Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NEXG.V ·

Treasury Metals Announces Significantly Improved Economics at Goliath Project After-Tax NPV of C$306 million and IRR of 25% at US $1,225 per ounce

Economic Studies

Treasury Metals Announces Significantly Improved Economics at Goliath Project

After-Tax NPV of C$306 million and IRR of 25% at US $1,225 per ounce

TSX:TML

Highlights (all currencies are reported in Canadian dollars unless otherwise specified):

• The PEA benefits from a 37% increase in the Life of Mine ("LOM") gold production profile,

while taking a conservative approach with respect t o operating and capital costs compared

with the 2012 PEA;

• Average annual production of 87,850 oz Au over a 13 year combined open pit and

underground mine life; peak production exceeding 10 0,000 oz per year Au from years three to

six;

• LOM head grade of 3.8 g/tonne (Au), an increase of 33% from the 2012 PEA; and

• Total cash cost is estimated at US$518 per equivale nt gold ounce ("AuEq") and an all-in

sustaining cost ("AISC"), as defined by the World G old Council, estimated at US$566 per

AuEq;

TORONTO, March 8, 2017 /CNW/ - Treasury Metals Inc. (TSX: TML) (" Treasury " or the " Company ") is

pleased to announce the results from an updated Pre liminary Economic Assessment ("PEA") integrating

recent engineering and incorporating the 2015 NI 43-101 Mineral Resource Estimate from its Goliath

Gold Project ("Goliath" or the "Project").

"The updated 2017 PEA benefits from increased minea ble resources and a higher grade profile while

using a more conservative approach related to all m ining costs, capital costs and dilution compared with

the 2012 PEA. As such, Treasury will confidently mo ve forward with a Feasibility Study in addition to the

other development activities set forth in our March 1, 2017 corporate update. The revised PEA is the

result of all the considerable progress made at Goliath over the past five years and represents a key

milestone in the path towards a production decision," said Chris Stewart, President and Chief Executiv e

Officer of Treasury.

Goliath is located in northwestern Ontario, lying 20 kilometres east of the city of the Dryden. The total

area of the Project is 49 km 2 and is owned 100% by the Company. The site benefit s significantly from

excellent access to infrastructure and is directly adjacent to the Trans-Canada highway and Canadian

Pacific Railway. The Project has access to electrical and natural gas power, rail, paved roadways to s ite

and several nearby communities.

The optimized mining plan used in the PEA envisions an initial open pit generating immediate revenues to

fund underground development. Underground ("UG") pr oduction begins in the second year with the open

pit operating over an additional 7 years at a reduced output to supplement UG production to a total of

2,500 tonnes per day over the course of a 13 year total mine life. Total gold production is estimated at

1.14 million ounces of gold and 2.0 million ounces of silver. Initial capital to fund construction is estimated

at C$133.2 million with an additional C$132.5 million in sustaining capital over the LOM primarily to fund

the underground expansion.

The mine is proposed to produce an average head gra de of 3.81 g/t gold and 10.55 g/t silver with Open

Pit and UG mining producing average grades of 1.58 g/t and 4.87 g/t of gold, respectively. The infill

diamond drilling programs completed since the PEA c ompleted by Treasury in 2012 (the "2012 PEA") has

resulted in improved project economics and overall confidence in the mine plan. The stripping ratio of

waste rock to mill feed has been reduced to 6:1, which represents a 35% improvement over the 2012

PEA. This stripping ratio does not include pre-production stripping of approximately 1.3 million m 3 cubed

of overburden material. All mined ounces in the open pit are within the Measured and Indicated

categories. Seventy per cent of the mineable ounces within the Underground are classified within the

Measured and Indicated categories which represent a significant increase from the 2012 PEA. UG

production is envisioned to be carried out at an average rate of 1,600 tonnes per day using the long hole

stoping method on 30 metre sublevels. Average UG operating costs have been estimated at $77/tonne,

a 28% increase over the cost assumption in the 2012 PEA.

Goliath PEA Overview

The 2017 PEA was prepared by CSA Global Canada Geosciences Ltd. ("CSA Global") with the

assistance of P&E Engineering Consultants and the C ompany's operations and exploration teams in

collaboration with a range of industry consultants (see Qualified Persons section below).

