Premium Nickel Reports Assays at Selebi North Underground 15.30 metres of 2.96% NiEq (1.84% Ni; 1.85% Cu; 0.10% Co) Incl. 8.45 metres of 3.07% NiEq (2.15% Ni; 1.40% Cu; 0.11% Co)
Premium Nickel Reports Assays at Selebi
North Underground
15.30 metres of 2.96% NiEq (1.84% Ni; 1.85% Cu; 0.10% Co)
Incl. 8.45 metres of 3.07% NiEq (2.15% Ni; 1.40% Cu; 0.11% Co)
Toronto, Ontario--(Newsfile Corp. - January 18, 2024) -
Premium Nickel Resources Ltd. (TSXV:
PNRL) (OTCQX: PNRLF) ("PNRL" or the "Company")
is pleased to report additional assay results
from drilling at its past-producing nickel-copper-cobalt sulphide ("
Ni-Cu-Co
") Selebi North underground
("
SNUG
") mine in Botswana. Previous results for 16 holes were released, November 14, November 27
and December 19, 2023, respectively. Results for a further seven holes are released herein. To date a
total of 23 holes have been released representing an aggregate of approximately 8,242 metres including
the holes and metres released herein. Details of the assay results are shown below along with
accompanying visuals via Figure 1 and Figure 2. Drill core photos for all holes released to date,
including the holes reported herein, are accessible by
Clicking Here
and can also be found on the
Company website at
www.premiumnickelresources.com
.
Highlights include:
SNUG-23-055 (South Limb): 15.30 metres of 2.96% NiEq (1.84% Ni; 1.85% Cu; 0.10% Co)
including 8.45 metres of 3.07% NiEq (2.15% Ni; 1.40% Cu; 0.11% Co)
and 3.00 metres of 3.01% NiEq (2.13% Ni; 1.28% Cu; 0.12% Co)
SNUG-23-054 (N3 Limb): 6.85 metres of 4.01% NiEq (2.72% Ni; 1.97% Cu; 0.15% Co)
SNUG-23-053 (South Limb): 6.05 metres of 2.78% NiEq (1.95% Ni; 1.23% Cu; 0.11% Co)
Keith Morrison, CEO of PNRL, commented:
"The Company is very encouraged with these and past
results as they continue to further substantiate our views that higher grade zones relating to the
conductive massive sulphide Ni-Cu-Co mineralization exist at Selebi North underground.
During the
Holiday season we completed additional borehole EM surveys in the area down plunge from these
mineralized structures at the Selebi North deposit. Our underground drilling will now continue to progress
down plunge, aiming to intercept additional mineralization that was not accounted for in the historic
resource."
The purpose of this drill program is to define mineralization down plunge of the existing workings that will
be used to complete a Mineral Resource Estimation ("
MRE
") prepared in accordance with National
Instrument 43-101 -
Standards of Disclosure for Mineral Projects
("
NI 43-101
"). Assay results are given
below in Table 1 and hole collar details are given in Table 2. Figures 1 and 2 show the location of holes
relative to the historic resource and underground infrastructure.
Table 1: Assay Results Selebi North Deposit
Hole-ID
From
(m)
To
(m)
*Length
(m)
Ni
(%)
Cu
(%)
Co
(%)
Limb
**NiEq
(%)
SNUG-23-038
47.90
51.55
3.65
1.05
1.27
0.04
N2
1.78
SNUG-23-038
60.00
62.35
2.35
0.62
0.94
0.02
N2
1.14
SNUG-23-038
65.40
70.10
4.70
0.53
2.09
0.05
N2
1.69
SNUG-23-038
77.25
85.85
8.60
0.48
0.93
0.03
N2
1.01
including
77.25
79.75
2.50
0.50
2.60
0.04
N2
1.89
SNUG-23-038
101.80
103.80
2.00
1.20
2.02
0.05
N2
2.32
SNUG-23-038
326.15
332.40
6.25
1.15
0.88
0.06
N3
1.71
SNUG-23-051
159.60
163.75
4.15
0.50
0.69
0.03
South
0.91
SNUG-23-051
182.10
183.40
1.30
0.37
1.47
0.02
South
1.15
SNUG-23-052A
140.40
148.00
7.60
0.97
0.97
0.05
N2
1.56
including
145.55
148.00
2.45
1.02
1.85
0.05
N2
2.05
SNUG-23-052A
357.30
358.75
1.45
1.59
0.31
0.07
N3
1.89
SNUG-23-053
74.95
81.00
6.05
1.95
1.23
0.11
South
2.78
SNUG-23-053
95.40
98.00
2.60
1.05
0.65
0.05
South
1.48
SNUG-23-054
110.80
116.80
6.00
0.87
1.23
0.04
N3
1.58
including
111.25
114.80
3.55
1.37
1.49
0.06
N3
2.24
SNUG-23-054
182.25
189.10
6.85
2.72
1.97
0.15
N3
4.01
SNUG-23-055
91.70
107.00
15.30
1.84
1.85
0.10
South
2.96
including
91.70
100.15
8.45
2.15
1.40
0.11
South
3.07
and
104.00
107.00
3.00
2.13
1.28
0.12
South
3.01
Hole-ID
From
(m)
To
(m)
*Length
(m)
Ni
(%)
Cu
(%)
Co
(%)
Limb
**NiEq
(%)
*Length refers to drillhole length and not true width. True width is unknown.
