37

1.96

Inferred

1.1% NiEq

989,000

0.53

0.70

0.026

0.98

1.66

0.29

1.56

Please see notes on Mineral Resource assumptions, at the end of this release, including metal prices and recoveries used. The underground cut-off

grade of 1.10% NiEq considers metal prices of $8.50/lb Ni, $3.75/lb Cu, $17.00/lb Co, $950/oz Pt, $1100/oz Pd and $1,950/oz Au, metal recoveries of

78% for Ni, 95.5% for Cu, 56% for Co, 69.2% for Pt, 68% for Pd and 67.7% for Au, a mining cost of US$80.00/t rock and processing, treatment and

refining, transportation and G&A cost of US$42.50/t mineralized material.

Crean Hill Project Economic Sensitivities

The Crean Hill Project is most sensitive to metal market prices and least sensitive to project capital cost.

Operating costs and exchange rate sensitivities fall between metal prices and capital costs and display

similar sensitivities.

Table 8: Crean Hill Project Sensitivities - Pre-Tax NPV(8%) ($M)

Variance

Metal Price

Exchange Rate

Capex

Opex

-20%

-42

595

294

445

-10%

113

411

280

355

Base

265

265

265

265

10%

423

149

251

175

20%

578

50

236

85

Figure 4: Crean Hill Project Sensitivities - Pre-Tax NPV(8%)

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/8002/223536_ff141bcd34c969fb_004full.jpg

Table 9: Crean Hill Project Sensitivities - Metal Price Comparison

Units

3 Yr Trailing

Average

2023 PEA

Base Case

Spot Price July

20, 2024

Nickel

$US/lb

9.96

9.50

8.50

7.30

Copper

$US/lb

4.06

3.50

4.00

4.20

Cobalt

$US/lb

19.89

22.00

13.00

12.45

Platinum

$US/oz

971

1000

900

965

Palladium

$US/oz

1622

1800

1000

923

Gold

$US/oz

1915

1700

2150

2401

Pre-Tax NPV (8%)

$M

491.6

481.7

259.3

181.6

Pre-Tax IRR

%

200

185

90

58

Post-Tax NPV (8%)

$M

348

341.2

189.2

135.1

Post-Tax IRR (%)

%

182

168

82

53

Qualified Person

The following Qualified Persons (QPs) oversaw the completion of the work in preparation of the PEA

and are responsible for the contents:

Independent QP for Geology and Mineral Resource Estimates

Mr. Allan Armitage, Ph.D., P.Geo., of SGS Geological Services.

Mr. Armitage conducted personal inspection of the site on May 25-26, 2022, July 25, 2023, July 02,

2024 and July 25, 2024.

Independent QP for Underground Mining and Financial Analysis

Mr. Henri Gouin, P.Eng., of SGS Geological Services.

Mr. Gouin last conducted a personal inspection of the site on May 13, 2024.

Independent QP for Underground Mining, Financial Analysis, Permitting and Environmental

Mr. William van Breugel, P.Eng., B.A.Sc. Geological Engineering, P.Eng., Associate Engineer of SGS

Geological Services.

Independent QP for Processing and Recovery

Mr. Dominic Fragomeni, P.Eng., Frago-Met Solution Ltd.

Technical information in this press release has been reviewed and approved by David King, M.Sc.,

P.Geo. Mr. King is the Senior Vice President, Exploration and Geoscience for Magna Mining Inc. and is

a qualified person under Canadian National Instrument 43-101.

Crean Hill Property Mineral Resource Estimate Notes:

1

.

The effective date of the Crean Hill Property Mineral Resource Estimate (MRE) is April 15,

2024. This is the close out date for the final mineral resource models and mine out models (as-

builts).

2

.

Allan Armitage, Ph.D., P. Geo. of SGS Geological Services is an independent Qualified Person

as defined by NI 43-101 and is responsible for the current Crean Hill MRE. Armitage conducted

multiple site visits to the Crean Hill Property including on May 25-26, 2022, July 25, 2023, July

02, 2024 and July 25, 2024.

3

.

The classification of the current MRE into Indicated and Inferred mineral resources is consistent

with current 2014 CIM Definition Standards - For Mineral Resources and Mineral Reserves.

4

.

All figures are rounded to reflect the relative accuracy of the estimate and numbers may not add

due to rounding.

5

.

The mineral resource is presented undiluted and in situ, constrained by 3D grade control

resource models, and are considered to have reasonable prospects for eventual economic

extraction. The mineral resource is exclusive of mined out material.

6

.

Mineral resources which are not mineral reserves do not have demonstrated economic viability.

An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated

Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected

that most Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with

continued exploration.

7

.

The Crean Hill mineral resource estimate is based on a validated drill hole database which

includes data from 4,646 surface and underground diamond drill holes completed between

1951 and March 2024. The drilling totals 739,448 m. The resource database totals 103,952

assay intervals representing 290,253 m of data.

8

.

The mineral resource estimate is based on a three-dimensional ("3D") resource model of the

main mineralization and a broader dilution envelope. 3D models of mined out areas were used

to exclude mined out material from the current MRE.

9

.

Grades for Ni, Cu, Co, Pt, Pd, Ag and Au are estimated for each mineralization domain using

~2.0 m capped composites assigned to that domain. To generate grade within the blocks, the

inverse distance squared (ID2) interpolation method was used for all domains.

10

.

Specific gravity values were assigned to each block based on a regression formula defined by a

database of 32,592 samples. SG=(0.2057xNi%+2.88).

11

.

Based on the size, shape, and orientation of the Crean Hill Deposit, it is envisioned that the

deposits may be mined using both bulk and selective mining methods including Longhole

Stoping.

12

.

The MRE is reported at a base case cut-off grade of 1.10% NiEq. The mineral resource grade

blocks are quantified above the base case cut-off grade and within the constraining mineralized

wireframes (considered mineable shapes).

13

.

The underground cut-off grade of 1.10% NiEq considers metal prices of $8.50/lb Ni, $3.75/lb Cu,

$17.00/lb Co, $950/oz Pt, $1100/oz Pd and $1,950/oz Au, metal recoveries of 78% for Ni, 95.5%

for Cu, 56% for Co, 69.2% for Pt, 68% for Pd and 67.7% for Au (Ag is not considered), a mining

cost of US$80.00/t rock and processing, treatment and refining, transportation and G&A cost of

US$42.50/t mineralized material.

14

.

The estimate of Mineral Resources may be materially affected by environmental, permitting,

legal, title, taxation, socio-political, marketing, or other relevant issues.

About Magna Mining Inc.

Magna Mining is an exploration and development company focused on nickel, copper and PGM projects

in the Sudbury region of Ontario, Canada. The Company's flagship assets are the past producing

Shakespeare and Crean Hill Mines. The Shakespeare Mine is a feasibility stage project which has

major permits for the construction of a 4,500 tonne per day open pit mine, processing plant and tailings

storage facility and is surrounded by a contiguous 180km

2

prospective land package. Crean Hill is a

past producing nickel, copper and PGM mine with a technical report dated August 2022. Additional

information about the Company is available on SEDAR (

www.sedar.com

) and on the Company's

website (

www.magnamining.com

).

For further information, please contact:

Jason Jessup

Chief Executive Officer

Or

Paul Fowler, CFA

Senior Vice President

416-356-8165

Email:

[email protected]

Cautionary Statement

This press release contains certain forward-looking information or forward-looking statements as

defined in applicable securities laws. Forward-looking statements are not historical facts and are

subject to several risks and uncertainties beyond the Company's control, including statements

regarding the production at the Shakespeare and Crean Hill Mines, the economic and operational