The PEA was prepared in accordance with National Instrument 43-101 and the technical report that

summarizes the results of the 2017 PEA will be filed on the Company's website and on Sedar

(www.sedar.com ) within 45 days of this press release.

PEA Assumptions and Economic Results (Base Case Met rics)

Table 1 presents a summary of the life-of-mine gold production information and other key highlights of the

Project. All amounts are in Canadian Dollars except the realized gold and silver price which is quoted in

US Dollars. All grade and oz. values are quoted separately as gold and silver unless specified as

equivalent ounces, with 1 oz Au = 110 oz Ag, calculated by base case metal prices as listed in Table 1.

Table 1

Project Parameters Unit Amount

Gold Resources

Gold and Silver Production – Recovered Resources Oz 1,142,000 and 2,075,000

Cut-off Grade – Open Pit and Underground Au g/tonne 0.55 and 2.10

Average Mill Feed Gold Grade Au (g/tonne) 3.81

Average Mill Feed Silver Grade Ag (g/tonne) 10.55

Average Open Pit Gold Grade (Au) Au (g/tonne) 1.58

Average Underground Gold Grade (Au) Au (g/tonne) 4.87

Average Gold Grade AuEq

(g/tonne)

3.91

Operating Metrics

Total Tonnes Mill Feed Produced Tonnes 9.8 million

Tonnes Mill Feed Produced breakdown OP and U/G 3.18 and 6.60 million

Mill Feed Production Rate tpd/tpa 2,500 tonne/day or 875,000/yr

Dilution (Open Pit) 25%

Dilution (UG) 15%

Strip Ratio (excluding 1.3 million m 3 of pre-

production overburden stripping)

Waste:Mill Feed 6:1

Gold Recovery (Processing) % 95.5%

Silver Recovery (Processing) % 62.6%

Average Gold Production Oz/year 87,850

Average Silver Production Oz/year 160,000

Average Gold Production (Au Equivalent) Au Eq 90,000

Peak Production (Year 6) Au 111,800

Mine life Years 13 years

Financial Metrics

Realized Gold and Silver Price (Base Case) US$/Oz $1,225 and $17

Total Initial Capital Expenditures C$M $133.2

Total Sustaining Capital (Including U/G) C$M $132.5

Cash Operating Cost US$/Oz $518

All in Sustaining Cost (AISC) US$/Oz $566

Mining Costs – Open Pit and UG $/tonne Open pit $3.45 and UG $77

Milling Costs and G & A costs $/tonne $18.15 and $2.85

Open Pit Waste Mining $/tonne $3.30

Overburden Removal $/m 3 $6.00

Exchange Rate US$ C$1.32

Cautionary statement required by NI 43-101

According to the cautionary statement required by NI 43-101, it should be noted that this assessment is

preliminary in nature as it includes Inferred mineral resources that cannot be categorized as reserves at

this time and as such there is no certainty that the preliminary assessment and economics will be

realized.

Project Economics

CSA Global concludes that under base case assumptio ns of 2,500 tpd production and US$1,225 per

ounce (base case – 3 year trailing average gold), t he Life of Mine post-tax net present value (NPV) of

$306 million based on a 5% discount rate, internal rate of return (IRR) of 25.0% and a payback of 4.1

years. The payback includes all UG mine development costs.

The following table summarizes the base case compar ed to various metal price assumptions:

Pre-Tax NPV and IRR Sensitivity to Gold Price

Gold Price

(USD)

NPV (5%)

(CDN$M)

NPV (7.5%)

(CDN$M) IRR

Payback

from

Production

US$1,150/oz $356.7 $268.3 26.3 4.0

US$1,200/oz $402.4 $306.2 28.7% 3.8

Base Case US$1,225/oz $425.3 $325.2 29.9% 3.7

US$1,275 $471.0 $363.2 32.3% 3.5

US$1,350 $539.4 $420.1 35.7% 3.2

US$1,500 $677.0 $534.3 42.3% 2.8

Post-Tax NPV and IRR Sensitivity to Gold Price

Gold Price

(USD)

NPV (5%)

(CDN$M)

NPV (7.5%)

