Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NCX.V ·

NorthIsle Copper and Gold Inc. | TSX.V: NCX

Corporate Updates

NorthIsle Copper and Gold Inc. | TSX.V: NCX

15th Floor – 1040 West Georgia Street | Vancouver, BC | V6E 4H1

www.northisle.ca | [email protected] | Tel: 604-638-2515

September 13, 2017 TSX Venture Exchange symbol: NCX

NORTHISLE COPPER AND GOLD INC. ANNOUNCES

POSITIVE PEA BASE CASE RESULTS:

$550.4 million After-Tax NPV (8%) and 14.3% IRR

VANCOUVER, B.C. – NorthIsle Copper and Gold Inc. (“NorthIsle” or the “Company”) is pleased

to announce the results of its Preliminary Economic Assessment (“PEA”), prepared by M3

Engineering & Technology Corp. , for its 100% owned North Island Copper and Gold

Project located in northern Vancouver Island British Columbia (“Project”). The results of

the PEA demonstrate the potential techn ical and economic viability of the P roject

constructed as an open-pit mine, with a concentrator processing nominally 75,000 tonnes

per day.

PEA HIGHLIGHTS:

• After tax NPV 8% of CAD $550.4 million, 14.3% IRR, 22-year mine life

• Life of Mine (LOM) metal production of 1.8 billion pounds of copper, 1.7 million ounces of

gold and 55 million pounds of molybdenum

• Annual production of 82 million pounds of copper, 79 thousand ounces of gold and 3

million pounds of molybdenum

• Initial capital costs of CAD $1.34 billion plus sustaining capital of $139 million

• Direct cash cost of production per pound of copper net of gold, molybdenum and pyrite

concentrate is CAD $1.17

“We are very pleased with the results of our maiden PEA ,” said Jack McC lintock, President of

NorthIsle. “This PEA shows the Project can be built and operated with excellent returns based on

conservative metal prices. There are a number of areas of potential impro vements that could

improve the Project further including advanced metallurgical studies to improve metal recoveries,

evaluating higher production rates, evaluating the use of the Island Copper pit for tailings disposal

and evaluating the potential for rhenium credits in the molybdenum concentrate . There remains

excellent potential to add tonnes to our resource base. Drilling this summer demo nstrated that

our Hushamu deposit remains open for a significant expansion of its resource. In addition, there

are several partially explored copper – gold exploration targets, any one of which could contribute

significantly to the resource base of the Project.”

PEA BASE CASE ECONOMIC RESULTS

Parameter Unit Base Case

Capital Cost CAD$ $1,344 million

Sustaining Capital CAD$ $139 million

NSR CAD$/ore tonne $17.61

Average Op Cost/tonne CAD$ $8.66

After tax Net Revenue CAD$ $2,349 million

After tax NPV 8% CAD$ $550 million

After tax IRR and pay back 14.3% and 5.1 years

Metal Price Cu US$ per pound $3.10

Au US$ per ounce $1,300

Mo US$ per pound $9.00

Pyrite concentrate US$ per tonne $86

Exchange rate US$ / CAD$ 0.75

PEA SUMMARY PRODUCTION STATISTICS

Category Units LOM

Tonnes Milled Mt 600

Average grade Cu % 0.18

Au gpt 0.24

Mo % 0.008

Tonnes produced Py MT 14.1

Throughput tpy 75,000

Mine Life years 22

Net Cash Cost* CAD$ $1.17

*Net direct cash costs that represent the cash cost incurred at each processing stage from mining through

to recoverable metal delivered to market less net by -product credits. Direct cash costs cover mining, ore

freight and milling costs, mine site administration and general expenses, concentrate freight, smelting and

smelter general and administrative costs, marketing costs (freight and selling).

NorthIsle Copper and Gold Inc. | TSX.V: NCX

15th Floor – 1040 West Georgia Street | Vancouver, BC | V6E 4H1

www.northisle.ca | [email protected] | Tel: 604-638-2515

INITIAL CAPITAL EXPENDITURES (CAD$ MILLIONS)

Mine $149.2

Pre-Production $125.6

Process $1,024.9

Owner’s Cost $44.5

Total $1,344.2

OPERATING COSTS

The mine operating costs were calculated to average CAD$ 2.02 per tonne moved.

