Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NICU.V ·

Magna Mining Completes Preliminary Economic Assessment ON the Crean Hill Project Study Demonstrates Base Case 15 Year MINE Life and Significant Potential Synergies with the Shakespeare Project

Economic Studies

MAGNA MINING COMPLETES PRELIMINARY ECONOMIC ASSESSMENT ON THE

CREAN HILL PROJECT

STUDY DEMONSTRATES BASE CASE 15 YEAR MINE LIFE AND SIGNIFICANT POTENTIAL

SYNERGIES WITH THE SHAKESPEARE PROJECT

SUDBURY, ONTARIO, CANADA, JULY 31, 2023 – Magna Mining Inc. (TSX.V: NICU) (OTCQB: MGMNF) (FSE:

8YD) (“Magna” or the “Company”) is pleased to announce the successful completion of its Preliminary

Economic Assessment ("PEA") by Stantec on its 100% owned Crean Hill Nickel Project (the "Project")

located in Sudbury, Ontario, Canada.

The Base Case scenario (“Base Case”) for the PEA envisions a combination of open pit and underground

mining, with Life of Mine (“LOM”) potential mineable resource being sold to a third-party existing mill in

Sudbury. Initial underground mining would be accessed from a new ramp developed from surface, prior

to rehabilitation of the existing shaft to access and hoist from the lower elevations. Resources are mined,

crushed, and sampled onsite, then trucked to the third -party mill for processing. An alternative milling

scenario was studied comparing the economics of the Base Case with an Alternative Processing scenario

(“Alternative Processing”) through a future mill at the Company’s Shakespeare Project.

Magna Mining CEO Jason Jessup commented: “This Preliminary Economic Assessment demonstrates why

we think the Crean Hill Nickel Project has the potential to be the next nickel producing mine in Canada.

The results of the Base Case study show positive economics, a long mine life, modest upfront capital cost,

and minimal permitting required before commencing advanced exploration development. The Crean Hill

Project contains a large potentially mineable resource, and the current PEA sch edule has not yet been

fully optimized. The next technical study will look at further optimization of cut -off grade, stope design

and scheduling to maximize revenues during the first years of mine life . It will incorporate not only the

diamond drilling tha t Magna has completed on Crean Hill since the acquisition in 2022 but also the

economics of a fully integrated mining complex with Magna’s Shakespeare Project. The results of the

Alternative Processing scenario considered in the PEA demonstrate potential r obust economics, which

makes a compelling case to proceed with this work. This is consistent with Magna’s vision of developing

a hub and spoke production model in the world class Sudbury nickel mining camp. “

Financial Analysis

Both the Base Case and Alternative Processing use metal prices of US$ 9.50/lb nickel, US$ 3.50/lb copper,

US$ 22.00/lb cobalt, US$ 1000/oz platinum, US$ 1800/oz Palladium, US$ 1700/oz gold, and a 1.3 C$/US$

exchange rate (Table 2).

The Base Case generates a pre - tax NPV (8%) of $290.4 million and an Internal Rate of Return (“IRR”) of

23.9%, after-tax NPV (8%) is $230.4 million, with an IRR of 23.4%.

The Alternative Processing generates a pre- tax NPV (8%) of $668.8 million and an IRR of 39.6%, after-tax

NPV (8%) is $516.1 million, with an IRR of 38.4%.

See Table 1 for a summary of PEA results (all results are reported in Canadian Dollars unless otherwise

noted).

Table 1: PEA Summary

Table 2: Metal Prices and Exchange Rate

Base Case Alternative

Processing

Total Resource Mined (Tonnes) 20,102,605 28,197,495

UG Resource Mined (Tonnes) 16,274,220 21,791,858

OP Resource Mined (Tonnes) 3,828,385 6,405,636

OP Waste Mined (Tonnes) 29,349,432 37,406,582

Strip Ratio 7.7 5.8

Mine Life (Years) 15 19

Ni in Resource Sold (Million lbs) 276.6 351.2

Cu in Resource Sold (Million lbs) 243.5 309.0

Co in Resource Sold (Million lbs) 9.8 12.5

Pt in Resource Sold (Thousands oz) 367.5 464.8

Pd in Resource Sold (Thousands oz) 401.6 496.8

Au in Resource Sold (Thousands oz) 220.2 273.8

Average NSR (C$/Tonne) $179.07 $165.20

Operating Cost (C$/Tonne) $116.57 $88.33

Pre-Tax NPV (8%) (C$ Million) $290.4 $668.8

Pre-Tax IRR 23.9% 39.6%

Post Tax NPV (8%) (C$ million) $230.4 $516.1

Post Tax IRR 23.4% 38.4%

Advanced Exploration Capital (C$ million) $48.4 $47.9

Initial Project Capital (C$ million) $81.1 $81.3

Sustaining Capital (C$ million) $248.9 $256.7

$ US / lb or Oz

Nickel $9.50

Copper $3.50

Cobalt $22.00

Platinum $1,000.00

Palladium $1,800.00

Gold $1,700.00

Exchange C$/US$ 1.3

Capital and Operating Costs

The Study was prepared in accordance with National Instrument 43 -101 (NI 43 -101 of the Canadian

Securities Administrators). The Base Case capital and operating cost estimates for the Advance

Exploration, Project Development and Operation phases of the Project are summarized below in Tables

3-8. Capital cost s assume development of a ramp from surface to access initial mining areas and

dewatering and rehabilitation of the existing main shaft and selected infrastructure as mining progresses

to lower levels.