(CDN$M) IRR

Payback

from

Production

US$1,150/oz $254.6 $185.1 22.1% 4.6

US$1,1200 $288.9 $213.6 24.1% 4.3

Base Case - US$1,225 $306.1 $227.9 25.0% 4.1

US$1,275 $340.4 $256.4 27.0% 3.9

US$1,350 $391.8 $299.1 29.8% 3.6

US$1,500 $494.9 $384.8 35.2% 3.2

Net Cash Flows

C$ Million Yearly

Average

Yearly

Average for

Yr 3 to 9

LOM Total

Net Metal Revenue $134.2M $166.1M $1,187M

Operating Cost $58.5M $67.2M $812.7M

Transportation, Royalties and Refining $0.6M $0.78M $9.3M

Capital Costs $18.6M $11.0M $265.7M

Pre-Tax Cash Flows $48.6M $81.1M $729.5M

Corporate Tax $18.8M $24.0M $254.5M

After-Tax Cash Flow $36.3M $63.5M $545.0M

Project Improvement and Future Trade-off Studies

• Resource Expansion: The resource remains open both at depth and on str ike. The PEA has also

taken a conservative approach to the exclusion of s everal areas of inferred resources. Specifically,

the PEA has excluded two zones of mineralized mater ial that are separated approximately 300

metres from the underground main resource area to the east and west, respectively. These areas

represent approximately 84,000 oz combined and high light the potential of resource expansion via

open strike extensions.

• Reduction and Optimization of Capital Expenditures: Availability of used equipment on the

market and/or the option of leasing equipment have potential to significantly reduce capital costs.

For example, used Open Pit, UG equipment, and used milling equipment such as a SAG Mill could

be sourced and would replace more expensive and lon g lead time expenses used in the PEA. As the

Project progresses, there will be continual options to explore using leased equipment and/or contract

mining to lessen the upfront investment needed depending on the market conditions as the project is

initiated. The Company will continue throughout the Feasibility study to evaluate all potential options

to increase the economics of the project.

• Mine Plan Optimization: Presently, the UG development costs in the PEA are based on contractor

rates for certain equipment and personnel. With the purchase of equipment and use of company

personnel, the overall UG development cost could be significantly reduced in the sustaining capital

section. Further optimization of open pit mining phases, along with the current infill drilling programs,

could help to reduce the stripping ratio in the initial years while providing optimized grade directly to

the mill in the initial years of production. In conjunction with optimized phase design, the PEA has

also elected to not use any low grade stockpile. Further optimization of mining could make use of a

low grade stockpile to provide an increased open pit head grade being fed to the mill prior to the

initiation of UG mining.

• Process Optimization : Further optimization of the gold processing plant could help to improve

economics by reducing operating costs and increasing gold recoveries. It has been recommended to

study the use of oxygen injection into the leaching circuit to both speed leaching times and reduce

cyanide consumption. A further advantage is the ability to operate the slurry leach circuit at a lower

pH that favours the carbon adsorption step and together with the accelerated leach kinetics can

allow a significant drop in leach tank volume requirements, significantly lowering capital costs.

The Company announced a detailed corporate update a nd project development strategy on March 1,

2017 to further advance the Company's Goliath Gold Project. The Company's key objectives for Goliath

and proposed timelines related to a Feasibility study and mine permits were provided in that report.

The Company will provide additional details related to Tailings Management and Closure process in

conjunction with the filing of the PEA on Sedar in April 2017.

Proposed Mining Plan

In a similar method to previous studies, the PEA proposes an initial open pit mining plan to take

advantage of mineralized material at surface. Revenues generated from open pit mining will be used in

the development of the underground operations. In an effort to optimize the mill head grade, the PEA

envisions that UG mine development will start immed iately in year one with the objective of creating

underground mill feed by year two. It has been proposed that once UG production is online the open pi t

production will decrease over an 8 year period to supplement the UG mill feed to the nameplate capacit y.

As proposed, the open pit will operate over an 8 year mine life and uses no significant stockpile from the

storage of low grade material. This will have the additional benefit of reduced re-handle costs for the low

grade stockpile that was proposed in previous studies.

Total gold production is estimated at 1,142,000 ounces of gold and 2,075,000 ounces of silver of which it

is proposed that 154,700 ounces of gold will be from the Open Pit and 987,300 ounces of gold will be

produced from the Underground. The PEA is based on an average milling rate of 875,000 tonnes per

year, or 2,500 tonnes per day with an average head grade of 3.81 g/t gold and 10.55 g/t silver.