**NiEq was calculated assuming a price of $US 7.39/lb for Ni, $US 3.77/lb for Cu and $US 13.86/lb for cobalt with no adjustments for recoveries and
payabilities.
Table 2: Drill Collar Information Selebi North Deposit
HOLE ID
Mine East
Mine North
Elevation
Dip
Mine
Azimuth
Hole Length
Comment
SNUG-23-038
34919.3
84907.2
-9.0
-36.9
220.9
374.3
Rig #3 895mL
SNUG-23-051
35094.4
84759.3
-51.9
-15.9
129.9
311.6
Rig #1 935mL
SNUG-23-052*
35081.7
84843.7
-7.8
-17.0
255.0
5.1
Rig #2 880mL
SNUG-23-052A
35081.7
84843.7
-7.8
-17.5
255.2
395.0
Rig #2 880mL
SNUG-23-053
35095.1
84759.6
-51.5
-1.4
148.1
134.2
Rig #1 935mL
SNUG-23-054
34918.9
84907.5
-8.2
-12.5
224.5
224.4
Rig #3 895mL
SNUG-23-055
35094.4
84759.0
-50.8
-1.6
165.0
137.4
Rig #1 935mL
*abandoned hole
The various mineralized zones have been historically mined and subsequently named N2 Limb, N3 Limb
and South Limb to demarcate their location on the folded mineralized horizon. Additional drilling is
needed to estimate true width and define the folded mineralization.
Drilling Continues
Two drills have been mobilized to the 810 metre level exploration drift, permitting testing areas further
down plunge of the three mineralized zones with the aim to demonstrate upside potential that will support
a future MRE.
As of January 17, 2024, a total of 18,120 metres in 49 drillholes have been completed from the initial
three underground drill bays and 514 metres have been drilled from two drill bays on the 810mL
exploration drift. During this initial phase, drilling is targeting the area down plunge of mine infrastructure
to characterize the remaining resource. Assay results for completed holes will be released as they are
received and confirmed by the Company.
Quality Control
The underground drilling program is being carried out through an agreement with Forage Fusion Drilling
Ltd. of Hawkesbury, Ontario, Canada, who have provided three Zinex U-5 drills for purchase and training
of local operators. Drill core samples are BQTK (40.7 mm diameter). All samples are ½ core cut by a
diamond saw on site. Half of the core is retained for reference purposes. Samples are generally 1.0 to
1.5 metre intervals or less at the discretion of the site geologists. Sample preparation and lab analysis
was completed at the ALS Chemex in Johannesburg, South Africa. Commercially prepared blank
samples and certified Cu/Ni sulphide analytical control standards with a range of grades are inserted in
every batch of 20 samples or a minimum of one set per sample batch. Analyses for Ni, Cu and Co are
completed using a peroxide fusion preparation and ICP-AES finish (ME-ICP81).
Holes are numbered as follows: SNUG (Selebi North Underground) + year + hole number starting at 013.
Qualified Person
The scientific and technical content of this news release has been reviewed and approved by Sharon
Taylor, Vice President Exploration of the Company, who is a "qualified person" for the purposes of NI
43-101.
Technical Report
Scientific and technical information relating to the Selebi Mine is supported by the technical report titled
"Technical Report on the Selebi Mines, Central District, Republic of Botswana, Report for NI 43-101"
,
dated June 16, 2022 (effective date of March 1, 2022) (the "
Selebi Technical Report
"), and prepared
by SLR Consulting (Canada) Ltd. for PNRL. Reference should be made to the full text of the Selebi
Technical Report, including the assumptions, limitations and data verification therein relating to the
historic data compilation presented in this news release, which was prepared in accordance with NI 43-
101 and is available electronically on SEDAR+ (
www.sedarplus.com
) under PNRL's issuer profile.
Historic Resource Estimate
The historical mineral resource estimate referenced herein (the "
Historic Resource
") was calculated
for the Selebi North, Selebi Main, Phikwe South and Southeast Extension deposits in accordance with
SAMREC, in 2016, and does not comply with NI 43-101. To that end, the Historic Resource is
considered to be historical in nature and should not be relied upon as a current mineral resource
estimate. While management believes that the Historic Resource could be indicative of the presence of
mineralization on the deposits, a qualified person for purposes of NI 43-101 has not completed sufficient
work to classify the historical mineral estimates as current mineral resource estimates and PNRL is not
treating the historical mineral estimates as current mineral resource estimates.
