NOVAGOLD Files Year-End 2024 Report with Strong Treasury to Fund Key Activities for Long-Term Value Creation
NYSE AMERICAN, TSX: NG
NEWS RELEASE
NOVAGOLD Files Year-End 2024 Report with Strong Treasury
to Fund Key Activities for Long-Term Value Creation
January 23, 2025 – Vancouver, British Columbia – NOVAGOLD RESOURCES INC. (“NOVAGOLD” or “the
Company”) (NYSE American, TSX: NG) today filed its 2024 fiscal year-end report and provided an update on
its Tier One1 gold development project, Donlin Gold, which NOVAGOLD owns equally with Barrick Gold
Corporation (“Barrick”).
Details of the financial results for the year ended November 30, 2024, are presented in the consolidated
financial statements and annual report on Form 10-K filed on January 23, 2025 which is available on the
Company’s website at www.novagold.com, on SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov.
All amounts are in U.S. dollars unless otherwise stated.
As detailed in the above filings, NOVAGOLD held a strong treasury of approximately $101 million in cash
and term deposits as of November 30, 2024, and reported net annual cash expenditures of $24.5 million —
including $12.4 million to fund NOVAGOLD’s share of the Donlin Gold project and $17.7 million in corporate
general and administrative costs, below its 2024 expenditure guidance of $31.2 million. As NOVAGOLD is a
development-stage company with no production, the Company reported earnings of ($45.6) million and
earnings per share of ($0.14) for the 2024 fiscal year, reflecting expenditures in line with budget.
In 2024, the following milestones were achieved at NOVAGOLD and Donlin Gold:
▶ Donlin Gold undertook the following key activities in 2024 to advance technical work to position the
project for an updated cost estimate:
Substantially completed metallurgical test work at a pilot plant in Ontario, Canada to
confirm proposed optimizations to the flowsheet; advanced an updated resource model;
and collected field and geochemical data for operational and closure planning;
Submitted the preliminary design packages for the Dam Safety Certification to the Alaska
Department of Natural Resources (ADNR) in the second half of 2024;
Collaborated with Donlin Gold, Calista Corporation (“Calista”), and The Kuskokwim
Corporation (TKC) on substantial ecological, educational and cultural awareness initiatives,
including community outreach in the project’s region — hosted public open houses in
three locations, participated in two Subsistence Community Advisory Committee meetings ,
and established three additional Shared Values Statements with local villages.
▶ NOVAGOLD and Barrick held a Donlin Gold workshop in Alaska in September 2024 to review the
important work completed to date and to agree on the next steps for the Donlin Gold project and
related 2025 activities.
▶ Donlin Gold board approved a budget of $43 million (100% basis) for 2025, comprising the
following key areas:
Camp operations with grid drilling to refine mine planning assumptions;
Updated mine planning;
Geotechnical engineering and geosciences closure planning;
1 NOVAGOLD defines a Tier One gold development project as one with a projected production life of at least 10 years, annual projected production of at least 500,000 ounces of
gold, and average projected cash costs over the production life that are in the lower half of the industry cost curve.
Page 2 of 6
Project planning;
Advancement of Dam Safety Certificate applications; and
Community relations, government affairs, and maintaining permits in good standing.
President’s Message
This last year was characterized by extensive efforts to increase Donlin Gold’s visibility and advance
activities for long-term sustainable value creation — strengthening the project’s position as a unique
opportunity to gain direct exposure to gold through one of the largest undeveloped gold assets globally2,
located in a stable, tier one, mining-friendly jurisdiction, Alaska3. With this strong foundation, we are
nearing critical milestones that we believe will allow us to unlock NOVAGOLD’s full potential.
Key activities in 2024 included the substantial completion of metallurgical test work at a pilot plant in
Ontario, Canada to confirm proposed optimizations to the flowsheet; field and geochemical data
collection to continue updating source characteristics for groundwater and surface water models for both
operational and closure planning; as well as advancement of the Donlin Gold resource model. Results
derived from the considerable technical work performed over these past twelve months will serve as
inputs into updated feasibility work.