Metallurgical and optimization studies continue to indicate high recoveries using a traditional Carbon in

Leach (CIL) circuit and estimated overall recovery of 95.5% for gold and 62.6% for silver.

Initial capital to fund construction is estimated at C$133.2 million with an additional C$132.5 million in

sustaining capital over the LOM primarily to fund the underground expansion. The main increases in the

capital costs since the 2012 PEA came from advanced engineering studies to support the mine permit

process and the major cost changes attributed to th e tailings facility, closure costs and open pit pre-

production costs. The total mill facility includes costs associated with a backfill plant for underground

production and the Company will make use of existing office, warehousing and electrical facilities onsite

to minimize capital costs needed for construction.

Advanced engineering studies also helped to revise operating cost estimates. The PEA has defined a

$18.15/tonne processing cost, $3.45/tonne for open pit ore mining, $3.30/tonne for open pit waste mini ng

and $77/tonne for underground mining costs. Underground development costs have been estimated at

$6,000/lateral metre and $4,500/lateral metre for contractor and owner rates, respectively, with a total of

14,725 total metres needed for capital development.

Metallurgy and Processing

A standard carbon-in-leach (CIL) circuit with gravity extraction is considered the base case for the

proposed processing facility. An average of 2,500 tonnes per day will be primary crushed with a jaw

crusher and then ground to the target leaching P80 of 106 microns using a single stage SAG mill and

classifying cyclones. A gravity circuit consisting of a scalping screen and centrifugal concentrator will be

fed from the cyclone feed distributor. The gravity concentrate will be batch treated in an intensive leach

reactor (ILR) with the pregnant solution treated by electrowinning. Cyclone overflow will pass through a

trash screen prior to entering the carbon in leach (CIL) circuit.

The PEA has provided for a 24 hour leaching residence time in the 6 tank CIL circuit with a cyanide

detoxification circuit to be used prior to discharge to the tailings facility. Average processing cost s have

been estimated at $18.15/tonne over the course of the mine life.

All metallurgical testing to date, which includes Teck Resource's previous 2,375 tonne bulk sample and

the most recent 420 kg representative sample, has shown extremely positive results for this proposed

circuit. Recoveries are estimated to be 95.5% for gold and 62.6% for silver.

Goliath LOM Production Profile

The attached chart provides an overview of the gold and silver production.

Pre-Production Capital and Sustaining Capital

C$M Initial Capital Sustaining Capital Total Capital

Processing Plant $90.7M $12.4M $103.1M

Tailings $11.1M $10.0M $21.1M

Open Pit Pre-Production $12.5M $0.0M $12.5M

Open Pit Equipment $17.0M $1.6M $18.6M

Underground $0.0M $96.3M $96.3M

2015 Mineral Resource Estimate

The following table summarizes the 2015 NI 43-101 M ineral Resource Estimate in the "Measured",

"Indicated" and "Inferred" Resource categories. The report is available on the company's website and on

www.sedar.com .

Mineral Resource Estimate Statement (1-8)

Category Cut -off

AuEq g/t

Tonnage Au

(g/t)

Contained

Au (oz)

Ag

(g/t)

Contained

Ag (oz)

AuEq

(g/t)

Contained

AuEq (oz)

Open Pit

Measured 0.35 1,015,000 1.90 62,100 7.8 256,000 2.00 65,200

Indicated 0.35 17,174,000 1.22 675,700 5.2 2,869,000 1.29 710,400

M+I 0.35 18,189,000 1.26 737,800 5.3 3,125,000 1.33 775,600

Inferred 0.35 1,351,000 0.99 42,800 4.3 186,000 1.04 45,000

Underground

Measured 1.90 103,000 7.32 24,200 23.1 76,000 7.60 25,100

Indicated 1.90 2,264,000 4.84 352,400 14.4 1,044,000 5.02 365,000

M+I 1.90 2,367,000 4.95 376,600 14.7 1,120,000 5.13 390,100

Inferred 1.90 2,120,000 4.22 287,300 10.9 743,000 4.35 296,300

Total

Measured 0.35&

1.90

1,117,000 2.40 86,300 9.2 332,000 2.51 90,300

Indicated 0.35&

1.90

19,437,000 1.65 1,028,100 6.3 3,913,000 1.72 1,075,500

M+I 0.35&

1.90

20,554,000 1.69 1,114,400 6.4 4,245,000 1.76 1,165,800

Inferred 0.35&

1.90

3,470,000 2.96 330,100 8.3 928,000 3.06 341,300

1. Mineral resources which are not mineral reserves do not have demonstrated economic

viability. The estimate of mineral resources may be materially affected by environmental,

permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.

