Drill Results

NGEx Minerals Ltd.

2800 – 1055 Dunsmuir Street

Vancouver BC, Canada V7X 1L2

T +1 604 689 7842

F +1 604 689 4250

[email protected]

NGEXminerals.com

NGEx Drills 22.85m at 4.01% Cu and 11.30 g/t Au (14.26% CuEq) within 126.6m

at 2.16% Cu and 3.30 g/t Au (5.09% CuEq)

December 17, 2025, Vancouver, British Columbia – NGEx Minerals Ltd. (“NGEx”, “NGEx Minerals” or the

“Company”) (TSX: NGEX; OTCQX: NGXXF) is pleased to announce drill results from DPDH048 which is the

first hole of the Phase 4 program at its 100% owned Lunahuasi high-grade copper-gold-silver project in

San Juan, Argentina. This hole successfully extends the Saturn Zone one hundred metres vertically below

DPDH046.

Highlights:

• Drillhole DPDH048 intersected 649.00m at 1.64% CuEq, including;

▪ 126.55m at 5.09% CuEq from 497.15m, including;

• 22.85m at 14.26% CuEq from 497.15m, including;

o 9.10m at 26.99 g/t Au from 508.90m, plus;

• 49.20m at 5.71% CuEq from 574.50m, including;

o 2.15m at 46.22 g/t Au from 583.00m.

Wojtek Wodzicki, President and CEO, commented, “Hole 48 is an excellent start to the Phase 4 program

and picks up where we left off at the conclusion of the Phase 3 program by continuing to define high-grade

copper-gold-silver zones as we successfully expand the deposit. Intersecting the Saturn Zone about 100m

below last season’s hole 46, this new hole confirms our expectations of the size and continuity of the Saturn

Zone including its important high-grade gold and silver component. To date we have drilled over 10,000m

during Phase 4 with ten holes completed an d eight underway and we look forward to providing regular

updates on assay results as we start the new year.”

Phase 4 Progress

Following an early start and good drilling productivity, the Phase 4 program is well ahead of schedule. To

date, over 10,000m have been drilled with ten holes completed and eight underway. Initial holes have

focused on defining and expanding the three named zones and drills will begin to do larger step-outs and

test new exploration targets early in the new year.

To date, two hol es have been drilled into the Jupiter Zone, three into Mars and twelve into Saturn. In

addition to the exploration holes, a geotechnical hole is currently being drilled down the centerline of the

proposed exploration adit as planning for that project progresses.

Additional assay results will be released once assays are received, analyzed, and confirmed by the

Company.

Table 1: Significant Intersections

Hole ID From (m) To (m) Length

(m)

Estimated

True Width

(m)

Cu % Au g/t Ag g/t CuEq %

DPDH048 112.00 761.00 649.00 649 0.73 1.00 20.1 1.64

incl 117.00 134.00 17.00 11 0.97 2.28 41.3 3.00

incl 132.00 134.00 2.00 1.4 1.31 12.35 78.5 11.01

and incl 167.40 179.00 11.60 8.1 0.26 1.37 19.4 1.42

and incl 231.00 238.70 7.70 5.0 1.65 2.13 27.1 3.44

and incl 285.00 302.50 17.50 12 0.36 1.12 30.2 1.45

and incl 424.80 426.50 1.70 1.2 3.86 2.08 35.0 5.69

and incl 470.00 477.00 7.00 4.9 1.47 1.90 16.7 3.00

and incl 497.15 623.70 126.55 89 2.16 3.30 59.2 5.09

incl 497.15 520.00 22.85 16 4.01 11.30 228.0 14.26

incl 497.15 501.30 4.15 2.9 6.91 1.81 40.4 8.59

and incl 508.90 518.00 9.10 6.4 6.31 26.99 547.5 30.81

and incl 574.50 623.70 49.20 34 3.23 2.95 38.1 5.71

incl 583.00 585.15 2.15 1.5 4.11 46.22 262.0 40.12

and incl 608.00 616.20 8.20 5.7 8.87 3.28 115.9 12.28

and incl 655.00 660.35 5.35 3.7 2.92 2.19 50.7 4.96

and incl 707.00 710.90 3.90 3.0 5.10 0.93 22.3 5.97

and incl 737.00 738.70 1.70 1.2 4.09 0.93 18.5 4.93

and incl 755.30 759.00 3.70 2.6 5.04 0.68 17.8 5.69

Copper equivalent (CuEq) for drill intersections is calculated based on US$3.00/lb Cu, US$1,500/oz Au and US$18/oz Ag, with

80% metallurgical recoveries assumed for all metals. The formula is: CuEq % = Cu % + (0.7292 * Au g/t) + (0.0088 * Ag g/t). A *

indicates that no CuEq was calculated as samples within the interval and/or the entire interval returned >100% CuEq.

