Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NG.TO ·

NOVAGOLD FILES FIRST QUARTER 2026 REPORT HIGHLIGHTING GROWING MOMENTUM ON KEY DONLIN GOLD WORKSTREAMS  Strengthened balance sheet: Completed upsized bought deal private placement for net proceeds of approximately $294 million

Financings

NEWS RELEASE

 www.novagold.com

Page | 1

NOVAGOLD FILES FIRST QUARTER 2026 REPORT HIGHLIGHTING

GROWING MOMENTUM ON KEY DONLIN GOLD WORKSTREAMS

 Strengthened balance sheet: Completed upsized bought deal private placement for net proceeds

of approximately $294 million

 Robust treasury: Ended quarter with ~$393 million in cash and term deposits

 Bankable Feasibility Study (BFS) launched: Appointed Fluor Corporation (“Fluor”) as lead

engineering firm; technical workstreams underway

 Strategic engineering contracts awarded: Retained WSP USA, Inc. (“WSP”), Worley Alaska, Inc.

(“Worley”), and Hatch Ltd. (“Hatch” and together with WSP and Worley, the “Specialist Contractors”)

for the on-site power plant, the natural gas pipeline, and the pressure oxidation circuit and oxygen

plant respectively — all advancing work toward completion of BFS expected in 2027 and supporting

progression of financing and development workstreams

 Energy infrastructure strategy under consideration: Donlin Gold signed a non-binding Letter of

Intent (LOI) with Glenfarne Alaska LNG, LLC (“Glenfarne”) to jointly evaluate natural gas supply from

the Alaska LNG pipeline and related infrastructure to power the proposed mine, potentially

enhancing cost efficiencies and project economics

April 1, 2026 – Vancouver, British Columbia – NOVAGOLD RESOURCES INC. (“NOVAGOLD” or the

“Company”) (NYSE American, TSX: NG) today filed its 2026 first quarter report and provided an update on

its Tier One1 gold development project, Donlin Gold, which is owned 60% by NOVAGOLD and 40% by

Donlin Gold Holdings, 100% wholly-owned by Paulson Advisers LLC (“Paulson”) and its affiliates.

Details of the financial results for the quarter ended February 28, 2026 are presented in the consolidated

financial statements and quarterly report on Form 10-Q filed on April 1, 2026, that is available on the

Company’s website at www.novagold.com, on SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov.

All amounts are in U.S. dollars unless otherwise stated.

As detailed in the above-mentioned filings, NOVAGOLD held approximately $392.5 million in cash and term

deposits as of February 28, 2026, and reported net first quarter operational cash expenditures of $20.8

million — reflecting $15.5 million to fund NOVAGOLD’s share of the Donlin Gold project and $5.3 million in

corporate general and administrative costs.

As NOVAGOLD is a development-stage company with no production, the Company reported earnings of

($15.4) million and earnings per share of ($0.04) for the first fiscal quarter of 2026. NOVAGOLD’s results for

the first quarter of 2026 reflect higher expenditures at Donlin Gold due to the commencement of BFS

related activities including hiring for key roles on the Donlin Gold project team and higher general and

administrative expenses at NOVAGOLD, while remaining in line with our 202 6 guidance.

New Technical Partnerships and Key Workstreams Propel Donlin Gold Forward

Following a transformational year for the Company and the Donlin Gold project, the first quarter of 2026

has delivered growing momentum and meaningful progress across key workstreams. Donlin Gold is

increasingly well-positioned for the next phase of development, supported by several important

milestones.

1 NOVAGOLD defines a Tier One gold development project as one with a projected production life of at least 10 years, annual pro jected production of

at least 500,000 ounces of gold, and average projected cash costs over the production life that are in the low er half of the industry cost curve.

These milestones include the selection of Fluor as the lead engineering firm to direct and integrate all

specialist workstreams for the BFS, expected to be completed in 2027, to support project financing and

development. Specialized contracts were also awarded to WSP, Worley, and Hatch to advance critical

infrastructure and processing components, including the on-site power plant, natural gas pipeline, and

the pressure oxidation circuit and oxygen plant.