2. The quantity and grade of reported Inferred resourc es in this estimation are uncertain in

nature and there has been insufficient exploration to define these Inferred resources as an

Indicated or Measured mineral resource and it is uncertain if further exploration will result in

upgrading them to an Indicated or Measured mineral resource category.

3. The mineral resources in this press release were estimated using the Canadian Institute of

Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and

Reserves, Definitions and Guidelines prepared by th e CIM Standing Committee on Reserve

Definitions and adopted by the CIM Council.

4. A gold price of US$1,397/oz and silver price of US$22.93/oz based on the April 30, 2015

three year trailing average prices and an exchange rate of US$1.06=Cdn$1.00 were utilized

in the AuEq cut-off grade calculations of 0.35 g/t AuEq for Open Pit and 1.90 g/t AuEq for

Underground mineral resources.

5. Open Pit mining costs were assumed at Cdn$5.00/t for mineralized material, Cdn$3.15/t for

waste rock and Cdn$2.00/t for overburden, while Und erground mining costs were assumed

at Cdn$70.00/t, with process costs of Cdn$13.81/t, G&A of Cdn$2.72/t, and process

recoveries of 95% for gold and 70% for silver.

6. The Au:Ag ratio used for AuEq was 82.68.

7. A bulk density model averaged 2.76 t/m 3 for mineralized material.

8. Totals in the table may not sum due to rounding.

Qualified Person

Technical information related to the PEA contained in this news release has been reviewed and approved

by Douglas Roy, M.A.Sc., P.Eng., an Associate Minin g Engineer with CSA Global, who is an independent

Qualified Person as defined by NI 43-101, with the ability and authority to verify the authenticity and

validity of this data. The PEA technical report will be filed on Sedar within 45 days. Technical infor mation

in the press release has also been reviewed and approved by Mark Wheeler, P. Eng., Director Projects,

who is a Qualified Person for the Goliath Gold Project under the definitions established by National

Instrument 43-101.

The 2015 Mineral Resource Estimate was prepared by Eugene Puritch, P.Eng., Antoine Yassa, P.Geo.,

and Yungang Wu, P.Geo. of P&E Mining Consultants Inc. of Brampton, Ontario, Independent Qualified

Persons ("QP"), as defined by National Instrument 43-101.

To view further details about the Goliath Gold Project, please visit the Company's website at

www.treasurymetals.com .

About Treasury Metals Inc.:

Treasury Metals Inc. is a gold focused exploration and development company with assets in Ontario,

Canada and is listed on the Toronto Stock Exchange ("TSX") under the symbol "TML". Treasury Metals

Inc.'s 100% owned Goliath Gold Project in northwestern Ontario is slated to become one of Canada's

next producing gold mines. With first-rate infrastructure currently in place and gold mineralization

extending to surface, Treasury Metals plans on the initial development of an open pit gold mine to fee d a

2,500 per day processing plant with subsequent underground operations in the latter years of the mine

life. Treasury Metals is currently in the mine perm it process and working towards completion of a

Feasibility Study on the Goliath Gold Project.

Follow us on Twitter @TreasuryMetals

Forward-looking Statements

This release includes certain statements that may be deemed to be "forward-looking statements". All

statements in this release, other than statements of historical facts, that address events or developm ents

that management of the Company expect, are forward- looking statements. Actual results or

developments may differ materially from those in forward-looking statements. Treasury Metals disclaims

any intention or obligation to update or revise any forward-looking statements, whether as a result of new

information, future events or otherwise, save and except as may be required by applicable securities

laws.

SOURCE Treasury Metals Inc.

To view the original version on PR Newswire, visit:

http://www.newswire.ca/en/releases/archive/March201 7/08/c4193.html

%SEDAR: 00027114E

For further information: Chris Stewart, President and CEO, T: 1.416.214.465 4,

[email protected]; Greg Ferron, Vice Pres ident, Corporate Development, T:

1.416.214.4654, [email protected]

CO: Treasury Metals Inc.

CNW 07:48e 08-MAR-17