Area Unit Cost (CAD$/t moved)

Drilling 0.13

Blasting 0.27

Loading 0.27

Hauling 0.67

Support 0.54

Mine General 0.14

Total Cost 2.02

The process operating costs were calculated to average CAD$ 4.88/tonne ore.

Area CAD$/tonne ore

Salaries & Wages 0.54

Power 1.55

Liners 0.34

Grinding Media 1.06

Reagents 0.85

Maintenance Parts & Repairs 0.44

Supplies & Services 0.10

Total Cost 4.88

NorthIsle Copper and Gold Inc. | TSX.V: NCX

15th Floor – 1040 West Georgia Street | Vancouver, BC | V6E 4H1

www.northisle.ca | [email protected] | Tel: 604-638-2515

MINING

Preliminary mine designs have been developed for Red Dog and Hushamu deposits based upon

Indicated and Inferred Resources. Resource models were imported to Minesight® mine planning

software where a Lerchs Grossman algorithm was applied to an NSR model to determine possible

pit limits.

The mine plan was developed to mine Red Dog concurrently with Hushamu in the early years of

the mine life until Red Dog Resources were depleted. The assumed processing rate is 75,000 t/d.

The overall mining rate peaks at 64 million t/a in the initial years averaging 54 million t/a over the

first 12 years of the total mine life of 22 years. The effective strip ratio after stockpile reclaim was

0.72:1.

The mine will be a conventional truck and shovel o peration with electrified pit operations at

Hushamu. Waste rock will be placed during construction and operation within the Tailings

Management Facility (TMF). A low-grade stockpile will be located at the pit rim on the northwest

side of Hushamu. An overburden stockpile will be located adjacent to the low-grade stockpile for

use in reclamation of the TMF at the end of the mine life.

The total resources processed in the conceptual mine plan are shown in the following Tables.

Mineral Resources Included in the Mine Plan

Indicated Resources ROM t x 1000 Cu % Au g/t Mo %

Hushamu Starter Pit 80,097.0 0.24 0.27 0.007

Hushamu Phase 1 Expansion 97,217.0 0.20 0.18 0.007

Hushamu Phase 1.5 Expansion 119,509.0 0.18 0.28 0.011

Hushamu Phase 2 Expansion 109,134.0 0.17 0.25 0.008

Red Dog 50,549.0 0.22 0.32 0.005

Total 456,506.0 0.20 0.25 0.008

Inferred Resources ROM t x 1000 Cu % Au g/t Mo %

Hushamu Starter Pit 2,530.0 0.12 0.15 0.015

Hushamu Phase 1 Expansion 12,802.0 0.13 0.12 0.010

Hushamu Phase 1.5 Expansion 40,554.0 0.14 0.22 0.012

Hushamu Phase 2 Expansion 84,859.0 0.14 0.21 0.008

Red Dog 2,152.0 0.17 0.27 0.003

Total 142,897.0 0.14 0.20 0.009

NorthIsle Copper and Gold Inc. | TSX.V: NCX

15th Floor – 1040 West Georgia Street | Vancouver, BC | V6E 4H1

www.northisle.ca | [email protected] | Tel: 604-638-2515

INFRASTRUCTURE

The nearby town of Port Hardy is a main distribution centre for the north end of Vancouver Island.

It has an airport with 3 daily flights to Vancouver, a hospital, schools and a college. All parts of

the North Island Project are accessible from Port Hardy through a network of logging roads.

A marine load out structure and a 138 KVA BC Hydro substation exist at the reclaimed Island

Copper Mine, approximately 27 km from the North Island mine site. One of BC’s largest wind farm

complexes is situated adjacent to the northwest end of the property and the 138 KV power line

connecting the wind farm to the main BC power grid passes immediately north of the North Island

Project.

ECONOMIC ANALYSIS

Economic evaluations were generated incorporating forecasts for metal prices using the long

term (Base Case), the SEC price and Spot Price. The spot price case is from September 6,

2017.