Fluor and the Specialist Contractors have commenced work on the BFS under the leadership of the newly

appointed Project Director Frank Arcese — who has extensive experience in delivering large-scale mining

projects. With major contractors now on board and ongoing progress on the BFS workstreams, the

Company expects to review the schedule and budget for the next phase of development by mid-2026 and

provide any update to guidance as required.

Furthermore, with the successful completion of an upsized bought deal private placement in February, the

Company is well positioned to support critical activities, including expenditures related to Donlin Gold,

settlement of the prepayment option on the promissory note with Barrick Mining Corporation (“Barrick”),

and general corporate purposes.

During the first quarter, as part of Donlin Gold’s infrastructure and energy strategy, Donlin Gold signed a

non-binding LOI with Glenfarne, majority owner and developer of the Alaska LNG project, to explore the

potential supply of natural gas for Donlin Gold’s on-site power generation.

Donlin Gold’s exceptional scale, high-grade open-pit mineralization, long mine life, competitive estimated

operating costs, significant exploration upside2, and location in an excellent mining jurisdiction, place it

among a rare class of global gold assets. The project hosts approximately 40 million ounces of Measured

and Indicated Mineral Resources, inclusive of Mineral Reserves, at an average grade of 2.22 grams per

tonne3 —more than twice the industry average4. Importantly, these resources represent only a portion of

an eight-kilometer mineralized trend that covers less than 5% of the broader land package, highlighting

substantial exploration potential. Donlin Gold continues to advance district-wide exploration aimed at

expanding existing resources and identifying new discoveries across the largely underexplored property.

Sustaining Strategic Engagement with Local Communities, Government and Regional Stakeholders

as Donlin Gold Enters Its Next Phase of Development

Donlin Gold LLC continues to prioritize meaningful engagement with local communities, stakeholders, and

government representatives in the Yukon-Kuskokwim (Y-K) region, Alaska, and Washington, D.C., in

support of project development and permitting. Decades of consistent outreach across 62 Y-K

communities have fostered strong relationships, facilitated knowledge exchange, and reinforced the

project’s social license while building lasting trust. The Donlin Gold team remains dedicated to advancing

the project responsibly through open, respectful, and transparent communication at every stage.

2 Donlin Gold data as per the report titled “NI 43-101 Technical Report on the Donlin Gold project, Alaska, USA” with an effective date of November 30,

2025 (the “2025 Technical Report”) and the report titled “S -K 1300 Technical Report Summary on the Donlin Gold Project, Alaska, USA” (the “2025

Technical Report Summary”), dated November 30, 2025.

3 Donlin Gold possesses Measured Resources of approximately 9 Mt grading 2.67 g/t and Indicated Resources of approximately 551 Mt grading

2.21 g/t, each on a 100% basis and inclusive of Mineral Reserves, of which approximately 6 Mt of Measured Resources and approximat ely 330 Mt of

Indicated Resources inclusive of Mineral Reserves is currently attributable to NOVAGOLD through its 60% ownership interest in Donlin Gold LLC.

Exclusive of Mineral Reserves, Donlin Gold possesses Measured Resources of approximately 1.4 Mt grading 1.18 g/t and Indicated Resources of

approximately 175 Mt grading 1.32 g/t, of which approximately 0.9 Mt of Measured Resources and approximately 105 Mt of Indicated Resources

exclusive of Mineral Reserves is currently attributable to NOVAGOLD. Donlin Gold possesses Proven Reserves of approximately 9 Mt grading 2.29 g/t

and Probable Reserves of approximately 495 Mt grading 2.02 g/t, each on a 100% basis, of which approximately 6 Mt of Proven R eserves and

approximately 297 Mt of Probable Reserves is attributable to NOVAGOLD. Mineral Reserves and Resources have b een estimated in accordance with NI

43-101 and S-K 1300.

4 As of March 2026, S&P Global Market Intelligence reports that the global industry average grade for open -pit and underground gold deposits with

over 1 million ounces in Measured and Indicated Mineral Resources, inclusive of Mineral Reserves, is 1.0 4 g/t. In comparison, Donlin Gold’s grade is

2.22 g/t, more than double the industry average.