Partnering for Broader Reach into the Project’s Region and Meaningful Impact
We recognize the importance of ecological stewardship in the Yukon-Kuskokwim (Y-K) region. Since mid-
2023, Donlin Gold has intensified efforts to monitor, survey, and engage on the crucial subject of salmon
fisheries in the Kuskokwim and Yukon River watersheds. In 2024, Donlin Gold launched a salmon smolt
monitoring program on the George River, a tributary of the Kuskokwim River, in partnership with the
Native Village of Napaimute to assess smolt health and migration patterns — an initiative that will
continue into 2025. Restoration of a portion of the historic Lyman placer site, which included significant
stream and pond habitat creation, including aquatic life access and use, was completed in 2024. Aquatic
restoration work on a reach of Snow Gulch previously disturbed by historic mining will start in 2025 .
In 2024, Donlin Gold, Calista, and TKC held public open houses in Anchorage, Bethel, and Crooked Creek
— the closest community to the project. Two Subsistence Community Advisory Committee meetings were
conducted, the first in Aniak during the second quarter and the second in Anchorage in December. Donlin
Gold also established three additional Shared Values Statements, bringing the total to 18. Donlin Gold’s
numerous partnerships in the Y-K region and statewide, aimed at supporting ecological projects,
education, summer youth employment programs, and cultural awareness efforts, continue to grow.
Together these efforts underscore Donlin Gold’s ongoing engagement with and commitment to local
communities, reinforcing existing long-term relationships and addressing specific community needs.
In 2024, the Donlin Gold project received continued support from U.S. Senators Lisa Murkowski and Dan
Sullivan, and then U.S. Representative Mary Peltola, including their submittal of a joint amicus brief in
federal court referring to Donlin Gold as one of the State’s “most important and necessary economic
development projects” in “one of the most impoverished regions in Alaska.”
2 Per S&P Global Market Intelligence, Donlin Gold is ranked 4th in Measured and Indicated contained ounces among primary gold development projects.
3 Per the Mining Journal Intelligence – World Risk Report 2024, Alaska ranks 13th globally on the Investment Risk Index and received an AA rating, the highest rating category
awarded.
Page 3 of 6
Maintaining Permits in Good Standing
In 2024, Donlin Gold submitted the preliminary design packages for the Dam Safety Certification to
ADNR. Comments from ADNR on these presentations are anticipated in 2025, with potential issuance of
the certification in 2026/2027.
Donlin Gold applied for and received an 18-month extension of the construction deadline on its air quality
permit through July 2026. The Alaska Pollutant Discharge Elimination System permit, which was originally
set to expire in 2023, as well as the Waste Management Permit, which was set to expire in January 2024,
are administratively extended by the Alaska Department of Environmental Conservation until renewed.
The Reclamation Plan, which was also set to expire in 2024, is administratively extended until 2027.
In state litigation, we continued to support the agencies in defending Donlin Gold’s 401 Water Quality
Certification, water rights permits and State pipeline Right-of-Way (ROW). These cases have been fully
briefed and argued, and decisions are anticipated in 2025.
In federal litigation, the Court issued a decision last fall on Donlin Gold’s Joint Record of Decision, 404
permit, and ROW, upholding the federal agencies’ analysis on two of the three issues raised. The plaintiffs
filed a request for reconsideration on one of these issues, which the Court subsequently denied. Briefing
on the appropriate remedy to address the Court’s decision on the remaining item — namely, the
evaluation of a theoretical large release from the project’s tailing storage facility — is scheduled to be
completed in early February 2025.
Gold Exposure Through One of the Largest Gold Assets Globally 4
NOVAGOLD views the Donlin Gold project as an exceptionally rare investment opportunity — particularly
given the acute scarcity of high-quality assets located in secure, mining-friendly jurisdictions, coupled with
the recent surge in gold price, reaching an all-time high of $2,790 on October 30th, 2024. With over 39
million ounces of gold in Measured and Indicated Resources and a grade of 2.24 grams per tonne 5,
representing twice the industry average, Donlin Gold stands out as one of the largest gold assets globally,
and is expected to be operationally cost-effective6. The project’s current resource spans only 5% of its
land package, offering remarkable further exploration potential. Projected to produce over one million
ounces in average annual output7 Donlin Gold’s success is anchored in its location in Alaska, among the
safest mining jurisdictions in the world8 with strong community and state support.