Parameter Unit Base Case SEC Spot Price

Copper US$ per lb $3.10 $2.50 3.12

Gold US$ per oz $1300 $1,213.12 1,333.10

Molybdenum US$ per lb $9.00 $7.03 7.14

Pyrite US$ per tonne $86 $86 $86

Exchange rate 0.75 0.75 0.75

Economic Result (After tax)

Net Revenue CAD$ M 2,349 1,339 2,342

NPV 8% CAD$ M 550 34 549

IRR % 14.3 8.4 14.3

Pay back Years 5.1 7.9 5.0

The Preliminary Economic Assessment (“PEA”) is preliminary in nature and includes inferred mineral resources that are considered

too speculative geologically to have the economic considerations applied to them that would allow them to be categorized as mineral

reserves and there is no certainty that the preliminary economic assessment will be realized. Mineral resources that are not mineral

reserves do not have demonstrated economic viability.

OPPORTUNITIES TO ENHANCE VALUE

The Project opportunities include advanced metallurgical studies to improve copper , gold

and molybdenum recoveries from current li fe of mine averages of 77.5% for copper ,

38.4% for gold (in the copper concentrate) and 59.5% for molybdenum; optimize primary

and rougher concentrate regrind sizes; determine the potential for rhenium credits in the

molybdenum concentrate; evaluate the use of the Island Copper pit for tailings disposal

in conjunction with a waste storage site to reduce overall CAPEX, OPEX, and societal

risk; and to evaluate higher production rates of 85 to 90 kptd. In addition, there are several

partially explored copper – gold exploration targets, any one of which could contribute

significantly to the resource base of the Project.

NorthIsle Copper and Gold Inc. | TSX.V: NCX

15th Floor – 1040 West Georgia Street | Vancouver, BC | V6E 4H1

www.northisle.ca | [email protected] | Tel: 604-638-2515

TECHNICAL REPORT

A National Instrument 43-101 (NI 43-101) compliant technical report entitled "North Island Project

PEA" prepared by the following Qualified Persons will be filed by the Company within 45 days of

this release on www.sedar.com:

• Laurie Tahija, of M3 Engineering – Recovery Methods

• Daniel Roth, P.Eng of M3 Engineering – Project Infrastructure; Capital and Operating Costs;

Economic Analysis

• Brian Game , P. Geo. – Principal of GeoMinEx Consultants – Geology, Exploration and

Environmental

• Thomas W. Shouldice, P.Eng of TS Technical Services Ltd. – Mineral Processing and

Metallurgical Testing

• Phil Burt, P. Geo. – CEO of Burt Consulting Services – Mineral Resource Estimates

• John Nilsson, P. Eng – Mining Methods

• Ben Wickland, P.Eng of Golder Associates Ltd. – Tailing Infrastructure

The Qualified Persons have reviewed and approved the scientific, technical, and economic

information obtained in this news release.

COMPANY OVERVIEW

NorthIsle Copper and Gold Inc. is a Vancouver based junior resource company committed to the

development of the North Island Project on Northern Vancouver Island. The North Island Project

is a 33,149 -hectare block of mineral titles 100% owned by NorthIsle stretching 50 kilometres

northwest from the now closed Island Copper Mine of BHP Billiton, which is located 10 km south

of Port Hardy. The North Island Project contains the Hushamu and Red Dog Deposits and five

other partially explored copper-gold porphyry occurrences.

On behalf of NorthIsle Copper and Gold Inc.

“John McClintock”

John McClintock

President, CEO and Director

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this news release.

This news release contains forward-looking statements. These forward-looking statements are based upon the reasonable beliefs of

Northisle and its management as of the date of this news release; however, forward-looking statements involve risks and uncertainties

and are based upon factors that may change and assumptions that may prove, with the passage of time, to be incorrect as a result of

exploration and other risk factors associated with mineral explor ation and development that are beyond the control of Northisle.

Accordingly, undue reliance should not be placed upon such statements. If factors materially change or assumptions are materi ally

incorrect, the actual results, performance or achievements of Northisle may be materially different from any future results,

performances or achievements expressed or implied by such forward-looking statements. Northisle does not undertake any obligation

to update or revise any forward -looking statements to reflect n ew information, future events or otherwise, excep t as required by

applicable law.