NEWS RELEASE

 www.novagold.com

Page | 3

In that spirit, Donlin Gold participated in important strategic government activities in the first quarter to

increase its presence and broaden our reach, including the Alaska Chamber of Commerce and Resource

Development Council Legislative fly-in, providing project updates, meetings with Congressional

delegation state directors, and holding discussions with the Alaska Department of Natural Resources

Commissioner and Deputy Commissioner. Donlin Gold also conducted two multi-day visits to Juneau,

Alaska, during the State Legislature’s session to hold 11 legislative meetings and engage with numerous

state representatives and senators.

In addition, during the first quarter, Donlin Gold and NOVAGOLD staff participated in the 4th annual

Juneau Mining Forum and a joint legislative reception for the Alaska Miners Association, Trucking

Association and Alaska General Contractors Association. Donlin Gold staff also attended Senator Lisa

Murkowski’s holiday luncheon and co-sponsored an event for Speaker Bryce Edgmon, Senator Cathy

Giessel, and Representative Louise Stutes.

As part of an ongoing commitment between Donlin Gold, Calista Corporation (“Calista”), and The

Kuskokwim Corporation (TKC) to seek input and share knowledge on subsistence matters, Donlin Gold

hosted its bi-annual Subsistence Community Advisory Committee (SCAC) meeting in Anchorage . The

SCAC members represent a range of perspectives on the project that are important to consider as we

advance development. Donlin Gold also held its first virtual SCAC session, which included participation

from both SCAC and Donlin Gold Project Community Advisory Committees. The meetings focused on the

Barge Communications Plan, providing SCAC members with an opportunity to review the project

approach, ask questions, and provide feedback that informs ongoing planning.

Donlin Gold also provided a project update at a town hall meeting in Bethel, the largest city downriver

from the project.

Supporting Social, Cultural, and Environmental Priorities in the Y-K Region

NOVAGOLD and Donlin Gold actively contributed to a wide range of programs and community events

across the Y-K region, supporting cultural preservation, strengthening stakeholder relationships,

advancing economic and social well-being, and promoting youth engagement. These efforts included

collaborating with Calista’s Shareholder Relations Committee and traveling to four Y-K communities to

engage directly with Calista shareholders on topics including the Donlin Gold project.

In the first quarter of 2026, Donlin Gold continued its support of local stakeholders across education,

sports, and cultural initiatives. Key programs included the Cook Inlet Tribal Council’s Native Youth

Olympics, the Alaska School Activities Association/First National Bank Alaska Wrestling State

Championships, the Girl Scouts of Alaska, the Lower Yukon School District Career Fair, the Kusilvak Career

Academy, and the University of Alaska Foundation’s Rural Alaska Honors Institute — a six-week, tuition-

free program helping rural and Alaska Native students earn college credits and develop academic skills.

Donlin Gold also hosted and supported the “Donlin Gold Classic” Invitational Basketball Tournament at

Bethel Regional High School, bringing together varsity teams and community members from across the Y-

K region.

Donlin Gold also engaged with municipal leaders and community stakeholders across Alaska by

participating in and supporting the Alaska Municipal League Conference, discussing regional priorities

and development opportunities. In addition, Donlin Gold pursued its support for the Alaska Safe Riders

winter safety program, promoting the safe use of snowmachines, all-terrain vehicles, and other

recreational off-road vehicles.

These various efforts are also aligned with Donlin Gold’s long-term objectives to support workforce

development and regional economic participation as the project advances.

Regulatory Approvals in Hand, Safeguarding Donlin Gold’s Permitting Position

Donlin Gold continues to support the State of Alaska in defending the Department of Environmental

Conservation’s Clean Water Act (CWA) Section 401 Water Quality Certification, which is the only

remaining challenge to Donlin Gold’s permits in State court. Briefing before the Alaska Supreme Court is

complete and oral argument is scheduled for April 8, 2026.