Estimated true widths are rounded to the nearest metre for widths over 10m and to the nearest 0.1m for widths less than 10m,

as this better reflects the precision of the estimates. True widths should be regarded as approximate as these are derived from an

estimation that uses a preliminary interpretation of the geological model and are subject to change as more information becomes

available.

DPDH048 was collared on the same platform as DPDH046 and drilled at 277o with a dip of -55o to intersect

the Saturn Zone down dip from that hole. It intersected the zone between 497.15m and 623.70m, with

two strong zones from 497.15m to 520.00m and 574.50m and 623.70m separated by lower grade

mineralization. Each of these two sub-zones contains an interval of high-grade gold mineralization which

appears to correlate well with the two distinct zones drilled in DPDH046 which are 77m and 90m away

measured along the apparent dip of the structures.

Qualified Persons and Technical Notes

The scientific and technical disclosure included in this news release have been reviewed and approved by

Bob Carmichael, B.A.Sc., P.Eng. who is the Qualified Person as def ined by NI 43 -101. Mr. Carmichael is

Vice President, Exploration for the Company.

Samples were cut at NGEx’s operations base in San Juan, Argentina by Company personnel. Diamond drill

core was sawed and then sampled in maximum 2-meter intervals, stopping at geological boundaries. Core

diameter is a mix of PQ, HQ and NQ depending on the depth of the drill hole. Samples were bagged ,

tagged, and packaged for shipment by truck to the ALS preparation laboratory in Mendoza, Argentina

where they were crushed and a 500g split was pulverized to 85% passing 200 mesh. The prepared sample

splits were sent to the ALS assay laboratory in Lima, Peru for copper, gold and silver assays, and multi -

element ICP. ALS is an accredited laboratory which is independent of the Compa ny. Gold assays were by

fire assay fusion with AAS finish on a 30g sample (Au-AA23). Any samples returning > 10 g/t were then

reanalyzed by fire assay with gravimetric finish on a 30g sample (Au -GRA21). Copper and silver were

assayed by atomic absorption following a 4-acid digestion. Samples were also analyzed for a suite of 48

elements with ME -MS61 plus mercury and a sequential copper leach analysis was completed on each

sample with copper greater than 500ppm (0.05%) . Sequential copper analysis involves t he sequential

leaching of the sample by acid, followed by a cyanide solution. It can be used to differentiate copper

speciation, with copper oxide minerals leachable with acid and secondary copper minerals (enargite,

chalcocite, covellite) leachable by cyanide. The residual copper remaining following the sequential leaches

it typically contained in chalcopyrite and bornite. Copper and gold standards as well as blanks and

duplicates (field, preparation , and analysis) were randomly inserted into the sampling sequence for

Quality Control. On average, 10% of the submitted samples are Quality Control samples. No data quality

problems were indicated by the QA/QC program.

About NGEx Minerals

NGEx Minerals is a copper and gold exploration company based in Canada, focused on exploration of the

Lunahuasi copper-gold-silver project in San Juan Province, Argentina, and the nearby Los Helados copper-

gold project located approximately nine kilometres to the northeast in Chile’s Region III. Both projects are

located within the Vicuña District, which includes the Caserones mine, and the Josemaria and Filo del Sol

deposits.

NGEx owns 100% of Lunahuasi and is the majority partner and operator for the Los Helados project,

subject to a Joint Exploration Agreement with Nippon Caserones Resources LLC, which is the indirect 30%

owner of the operating Caserones open pit copper mine located approximately 17 kilometres north of Los

Helados. Lundin Mining Corporation holds the remaining 70% stake in Caserones.

The Company’s common shares are listed on the TSX under the symbol "NGEX" and also trade on the

OTCQX under the symbol “NGXXF”. NGEx is part of the Lundin Group of Companies.

Additional information relating to NGEx may be obtained or viewed on SEDAR+ at www.sedarplus.ca.

For further information, please contact:

Finlay Heppenstall

VP, Corporate Development & Investor Relations

Tel: +1 (604) 806-3089

[email protected]

Additional Information

Neither the TSX nor its Regulation Services Provider (as that term is defined in the policies of the TSX )

accepts responsibility for the adequacy or accuracy of this news release.

The information contained in this news release was accurate at the time of dissemination but may be

superseded by subsequent news release(s). The Company is under no obligation, nor does it intend to

update or revise the forward-looking information, whether as a result of new information, future events

or otherwise, except as may be required by applicable securities laws.