2025 Activities and Next Steps
NOVAGOLD and Barrick held a workshop in Alaska in September 2024 to review the important work
completed to date, as well as to discuss the next steps for the project and related activities in 2025.
Subsequently, Donlin Gold’s board approved a path forward with a 2025 budget of $43 million on a 100%
basis. Camp operations will resume in the coming months to complete grid drilling toward refining mine
planning assumptions. Efforts will continue to advance key workstreams and preparation for a cost
4 Per S&P Global Market Intelligence, Donlin Gold is ranked 9th in Measured and Indicated contained ounces among primary gold deposits.
5 Donlin Gold data as per the report titled “NI 43-101 Technical Report on the Donlin Gold project, Alaska, USA” with an effective date of June 1, 2021 (the “2021 Technical
Report”) and the report titled “S-K 1300 Technical Report Summary on the Donlin Gold project, Alaska, USA” (the “S-K 1300 Technical Report Summary”), dated November 30,
2021. Donlin Gold possesses Measured Resources of approximately 8 Mt grading 2.52 g/t and Indicated Resources of approximately 534 Mt grading 2.24 g/t, each on a 100%
basis and inclusive of Mineral Reserves, of which approximately 4 Mt of Measured Resources and approximately 267 Mt of Indicated Resources inclusive of Reserves is
attributable to NOVAGOLD through its 50% ownership interest in Donlin Gold LLC. Exclusive of Mineral Reserves, Donlin Gold possesses Measured Resources of approximately 1
Mt grading 2.23 g/t and Indicated Resources of approximately 69 Mt grading 2.44 g/t, of which approximately 0.5 Mt of Measured Resources and approximately 35 Mt of
Indicated Resources exclusive of Mineral Reserves is attributable to NOVAGOLD. Donlin Gold possesses Proven Reserves of approximately 8 Mt grading 2.32 g/t and Probable
Reserves of approximately 497 Mt grading 2.08 g/t, each on a 100% basis, of which approximately 4 Mt of Proven Reserves and approximately 249 Mt of Probable Reserves is
attributable to NOVAGOLD. Mineral Reserves and Resources have been estimated in accordance with NI 43-101 and S-K 1300.
6 Donlin Gold data as per the 2021 Technical Report and the S-K 1300 Technical Report Summary detailed in footnote 5 above, with anticipated life of mine operating cash cost
of $635 per gold ounce. Peer data per S&P Global Market Intelligence, Donlin Gold ranks in the lower half of the industry cost curve.
7 Donlin Gold data as per the 2021 Technical Report and the S-K 1300 Technical Report Summary detailed in footnote 5 above, with anticipated average annual production of 1.1
million gold ounces over 27 years on a 100% basis.
8 Please see footnote 3 above.
Page 4 of 6
update. Additional work will include project and mine planning, further advancement of the Dam Safety
Certificate applications with work on the Detailed Design Packages, steadfast support of pending
litigation, and ongoing community relations and government affairs activities.
With a strong treasury of over $100 million, NOVAGOLD is well positioned to fund our share of activities
for at least the next two years at current spending levels. The path ahead for Donlin Gold is clear, guided
by the principles of patience, partnership, and an unrelenting focus on long-term value creation. We firmly
believe that with one of the industry’s most attractive development gold assets, NOVAGOLD is optimally
positioned to deliver exceptional returns.
We extend our heartfelt gratitude to our colleagues, partners, members of NOVAGOLD’s board of
directors, and shareholders for their unwavering support. As a new year begins, we remain deeply
committed to fulfilling each and every single one of the promises we have made and are excited to
achieve new milestones together. To our valued shareholders, we express our profound appreciation for
the trust they have placed in our vision, which drives us to continually strive for excellence and deliver
meaningful results. At NOVAGOLD, we are not just advancing a mining project. We are building a legacy
rooted in partnership, sustainability, and value creation — for all stakeholders.