In 2025, the U.S. Alaska District Court directed the U.S. Army Corps of Engineers (USACE) and the Bureau

of Land Management (BLM) to supplement the current Environmental Impact Statement with an analysis

of a larger theoretical tailings dam release, while leaving Donlin Gold’s Federal permits in place. The

USACE, in consultation with BLM, will lead the Supplemental Environmental Impact Statement (SEIS)

process to conduct this analysis. The CWA permits and BLM ROW remain in place during this

supplementation, which is being undertaken under the Fixing America’s Transportation Act (“FAST -41”)

program and coordinated by the Federal Permitting Improvement Steering Council ( the “Permitting

Council”). The USACE has submitted a schedule for completing the SEIS by mid-2027 to the Permitting

Council. A Notice of Intent to prepare a SEIS was issued in January 2026, and the public comment period

for the scoping process closed in February 2026. The USACE and cooperating agencies will now review

and consider comments received and proceed with preparation of the draft SEIS which is anticipated to

be published in September 2026, in accordance with the coordinated FAST-41 permitting schedule.

These milestones demonstrate the project’s solid regulatory foundation, the successful defense to date of

its permits by Federal and State agencies, and the ongoing progress being made toward future

development.

NOVAGOLD Outlook

With a pivotal year behind us — which, among other achievements, included the acquisition of Barrick’s

50% interest in Donlin Gold together with Paulson, as well as key financings — the Company enters 2026

with strong momentum and is well positioned to responsibly advance into the next phase of

development, maximizing the project’s value proposition and its exceptional leverage to gold prices.

In 2026, Donlin Gold’s primary focus remains on progressing the BFS and enhancing the project’s long-

term potential. Core priorities include advancing engineering and technical workstreams, pursuing

exploration to identify district-wide opportunities, and evaluating potential financing options. Engineering

efforts, led by Fluor, are advancing workstreams and integrating inputs from Specialist Contractors into a

comprehensive framework for engineering, cost, and schedule, targeted for completion in 2027.

In parallel, Donlin Gold is building a project team and advancing critical site and technical activities to

support the BFS, including geotechnical drilling and materials assessments along the planned upriver port

and access road. Donlin Gold will continue to support permitting activities and maintain deep

engagement with Alaska Native Corporation landowners, local communities, and government

stakeholders as it moves toward BFS completion and the project’s next stage of development.

NOVAGOLD remains focused on delivering on every single commitment made, advancing the Donlin Gold

project responsibly, and achieving critical milestones. We extend our sincere appreciation to our

shareholders, stakeholders, and Board of Directors for their ongoing support and trust. We are also

grateful to the Donlin Gold team for their hard work and commitment, and we look forward to a year of

continued progress and opportunity.

Sincerely,

Gregory A. Lang

NEWS RELEASE

 www.novagold.com

Page | 5

President and CEO

Liquidity and Capital Resources

As of February 28, 2026, the Company had cash resources comprising cash and cash equivalents and term

deposits totaling approximately $392.5 million, which are sufficient to cover the anticipated funding costs

to complete the Donlin Gold BFS and to exercise its option to prepay the Barrick promissory note .

Cash used in operating activities during the first quarter of 2026 was $5.3 million, $0.2 million lower than

the comparative prior year period. Cash used in investing activities during the first quarter of 2026

increased by $278.7 million from the comparative prior year period primarily due to $270.0 million in net

purchases of term deposits and $11.9 million in incremental Donlin Gold funding partially offset by

$3.2 million in proceeds from the sale of marketable securities. Funding of Donlin Gold was higher in the

first quarter of 2026 compared to the same period in 2025 due to increased activity following the

commencement of the Donlin Gold BFS in early February 2026 and due to the Company’s share of Donlin

Gold funding increasing by 10% from 50% to 60% starting in the third quarter of 2025.

Cash provided by financing activities during the first quarter of 2026 increased by $2 94.1 million from the

comparative prior year period primarily due to $310.2 million in proceeds from a private placement

offering less $16.2 million of issuance costs.

As of As of

February 28, 2026

$

November 30, 2025

$

Cash and term deposits 392,493 115,143

Total assets 619,434 335,913

Total liabilities 175,192 172,119

2026 Outlook

NOVAGOLD’s anticipated operating expenditures during fiscal year 2026 are unchanged from previously

issued guidance at approximately $98.5 million, including $78.8 million to fund the Donlin Gold project

and to continue to advance the BFS, and $19.7 million for corporate general and administrative costs.

With the commencement of the Donlin Gold BFS during the first quarter of 2026, NOVAGOLD’s pro -rata

share of Donlin Gold expenditures is expected to increase over the next 18 to 24 months from fiscal 2025

levels.