Operating costs assume contractor surface mining and project period underground development, with

owner operated underground development and production during the operating period.

Table 3: Base Case Advanced Exploration Costs

Table 4: Base Case Costs UG and Open Pit (after Advanced Exploration)

Item Cost (millions)

ADEX Direct Capital Costs $20.18

ADEX Indirect Costs $4.04

ADEX Contingency $8.47

ADEX Capitalized Operating Costs $15.68

ADEX Total Capital Costs $48.36

Item UG Cost

(millions)

OP Cost

(millions)

Combined Cost

(millions)

Project Period Direct Capital Costs $34.63 $15.42 $50.06

Project Period Indirect Costs $6.93 $3.08 $10.01

Project Period Contingency $14.55 $6.48 $21.02

Sustaining Capital Costs $247.16 $1.70 $248.86

Total Capital Costs $303.27 $26.69 $329.96

Operating Costs during Project Period $13.33 $21.57 $34.90

Opex during Operating Period $1,921.02 $371.70 $2,292.73

Total Operating Costs $1,934.35 $393.27 $2,327.62

Closure Costs $5.85 $11.24 $17.09

Royalties $90.42 $14.42 $104.84

Pre Tax NPV8% (includes ADEX) $251.99 $38.44 $290.43

Pre Tax IRR (includes ADEX) 22.43% 37.82% 23.91%

Taxes $146.86 $16.69 $163.29

Post Tax NPV8% (includes ADEX) $203.02 $26.12 $230.44

Post Tax IRR (includes ADEX) 22.39% 29.62% 23.37%

Table 5: Base Case Capital Costs UG – Detail

Table 6: Base Case Capital Costs Open Pit – Detail

Table 7: Base Case Operating Costs UG – Detail

Table 8: Base Case Operating Costs OP – Detail

Item Project Period

(millions)

Sustaining

(millions)

Total

(millions)

Development $20.48 $131.71 $152.19

Infrastructure $14.15 $115.46 $129.61

Closure $0.00 $5.85 $5.85

Subtotal $34.63 $253.01 $287.64

Indirects $6.93 $0.00 $6.93

Contingency $14.55 $0.00 $14.55

Total UG Capital Cost $56.11 $253.01 $309.12

Item Project Period

(millions)

Sustaining

(millions)

Total

(millions)

Site Preparation $1.28 $1.70 $2.98

Existing Waste Rock Pile $14.15 $0.00 $14.15

Closure $0.00 $11.24 $11.24

Subtotal $15.42 $12.94 $28.37

Indirects $3.08 $0.00 $3.08

Contingency $6.48 $0.00 $6.48

Total UG Capital Cost $24.99 $12.94 $37.93

Item ADEX

(millions)

Project Period

(millions)

Operating Period

(millions)

Total Operating

(millions)

Cost per Tonne of

Mineralized Resource

Mined

Mining $0.63 $3.59 $651.05 $655.27 $40.26

Indirects and G & A $13.06 $6.30 $470.28 $489.64 $30.09

Diamond Drilling $1.06 $1.00 $15.88 $17.94 $1.10

Surface Handling and Processing Related $0.93 $2.44 $783.81 $787.17 $48.37

Total Operating Costs $15.68 $13.33 $1,921.02 $1,950.03 $119.82

Item ADEX

(millions)

Project Period

(millions)

Operating Period

(millions)

Total Operating

(millions)

Cost per Tonne of

Mineralized Resource

Mined

Mining - Pit Waste $0.00 $15.90 $168.18 $184.08 $48.08

Mining - Pit Mineralized Resource $0.00 $0.65 $23.36 $24.01 $6.27

Processing Related $0.00 $5.02 $180.16 $185.18 $48.37

Total Operating Costs $0.00 $21.57 $371.70 $393.27 $102.73

Mining and Infrastructure

Previous mining activity at the Crean Hill site makes this project particularly favorable for

revitalization. The site is located near the Trans-Canada Highway, approximately 35km from Sudbury

with access to a well-established supply and service sector focused on the mining industry. The PEA

envisions both surface open pit and underground mining. The open pit surface mining has been

constrained to not interfere with the existing main shaft to the south and water control dam north of

the mineralized zones. Initially underground mining areas will be accessed from a newly developed ramp

from surface, and dewatering and rehabilitation of the existing main shaft and selected infrastructure

will be completed as mining progresses to lower levels. Surface mining will consist of conventional truck

and shovel mining, and underground mining will utilize a combination of conventional longhole and cut

and fill stoping. Power lines capable of supporting mining activities are in close proximity to the project,

and heating requirements are to be fueled by propane. Mined resource crushing and sampling activities

will occur on site prior to shipment to the processing facility. Water treatment is managed onsite

utilizing the existing third-party treatment facility.

