Treasury Metals Announces Results from 2020 / 2021 Drilling Program at Goliath Gold Complex Program represents Treasury's first phase of exploration at Goldlund Deposit

Exploration Programs

Treasury Metals Announces Results from 2020 / 2021 Drilling Program

at Goliath Gold Complex

Program represents Treasury's first phase of exploration at Goldlund Deposit

TSX: TML OTCQX: TSRMF

Highlights:

Drill results focused on under-drilled areas of near surface Zones 2 and 3 at Goldlund Deposit

Drill Hole GL-20-037 returns

10.0m

at 2.23 g/t gold including

6.0m

at 2.99 g/t gold

Drill Hole GL-20-035 includes 1.41 g/t gold over

17.6m

within Zone 2

Maiden resource for Miller zone to be included in upcoming PEA for Goliath Gold Complex and included in preliminary mine plan

65km strike length of the Wabigoon Greenstone belt hosts several prospective exploration targets with historical gold anomalies and

showings

Continued aggressive exploration program planned post-PEA announcement with second drill to be mobilized at Goliath

TORONTO

,

Jan. 25, 2021

/CNW/ -

Treasury Metals Inc.

(TSX: TML) ("

Treasury

" or the "

Company

") is pleased to announce the initial results from its

10,000m

diamond drilling program at the Goldlund Gold Deposit ("Goldlund") within the larger 100% owned Goliath Gold Complex (the "Project" or

"GGC"), which includes the Goliath and Goldlund deposits and the Miller prospect along a prospective 65km trend in

Northwestern Ontario

.

The exploration program has been designed to ensure the safety of the workforce and surrounding communities during the COVID-19 pandemic and

incorporates enhanced operating protocols that are consistent with local health guidance.

The drilling represents Treasury's first phase of active exploration at Goldlund. All holes are targeting extensions of Zones 2 and 3 in the near surface

area directly to the northeast of the targeted main zone open pit (Zone 1). Resource evaluation work undertaken as part of the ongoing Preliminary

Economic Assessment (the "2021 PEA") at GGC have demonstrated the potential for additional conversion of Inferred Resources into Indicated

Resources within an area contained within the anticipated pit area at Goldlund. Importantly, geological interpretation shows that this area has potential

to improve continuity within Zones 2 and 3 and potentially improve resources contained within the conceptual pit shell.

Drilling to date has found notable intersections across extended intervals of mineralization above the anticipated open pit mineable cut-off grade, including

hole GL-20-037 which includes 2.23 g/t gold over

10.0m

within Zone 3, including 2.99 g/t gold over

6.0m

, and GL-20-035 which includes 1.41 g/t gold

over

17.6m

within Zone 2.

"We are pleased to be able to share the initial results from our first drill program at Goldlund. The results announced today help to fill in under-drilled

areas of Zones 2 and 3 at Goldlund and are anticipated to improve continuity of the deposit," said

Jeremy Wyeth

, President and CEO of Treasury

Metals.

"Looking ahead, we anticipate more results from this initial drill program later this quarter and the inclusion of a maiden resource for the Miller prospect

as part of our PEA in early February. Our land package on the Wabigoon Greenstone belt exceeds 300 square kilometres and the majority of the 65

kilometre strike length is either under- or un-explored. More details for an expanded 2021 drill program will be included as part of the PEA announcement

where we will identify new targets and discuss our plans to mobilize a second drill at Goliath," added Mr. Wyeth.

Table 1: Selected Significant Intercepts in Zone 2 and Zone 3 from 2020 / 2021 Goldlund Drilling

Hole ID

Zone

From

(m)

To (m)

Length

(m)

Au (g/t)

GL-20-035

2

167.00

184.60

17.60

1.41

including

177.10

183.63

6.53

2.33

including

182.60

183.63

1.03

8.16

GL-20-037

3

82.00

92.00

10.00

2.23

including

86.00

92.00

6.00

2.99

including

87.50

88.80

1.30

6.86

and including

91.00

92.00

1.00

6.83

3

110.00

114.00

4.00

4.19

Including

110.00

111.00

1.00

15.90

GL-20-038

2

67.00

83.00

16.00

1.42

including

77.00

78.00

1.00

11.90

GL-20-042

3

69.00

71.51

2.51

5.00

including

70.00

71.00

1.00

10.60

Note: Reported intervals are drilled core lengths and do not indicate true widths. For duplicate samples, an average of the two gold assays are used to calculate the intersection grade. All grades are un-capped.