Sincerely,
Gregory A. Lang
President and CEO
Liquidity and Capital Resources
At At
November
30, 2024
$
November
30, 2023
$
Cash and term deposits 101,224 125,749
Total assets 109,753 133,290
In 2024, cash and cash equivalents decreased by $3.5 million, mainly to fund our share of Donlin Gold,
corporate administrative expenses, partially offset by a net reduction of term deposits held.
Spending on operating activities in 2024 increased by $4.9 million compared to the prior year, primarily
due to increased corporate general and administrative expenses, lower interest income on cash and term
deposits, and higher income tax withholding related to passive income taxable in Canada on a portion of
interest income earned by U.S. subsidiaries. Cash provided from investing activities in 2024 increased by
$19.7 million compared to the prior year, primarily due to a net reduction of term deposits held in 2024
and lower Donlin Gold funding requirements.
2025 Outlook
Our anticipated expenditure in fiscal year 2025 will be approximately $37.5 million, including $21.5 million
to fund our share of the Donlin Gold project and $16.0 million for corporate general and administrative
costs.
NOVAGOLD’s main objectives include continuing to advance the Donlin Gold project towards a
construction decision; maintaining support for Donlin Gold among the project’s stakeholders; promoting
a strong safety, sustainability, and environmental culture; maintaining a favorable reputation of
NOVAGOLD; and preserving a healthy balance sheet. Our operations primarily relate to the delivery of
project milestones, including the achievement of various technical, environmental, sustainable
Page 5 of 6
development, economic and legal objectives, obtaining necessary permits, completion of feasibility
studies, preparation of engineering designs, and the financing to fund these objectives.
Conference Call & Webcast Details
NOVAGOLD’s conference call and webcast to discuss these results will take place today at 8:00 am PT
(11:00 am ET). The webcast and conference call-in details are provided below.
The video webcast and conference call-in details are provided below.
Video Webcast: www.novagold.com/investors/events/
North American callers: 1-844-763-8274
International callers: 1-647-484-8814
About NOVAGOLD
NOVAGOLD is a well-financed precious metals company, solely focused on the responsible and
sustainable development of its flagship Donlin Gold project in Alaska, one of the safest mining
jurisdictions in the world9. The Donlin Gold project, owned in equal partnership with Barrick, is positioned
to be one of the world’s largest gold mines, with approximately 39 million ounces of gold in the Measured
and Indicated Mineral Resource (541 million tonnes at an average grade of approximately 2.24 grams pe r
tonne, on a 100% basis) categories, inclusive of Proven and Probable Mineral Reserves. According to the
2021 Technical Report and the S-K 1300 Technical Report Summary10 Donlin Gold is expected to produce
an average of approximately one million ounces of gold over a 27-year mine life on a 100% basis. There’s
substantial exploration potential beyond the designed footprint of the Donlin Gold open pit, which
currently covers three kilometers of an approximately eight-kilometer-long gold-bearing trend. Current
activities at the Donlin Gold project focus on state permitting, engineering studies, community and
government engagement, and other environmental, educational and cultural initiatives in preparation for
the eventual construction and operation of this project. With a robust balance sheet, NOVAGOLD is well
positioned to finance its share of current activities.
NOVAGOLD Contacts:
Mélanie Hennessey
Vice President, Corporate Communications
604-669-6227 or 1-866-669-6227
Cautionary Note Regarding Forward-Looking Statements
This media release includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the
meaning of applicable securities legislation, including the United States Private Securities Litigatio n Reform Act of 1995. Forward-looking statements
include future-oriented financial information or financial outlook within the meaning of securities laws, including information regarding NOVAGOLD’s
anticipated expenditures. Such information is intended to assist readers in understanding NOVAGOLD’s current expectations and plans relat ing to the
future. Such information may not be appropriate for other purposes. Forward-looking statements are frequently, but not always, identified by words such as
“expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”, “possible ”, and similar expressions, or statements that events, conditions, or results
“will”, “may”, “could”, “would” or “should” occur or be achieved. Forward -looking statements are necessarily based on several opinions, estimates and
assumptions that management of NOVAGOLD considered appropriate and reasonable as of the date such statements are made, are subject to known and
unknown risks, uncertainties, assumptions, and other factors that may cause the actual results, activity, performance, or ach ievements to be materially
different from those expressed or implied by such forward -looking statements. All statements, other than statements of historical fact, included herein are
forward-looking statements. These forward-looking statements include statements regarding the anticipated timing of certain judicial and/or
administrative decisions; the 2025 outlook; the timing and potential for commencing a new feasibility study on the Donlin Gold project; the results of future
feasibility studies; our goals and expenditures for 2025; ongoing support provided to key stakeholders including Native Corporation partners; continuation
of Donlin Gold’s salmon smolt monitoring program; Donlin Gold’s continued support for the state and federal permitting process; sufficiency of working
capital; the potential development and construction of the Donlin Gold project; the timing and ability for the Donlin Gold project to hit critical milestones;
the ability for the Tier One gold development project to hit the anticipated projections; the sufficiency of funds to continue to advance development of