Figure 1 illustrates the existing development and historical mining, the base case open pit, underground

development and stopes. Figure 2 illustrates the LOM production profile and Table 9 summarizes the

Base Case production statistics.

Figure 1: Crean Hill Mine Longitudinal Section Showing Existing Workings, Planned Development and

Stoping, Looking North.

Table 9: Base Case Production Statistics Including Potentially Minable Resources

The Potentially Mineable Resource is based on NSR cut-off of $43.28/Tonne for open pit mining, $123.50/Tonne for underground

longhole stoping, and $134.50/Tonne for underground mechanized cut and fill.

Item UG Open Pit Combined

Tonnes Mined 16,274,220 3,828,385 20,102,605

Average NSR $/tonne $190.36 $131.05 $179.07

Ni (%) 0.65 0.53 0.62

Cu (%) 0.58 0.41 0.55

Co (%) 0.02 0.02 0.02

Pt (grams per tonne) 0.62 0.36 0.57

Pd (grams per tonne) 0.71 0.22 0.62

Au (grams per tonne) 0.38 0.17 0.34

Figure 2: Life of Mine Production Profile

Permitting

The Crean Hill project is a brownfield site with existing disturbance and a Closure Plan that has been filed

by Vale. Vale retains surface rights to the property and responsibility for the permitting of surface

activities. All surface infrastructure for new operations will be captured in an amended closure plan. Other

permits that may be required for new future operations would include a new or amended Environmental

Compliance Approval (ECA) for air and noise related to cru shing and transportation, and for drilling and

blasting in a future open pit scenario. An additional ECA will be required for domestic sewage along with

a regional health authority authorization. As currently designed in the PEA, there are no requirements for

a federal or provincial environmental assessment(s) on site. The PEA assumes that all relevant permits for

the commencement of advanced exploration at Crean Hill will be received in Q4, 2023.

Mineral Resources

The PEA potentially mineable resources (Table 9) are a subset of the current Crean Hill Mineral Resource

Inventory (Table 10). Appropriate mining dilution and recoveries were applied to the design stopes

depending on mining method used. Current Mineral Resources at Crean Hill were est imated by SGS

Geological Services. Mineral Resources include near surface mineralization with potential for open pit

mining, as well as higher grade mineralization amenable to conventional underground mining methods.

The full technical report, titled “Mineral Resource Estimate for the Denison Ni-Cu-PGE Sulphide Deposit,

Denison Project, Sudbury, Ontario, Canada” with an effective date of August 19th, 2022 and a report date

of December 14th, 2022, was prepared in accordance with NI 43-101 – Standards of Disclosure for Mineral

Projects and is available on SEDAR (www.sedar.com) under the Company’s issuer profile.

Table 10: Denison Mineral Resources as of August 19, 2022 (Denison is now referred to as th e “Crean

Hill Project”). Please see notes on Mineral Resource assumptions, at the end of this release, including

metal prices and recoveries used.

(A) Open Pit Resources

(B) Underground Resources

Crean Hill Project Economic Sensitivities

The Crean Hill Project is most sensitive to metal price and metal grade, and least sensitive to project capital

cost. Project sensitivities are illustrated in Table 11 and Figure 3.

Table 11: Crean Hill Project Sensitivities – Post-Tax NPV (millions)

Cut-off

Grade Tonnes Ni % Cu % Co % Pt g/t Pd g/t Au g/t NiEq %

0.3% NiEq 16,760,000 0.53 0.49 0.02 0.48 0.37 0.25 1.08

0.3% NiEq 434,000 0.43 0.49 0.02 0.29 0.14 0.07 0.82

Indicated

Inferred

Cut-off

Grade Tonnes Ni % Cu % Co % Pt g/t Pd g/t Au g/t NiEq %

1.1% NiEq 14,531,000 0.96 0.84 0.03 0.88 1.02 0.54 2.07

1.1% NiEq 1,170,000 0.61 0.46 0.02 0.64 1.09 0.21 1.41

Indicated

Inferred

Variance Metal Price Metal Grade Capex Opex

-20% -$85.4 -$94.6 $272.7 $431.4

-10% $78.9 $73.7 $251.6 $331.6

Base $230.4 $230.4 $230.4 $230.4

10% $363.0 $376.6 $209.3 $127.6

20% $492.7 $519.3 $188.2 $22.9