NOVAGOLD’s catalysts in the coming year include completing the BFS and moving to a subsequent Final

Investment Decision; maintaining a favorable reputation of NOVAGOLD and the Donlin Gold project

among shareholders and stakeholders; promoting strong community outreach and a sustainability culture;

upholding strong safety and environmental performance; and managing the Company’s treasury

effectively and efficiently.

Conference Call & Webcast Details

NOVAGOLD’s conference call and webcast to discuss these results will take place April 1, 2026, at 8:00 am

PT (11:00 am ET). The webcast and conference call-in details are provided below.

Video Webcast: www.novagold.com/investors/events

North American callers: 1-833-752-3655

International callers: 1-647-846-8520

About NOVAGOLD

NOVAGOLD is a well-financed precious metals company focused on the development of the Donlin Gold

project in Alaska, one of the safest mining jurisdictions in the world. With approximately 40 million ounces

of gold in the Measured and Indicated Mineral Resource categories (560 million tonnes at an average

grade of approximately 2.22 grams per tonne, in the Measured and Indicated Mineral Resource categories

on a 100% basis)5, inclusive of Proven and Probable Mineral Reserves, the Donlin Gold project is regarded

to be one of the largest, highest-grade, and most prospective known open-pit gold deposits in the world.

According to the 2025 Technical Report and the 2025 Technical Report Summary (as defined below), the

Donlin Gold project is expected to produce an average of more than one million ounces per year over a

27-year mine life on a 100% basis once in production. 6

About Donlin Gold Holdings

Donlin Gold Holdings, 100% wholly-owned by Paulson Advisers LLC and its affiliates, is the 40% owner of

the Donlin Gold project. Donlin Gold Holdings, together with NOVAGOLD, owns 100% of Donlin Gold and

shares equal voting and operating control with NOVAGOLD through its operating agreement.

NOVAGOLD Contacts:

Mélanie Hennessey

Vice President, Corporate Communications

Frank Gagnon

Manager, Investor Relations

604-669-6227 or 1-866-669-6227

[email protected]

www.novagold.com

Cautionary Note Regarding Forward-Looking Statements

This media release includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking

statements”) within the meaning of applicable securities legislation, including the United States Private Securities Litigation Reform Act

5 Donlin Gold data as per the 2025 Technical Report and the 2025 Technical Report Summary. Donlin Gold possesses Measured Resources of

approximately 9 Mt grading 2.67 g/t and Indicated Resources of approximately 551 Mt grading 2.21 g/t, each on a 100% basis an d inclusive of Mineral

Reserves, of which approximately 6 Mt of Measured Resources and approximately 330 Mt of Indicated Resources inclusive of Mineral Reserves is

currently attributable to NOVAGOLD through its 60% ownership interest in Donlin Gold LLC. Exclusive of Mineral Reserves, Donl in Gold possesses

Measured Resources of approximately 1.4 Mt grading 1.18 g/t and Indicated Resources of approximately 175 Mt grading 1.32 g/t, of which

approximately 0.9 Mt of Measured Resources and approximately 105 Mt of Indicated Resources exclusive of Mineral Reserves is c urrently attributable to

NOVAGOLD. Donlin Gold possesses Proven Reserves of approximately 9 Mt gr ading 2.29 g/t and Probable Reserves of approximately 495 Mt grading

2.02 g/t, each on a 100% basis, of which approximately 6 Mt of Proven Reserves and approximately 297 Mt of Probable Reserves is attributable to

NOVAGOLD. Mineral Reserve and Resources have been estimated in accordance with NI 43-101 and S-K 1300.

6 Anticipated average annual gold production during full life of mine if put into production as contemplated in the 2025 Techni cal Report and the 2025

Technical Report Summary.