Cautionary Note Regarding Forward-Looking Statements

Certain statements made and information contained herein in the news release constitutes “forward -looking

information” and “forward-looking statements” within the meaning of applicable securities legislation (collectively,

“forward-looking information”). All statements other than statements of historical facts included in this document

constitute forward -looking information in cluding, but not limited to, statements regarding: the geological

interpretation of the Lunahuasi system including apparent correlations between drill holes; the nature and timing of

the work to be undertaken to advance the Lunahuasi project, including the timing of larger step-outs and testing of

new exploration targets ; the timing of drill results; and the Company’s ability to use information gathered from

drilling to date to effectively target and drill in future campaigns. Generally, this forward-looking information can

frequently, but not always, be identified by use of forward -looking terminology such as "plans", "expects" or "does

not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", “projects”, “budgets ”,

“assumes”, “strategy”, “objectives”, “potential”, “possible”, "anticipates" or "does not anticipate", or "believes", or

variations of such words and phrases or statements that certain actions, events, conditions or results “will”, "may",

"could", "would", “should”, "might" or "will be taken", "will occur" or "will be achieved" or the negative connotations

thereof.

Forward-looking information is necessarily based upon various estimates and assumptions including, without

limitation, the expectations and beliefs of management with respect to the nature, scope and timing of the work to

be undertaken to advance the Lunahuasi Project. Although the Company believes that these factors and expectations

are reasonable as at the date of this document , in light of management’s experience and perception of current

conditions and expected developments, these statements are inherently subject to significant business, economic and

competitive uncertainties and contingencies. Known and unknown risks, uncertainties and ot her factors may cause

actual results or events to differ materially from those anticipated in such forward -looking statements and undue

reliance should not be placed on such statements and information. Such factors include, without limitation: the

emergence or intensification of infectious diseases, such as COVID 19, and the risk that such an occurrence globally,

or in the Company’s operating jurisdictions and/or at its project sites in particular, could impact the Company’s ability

to carry out the program and could cause the program to be shut down ; estimations of costs, and permitting time

lines; ability to obtain environmental permits, surface rights and property interests in a timely manner; currency

exchange rate fluctuations; requirements for addition al capital; changes in the Company’s share price; changes to

government regulation of mining activities; environmental risks; unanticipated reclamation or remediation expenses;

title disputes or claims; limitations on insurance coverage, fluctuations in th e current price of and demand for

commodities, particularly gold prices, as they are fluctuating currently due to market volatility ; material adverse

changes in general business, government and economic conditions in the Company’s operating jurisdictions,

particularly Argentina; the availability of financing if and when needed on reasonable terms; risks related to material

labour disputes, accidents, or failure of plant or equipment; there may be other factors that cause results not to be

as anticipated, estimated, or intended, including those set out in the Company’s annual information form and annual

management discussion and analysis for the year ended December 31, 2024, which are available on the Company’s

website and SEDAR+ at www.sedarplus.ca under the Company’s profile.

The forward-looking information contained in this news release is based on information available to the Company as

at the date of this news release. Except as required under applicable securities legislation, the Company doe s not

undertake any obligation to publicly update and/or revise any of the forward-looking information included, whether

as a result of additional information, future events and/or otherwise. Forward -looking information is provided for

the purpose of provi ding information about management's current expectations and plans and allowing investors

and others to get a better understanding of the Company's operating environment. Although the Company has

attempted to identify important factors that would cause actual results to differ materially from those contained in

forward-looking information, there may be other factors that cause results not to be as anticipated, estimated, or

intended. There can be no assurance that such statements will prove to be accurate, as actual results and future

events could differ materially from those anticipated in such statements. All the forward -looking information

contained in this document is qualified by these cautionary statements. Readers are cautioned not to place undue

reliance on forward-looking information due to the inherent uncertainty thereof.

Cautionary Note to U.S. Readers

Information concerning the mineral properties of the Company contained in this news release has been prepared in

accordance with the requirements of Canadian securities laws, which differ in material respects from the

requirements of securities laws of the United States applicable to U.S. companies subject to the reporting and

disclosure requirements of the United States Securities and Exchange Commission.

DECEMBER 2025

Lunahuasi Project

Plan View

0 800m

Overburden

Alluvial

Colluvial

Lithology

Silicified structural zone

Volcaniclasc sequence (rhyolite tuff, breccia)

Volcaniclasc sequence (andesite, sandstone, conglomerate)

Quartz diorite porphyry

Access track

Length m @ CuEq %

Cu % / Au gpt / Ag gpt

NORTH

Phase 1, 2, 3 Holes

Phase 4 Holes

DPDH048

126.5m @ 5.09

2.16/3.30/59.2

437600E

6856000N

2.0 - 4.0 %

4.0 - 10.0 %

> 10.0 %

CuEq %

1.0 - 2.0 %

Jupiter Mars

Saturn