While within the anticipated area of the Goldlund open pit, the drill holes announced today will not be included in the resources used in the 2021 PEA but

will contribute to future work as Treasury proceeds to advanced studies. The holes have the potential to both extend the planned open pit and add

ounces internal to the pit if continuity of the Zones can be confirmed.

Figure 1

below shows the location of released diamond drill holes and those

pending results at Goldlund.

Figure 1: Goldlund Plan Map showing 2020 / 2021 Drill Program Hole Locations

Figure 1: Goldlund Plan Map showing 2020 / 2021 Drill Program Hole Locations (CNW Group/Treasury Metals Inc.)

See

Table 2

below which details the collar locations for the drill holes with completed assays.

Table 2: Drill hole collar locations

Hole ID

Azimuth

Dip

Northing

UTM

Easting

UTM

Elevation

(masl)

Hole Depth

(m)

GL-20-035

333

-48

5528083

547830

413

201

GL-20-036

341

-52

5528129

547898

413

126

GL-20-037

335

-50

5528166

547925

413.5

177

GL-20-038

332

-48

5528167

547840

414

126

GL-20-040

341

-47

5528178

547942

414.5

180

GL-20-042

340

-48

5528230

547984

414

177

GL-20-044

343

-53

5528078

547803

413

210

Complete results from the 2020/2021 drill program at Goldlund can be found

here

on Treasury's website.

QA / QC

The Company has implemented a quality assurance and quality control (QA/QC) program to ensure sampling and analysis of all exploration work is

conducted in accordance with the CIM Exploration Best Practices Guidelines. The drill core is sawn in half with one-half of the core sample dispatched to

Activation Laboratories Ltd. facility located in

Dryden, Ontario

. The other half of the core is retained for future assay verification and/or metallurgical

testing. Other QA/QC procedures include the insertion of blanks and Canadian Reference Standards for every tenth sample in the sample stream. A

quarter core duplicate is assayed every 20

th

sample. The laboratory has its own QA/QC protocols running standards and blanks with duplicate samples

in each batch stream. Additional checks are routinely run on anomalous values including gravimetric analysis and pulp metallic screen fire assays. Gold

analysis is conducted by lead collection, fire assay with atomic absorption and/or gravimetric finish on a 50-gram sample. Check assays are conducted

at a secondary ISO certified laboratory (in this case AGAT Laboratories located in

Mississauga, Ontario

) following the completion of a program.

Qualified

Persons

Mark Wheeler

, P.Eng., Director, Projects, and

Adam Larsen

, Exploration Manager, are both considered as a "Qualified Person" for the purposes of

National Instrument 43-101 Standards of Disclosure for Mineral Projects ("

NI 43-101

"), and have reviewed and approved the scientific and technical

disclosure contained in this news release on behalf of Treasury.

Twitter

@TreasuryMetals

About Treasury Metals Inc.

Treasury Metals Inc. is a gold focused company with assets in

Canada

. Treasury's Goliath Gold Complex, which includes the Goliath and Goldlund

deposits and the Miller prospect, is located in

Northwestern Ontario

. The deposits benefit substantially from excellent access to the Trans-Canada

Highway, related power and rail infrastructure, and close proximity to several communities including

Dryden, Ontario

. The Company also owns several

other projects throughout

Canada

, including the Lara Polymetallic Project, Weebigee-Sandy Lake Gold Project JV, and grassroots gold exploration

property Gold Rock.

To view further details about Treasury, please visit the Company's website at

www.treasurymetals.com

.

Forward-Looking Statements

This release includes certain statements that may be deemed to be "forward-looking statements". All statements in this release, other than statements

of historical facts, that address events or developments that management of the Company expect, are forward-looking statements. Actual results or

developments may differ materially from those in forward-looking statements. Treasury Metals disclaims any intention or obligation to update or revise

any forward-looking statements, whether as a result of new information, future events or otherwise, save and except as may be required by applicable

securities laws.

View original content to download multimedia:

http://www.prnewswire.com/news-releases/treasury-metals-announces-results-from-2020--2021-drilling-program-at-goliath-gold-complex-301213829.html

SOURCE

Treasury Metals Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/January2021/25/c2382.html

%SEDAR: 00027114E

For further information:

Jeremy Wyeth, President & CEO, T: +1 416 214 4654; Nicholas Van Dyk, Vincic Advisors, T: +1 604 364 5752, Email:

[email protected]

CO: Treasury Metals Inc.

CNW 07:00e 25-JAN-21