NEWS RELEASE

 www.novagold.com

Page | 7

of 1995. Forward-looking statements include future-oriented financial information or financial outlook within the meaning of securities

laws, including information regarding NOVAGOLD’s anticipated expenditures. Such information is intended to assist readers in

understanding NOVAGOLD’s current expectations and plans relating to the future. Such information may not be appropriate for other

purposes. Forward-looking statements are frequently, but not always, identified by words such as “expects”, “anticipates”, “believes”,

“intends”, “estimates”, “potential”, “possible”, and similar expressions, or statements that events, conditions, or results “will”, “may”,

“could”, “would” or “should” occur or be achieved. Forward-looking statements are necessarily based on several opinions, estimates and

assumptions that management of NOVAGOLD considered appropriate and reasonable as of the date such statements are made, are

subject to known and unknown risks, uncertainties, assumptions, and other factors that may cause the actual results, activity,

performance, or achievements to be materially different from those expressed or implied by such forward-looking statements. All

statements, other than statements of historical fact, included herein are forward-looking statements. These forward-looking statements

include statements regarding the anticipated timing of certain judicial and/or administrative decisions; statements regarding potential

infrastructure development, including but not limited to the natural gas pipeline; timing of the completion of the detailed design

package, if at all; plans for and the estimated timing of aspects of an updated Bankable Feasibility Study on the Donlin Gold project; our

goals and planned activities for 2026; our future exploration plans at Donlin Gold; ongoing support provided to key stakeholders

including Alaska Native Corporation landowners; Donlin Gold’s continued support for the state and federal permitting process;

sufficiency of working capital; the potential development and construction of the Donlin Gold project; the timing and ability for the

Donlin Gold project to achieve critical milestones; the ability for the Donlin Gold development project to achieve the anticipated

projections; the sufficiency of funds to continue to advance development of Donlin Gold; the anticipated use of net proceeds from

previous offerings; perceived merit of properties; mineral reserve and mineral resource estimates; Donlin Gold’s ability to secure the

permits needed to construct and operate the Donlin Gold project in a timely manner, if at all; legal challenges to Donlin Gold’s existing

permits and the timing of decisions in those challenges; plans to continue to advance the Donlin Gold project safely, socially and

environmentally responsibly and to sustainably generate value for our stakeholders; continued cooperation between the owners of

Donlin Gold LLC to advance the project; the Company’s ability to deliver on its strategy with the Donlin Gold project, increasing the

value of the project; the success of the strategic mine plan for the Donlin Gold project; the success of the Donlin Gold community

relations plan; the anticipated timing and outcome of exploration drilling at the Donlin Gold project and the timing thereof; and the

completion of test work and modeling and the timing thereof. In addition, any statement that refers to expectations, intentions,

projections or other characterizations of future events or circumstances are forward-looking statements. Forward-looking statements

are not historical facts but instead represent the expectations of NOVAGOLD management’s estimates and projections regarding future

events or circumstances on the date the statements are made. Important factors that could cause actual results to differ materially from

expectations include the need to obtain additional permits and governmental approvals; the timing and likelihood of obtaining and

maintaining permits necessary to construct and operate; the need for additional financing to complete an updated Bankable Feasibility

Study and to explore and develop properties; availability of financing in the debt and capital markets; the disparity between the

economic and governance level at Donlin Gold and the Company; disease pandemics; uncertainties involved in the interpretation of

drill results and geological tests and the estimation of reserves and resources; changes in mineral production performance, exploitation

and exploration successes; changes in national and local government legislation, taxation, controls or regulations and/or changes in the

administration of laws, policies and practices, expropriation or nationalization of property and political or economic developments in

the United States or Canada; the need for continued cooperation between the owners of Donlin Gold LLC to advance the project; the

need for cooperation of government agencies and Native groups in the development and operation of properties; risks of construction

and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with environmental and permit

requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases, which could

include significant increases in estimated capital and operating costs; fluctuations in metal prices and currency exchange rates; whether

or when a positive construction decision will be made regarding the Donlin Gold project; and other risks and uncertainties disclosed in

NOVAGOLD’s most recent reports on Forms 10-K and 10-Q, particularly the “Risk Factors” sections of those reports and other

documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. Copies of these filings may be

obtained by visiting NOVAGOLD’s website at www.novagold.com, or the SEC’s website at www.sec.gov, or on SEDAR+ at

www.sedarplus.ca. The forward-looking statements contained herein reflect the beliefs, opinions and projections of NOVAGOLD on the

date the statements are made. NOVAGOLD assumes no obligation to update the forward-looking statements of beliefs, opinions,

projections, or other factors, should they change, except as required by law.