9 Please see footnote 3 above.
10 Donlin Gold data as per the 2021 Technical Report and the S-K 1300 Technical Report Summary. Please see footnote 5 above.
Page 6 of 6
Donlin Gold, including to a construction decision; perceived merit of properties; mineral reserve and mineral resource estima tes; Donlin Gold’s ability to
secure the permits needed to construct and operate the Donlin Gold project in a timely manner, if at all; legal challenges to Donlin Gold’s existing permits
and the timing of decisions in those challenges; whether the Donlin Gold LLC board will continue to advance the Donlin Gold p roject safely, socially
responsibly and to sustainably generate value for our stakeholders; continued cooperation between the owners of Donlin Gold LLC to advance the project;
the Company’s ability to deliver on its strategy with the Donlin Gold project, increasing shareholder and stakeholder wealth; the success of the strategic
mine plan for the Donlin Gold project; the success of the Donlin Gold community relations plan; the outcome of exploration dr illing at the Donlin Gold
project and the timing thereof; the completion of test work and modeling and the timing thereof. In addit ion, any statements that refer to expectations,
intentions, projections or other characterizations of future events or circumstances are forward -looking statements. Forward-looking statements are not
historical facts but instead represent the expectations of NOVAGOLD management’s estimates and projections regarding future events or circumstances on
the date the statements are made. Important factors that could cause actual results to differ materially from expectations in clude the need to obtain
additional permits and governmental approvals; the timing and likelihood of obtaining and maintaining permits necessary to construct and operate; the
need for additional financing to explore and develop properties and availability of financing in the debt and capital markets; disease pandemics;
uncertainties involved in the interpretation of drill results and geological tests and the estimation of reserves and resourc es; changes in mineral production
performance, exploitation and exploration successes; changes in nati onal and local government legislation, taxation, controls or regulations and/or
changes in the administration of laws, policies and practices, expropriation or nationalization of property and political or economic developments in the
United States or Canada; the need for continued cooperation between Barrick and NOVAGOLD for the continued exploration, development and eventual
construction of the Donlin Gold property; the need for additional capital if NOVAGOLD determined to proceed with an updated f easibility study on its own;
the need for cooperation of government agencies and Native groups in the development and operation of properties; risks of co nstruction and mining
projects such as accidents, equipment breakdowns, bad weather, disease pandemics, non -compliance with environmental and permit requirements,
unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases, which could includ e significant increases in
estimated capital and operating costs; fluctuations in metal prices and currency exchange rates; whether or when a positive construction decision will be
made regarding the Donlin Gold project; and other risks and uncertainties disclosed in NOVAGOLD’s most recent reports on Forms 10 -K and 10-Q,
particularly the “Risk Factors” sections of those reports and other documents filed by NOVAGOLD with applicable securit ies regulatory authorities from
time to time. Copies of these filings may be obtained by visiting NOVAGOLD’s website at www.novagold.com, or the SEC ’s website at www.sec.gov, or on
SEDAR+ at www.sedarplus.ca. The forward-looking statements contained herein reflect the beliefs, opinions and projections of NOVAGOLD on the date the
statements are made. NOVAGOLD assumes no obligation to update the forward -looking statements of beliefs, opinions, projections, or other factors,
should they change, except as required by law.