About Premium Nickel Resources Ltd.
PNRL is a mineral exploration and development company that is focused on the redevelopment of the
previously producing nickel, copper and cobalt resources mines owned by the Company in the Republic
of Botswana. We are driven by our belief that the demand for these metals will continue to grow in the
medium to long term, as a result of global urbanization and the increasing adoption of electric motors
over internal combustion engines. These metals are vital for achieving a low-carbon future.
PNRL is committed to governance through transparent accountability and open communication within
our team and our stakeholders. Our skilled team has worked over 100 projects collectively, accumulating
over 400 years of resource discoveries, mine development and mine re-engineering experience on
projects like the Company's Selebi and Selkirk mines. PNRL's senior team members have on average
more than 20 years of experience in every single aspect of mine discovery and development, from
geology to operations.
ON BEHALF OF THE BOARD OF DIRECTORS
Keith Morrison
Chairman and Chief Executive Officer
Premium Nickel Resources Ltd.
For further information about Premium Nickel Resources Ltd., please contact:
Jaclyn Ruptash
Vice President, Communications and Government and Investor Relations
+1 (604) 770-4334
Cautionary Note Regarding Forward-Looking Statements:
This news release contains "forward-looking information" within the meaning of applicable Canadian
securities legislation based on expectations, estimates and projections as at the date of this news
release. Forward-looking information involves risks, uncertainties and other factors that could cause
actual events, results, performance, prospects and opportunities to differ materially from those
expressed or implied by such forward-looking information. Forward-looking information in this news
release includes, but is not limited to: the ability of the Company to implement its drilling, geoscience and
metallurgical work on its properties and work plans generally; the implementation of the objectives, goals
and future plans of the Company including the proposed advancement of the Selebi Mines as currently
contemplated; the ability of exploration activities (including drill results) to accurately predict
mineralization; management's belief that the Selebi and Selebi North deposits may be connected at
depth; the timing to release of the remaining assay results; the ability of the Company to implement its
drilling, geoscience and metallurgical work on its properties and work plans generally; the
implementation of the objectives, goals and future plans of the Company including the proposed
advancement of the Selebi Mines as currently contemplated; the ability of the Company to define mineral
resource estimates on the Selebi Mines in accordance with NI 43-101 and/or obtain an updated MRE in
respect of the Selebi Mines; the productivity rates for underground drilling at Selebi North; drilling results
confirming the legacy fold pattern continues at depth; the effective targeting activities proposed by the
Company; the ability to identify mineralization down plunge of existing workings and the ability of such
findings to be used to complete a MRE; the ability and timing of advancing the underground drilling
program at Selebi North as contemplated (if at all); the results of the drill program on Selebi North and
the timing and disclosures of the Company regarding same;
the relationships between, and continuity of,
the various deposits (if any); the benefits of the Company's approach to exploration; management's
belief that the Historic Resource could be indicative of the presence of mineralization on the deposits;
and the anticipated benefits of the Company's approach to the resource development plan. These
forward-looking statements, by their nature, require the Company to make certain assumptions and
necessarily involve known and unknown risks and uncertainties that could cause actual results to differ
materially from those expressed or implied in these forward-looking statements. Factors that could
cause actual results to differ materially from such forward-looking information include, but are not limited
to, capital and operating costs varying significantly from estimates; the preliminary nature of metallurgical
test results; the ability of exploration results to predict mineralization or the feasibility of mine production;
delays in obtaining or failures to obtain required governmental, environmental or other project approvals;
uncertainties relating to the availability and costs of financing needed in the future; changes in equity
markets; inflation; fluctuations in commodity prices; delays in the development of projects; the other risks
involved in the mineral exploration and development industry; and those risks set out in the Company's
public disclosure record on SEDAR+ (
www.sedarplus.com
) under PNRL's issuer profile. Although the
Company believes that the assumptions and factors used in preparing the forward-looking information in
this news release are reasonable, undue reliance should not be placed on such information, which only
applies as of the date of this news release, and no assurance can be given that such events will occur in
the disclosed time frames or at all. The Company disclaims any intention or obligation to update or
revise any forward-looking information, whether as a result of new information, future events or otherwise,
other than as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is
defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy
or accuracy of this news release.
Follow Us
X (formally Twitter):
https://twitter.com/PremiumNickel
Linked in:
https://www.linkedin.com/company/premium-nickel-resources
Facebook:
https://www.facebook.com/PremiumNickel
Figure 1: Selebi North: Location of Reported Drill Holes with Underground Infrastructure,
Historic Resources and Exploration Targets
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7759/194676_9ff7bdf744653905_002full.jpg
Figure 2: Selebi North Drill Hole Location
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7759/194676_9ff7bdf744653905_003full.jpg
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/194676