Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NCP.V ·

Nickel Creek Platinum Announces Positive PFS for its Nickel Shäw Project

Economic Studies

Nickel Creek Platinum Announces Positive PFS for its Nickel

Shäw Project

TORONTO, August 24, 2023 - Nickel Creek Platinum Corp. (TSX: NCP) ( OTCQB: NCPCF)

("Nickel Creek" or the "Company") is pleased to announce the results of a positive pre-feasibility

study (“PFS”) at its 100% -owned Nickel Shäw Project (the “Project”) located in the Yukon,

Canada. The PFS has been prepared by AGP Consultants Inc. (“AGP”). The estimated Project

after-tax net present value (“NPV”) at a 5% discount rate is $143 million with an after-tax internal

rate of return (“IRR”) of 5.8%. All dollars are expressed in Canadian dollars unless otherwise

stated.

Stuart Harshaw, President and CEO of Nickel Creek commented: "The PFS is an important

milestone in realizing the opportunity the Nickel Shäw Project represents in the critical mineral

space where it can provide nickel and copper to take advantage of the strong nickel market for

EV batteries. The sensitivity to energy costs illustrates how working with the different levels of

government can lead to a significant improvement in value, especially when combined with the

previously announced intention of the Federal government to provide a tax incentive for critical

mineral projects such as Nickel Shäw. Moving forward, our focus will be to continue to add value

to the project through work on identified key economic areas of opportunity and continued mineral

exploration success while advancing towards a feasibility study.”

Project PFS Highlights

• $143 million after-tax NPV using a 5% discount rate and an IRR of 5.8% at the following

commodity prices : nickel - US$11.00/pound (“lb”); c opper – US$4.00/lb; palladium –

US$2,100/troy ounce (“troy oz”); platinum – US$1,000/troy oz; cobalt – US$23/lb; and gold –

US$1,800/troy oz, each using a 0.75 Canadian to US exchange rate.

• Life of mine (“LOM”) after-tax cash flow of approximately $1.7 billion with an after-tax payback

period of 12.7 years.

• Pre-production capital cost of approximately $1.7 billion, with a construction period of 3.0

years.

Project Opportunities

• If paying Yukon grid rates of $0.11/kWhr, the after-tax NPV at a 5% discount rate increases

by $324 million to $467 million (see NPV sensitivities section below for additional information).

• The Company’s after-tax NPV at a 5% discount rate increases from $143 million to $336

million if the Canadian tax incentive for critical mineral companies is enacted (see Investment

Tax Credit for Clean Technology Manufacturing section below for additional information).

• The Company plans to further investigate the opportunity of carbon tax offsets associated with

carbon sequestration in the tailings facility with ongoing testwork and analysis.

Mineral Resource

On June 1, 2023, the Company announced an updated mineral resource estimate with an

effective date of April 3, 2023:

Notes:

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Summation errors may occur due to rounding.

Effective Date is April 3, 2023.

Mineral Resources amenable to open pit extraction are reported within an optimized containing shell.

Average grade calculations on this table are impacted by rounding.

Tonnages are reported in units of 1,000 metric tonnes (Ktonnes).

Contained Base Metal reported in units of 1,000,000 lbs, M Lbs.

Contained Precious Metal reported in units of 1,000 troy ounces, K Ozs.

Metal Prices for Resource Determination in US$

Nickel: $12.10/lb; Copper: $4.45/lb; Cobalt: $25.30/lb; Palladium: $2,415/troy oz; Platinum: $1,150/troy oz; Gold: $2,015/troy oz.

Net Smelter Return (NSR) cut-off grades range from $17.30 to $17.61 Canadian dollars depending on Bulk Con and Split Con

Mining costs, vary by bench, separately for ore and waste:

Base waste mining cost @1330m = C$2.26/t, 10 m bench incremental cost above = C$0.004/t, 10 m bench incremental cost

below = C$0.02/t

Base ore mining cost @1330m = C$1.99/t, 10 m bench incremental cost above = C$0.019/t, 10 m bench incremental cost below

= C$0.015/t

Process and G&A costs: Bulk con – C$17.30/t; Split con = C$17.61/t

Calculated process recoveries by concentrate type:

Ni Cu Co Pd Pt Au

Bulk con: Eq1 Eq2 57.0% 54.0% 47.8% 74.4%

Cu con: Eq3 Eq4 3.36% 3.19% 0.91% 23.58%

Ni con: Eq5 Eq6 53.64% 50.81% 46.89% 50.82%

where: Eq1 = Ni recovery to Bulk Con = MIN (23.21*LN(X)+30.362,88)

where X = (%S-%Cu)/%Ni Capped at 12.0%

Eq2 = Cu recovery to Bulk Con = ((Cu-0.06)/Cu)) *100, Constant tail at 0.06% Cu

Eq3 = Ni recovery to Cu Con=Ni recovery to achieve 25.6% Cu and 1.1% Ni grades in Cu Con

Eq4 = Cu recovery to Cu Con = Cu recovery to Bulk Con * 0.623

Eq5 = Ni recovery to Bulk Con – Ni recovery to Cu Con

Eq6 = Cu recovery to Bulk Con – Cu recovery to Cu Con

Capping of grades varies based on lithology for each metal.

The density is assigned based on lithology and varies between 2.76 g/cm3 and 3.38 g/cm3.

Ni Cu Co Pd Pt Au Mg S

Class Ktonnes % % % g/t g/t g/t % %

Measured 122,363 0.25 0.15 0.014 0.23 0.24 0.05 16.03 0.78

Indicated 314,332 0.26 0.13 0.014 0.24 0.22 0.04 17.26 0.64

Total M+I 436,695 0.26 0.13 0.014 0.23 0.22 0.04 16.92 0.68

Inferred 114,016 0.27 0.13 0.015 0.25 0.20 0.04 17.46 0.69

Ni Cu Co Pd Pt Au

Class Ktonnes M Lbs M Lbs M Lbs k Ozs k Ozs k Ozs

Measured 122,363 679 411 38 905 944 184

Indicated 314,332 1,792 871 99 2,385 2,197 361

Total M+I 436,695 2,471 1,281 137 3,290 3,141 545

Inferred 114,016 668 339 37 916 733 128

Metal Grades

Contained Metal

Project Description

The Company’s flagship asset is its 100%-owned Nickel Shäw Ni-Cu-Co-PGM Project, located in

southwestern Yukon, Canada. The Nickel Shäw Project contains the Company’s core Ni-Cu-Co-

PGM Wellgreen deposit, as well as the Arch, Burwash, Formula, Musk and Quil l claims. The

Wellgreen deposit is a polymetallic deposit with mineralization that includes the significant co-

occurrence of nickel, copper, cobalt, platinum group metals (“PGMs”) and gold.

The Nickel Shäw property contains an extensive Ni -Cu-Co-PGM mineralized system hosted by

mafic/ultramafic intrusions related to Triassic -age flood basalts . With over 2.4 billion pounds of

nickel, 1.2 billion pounds of copper, 6.9 million ounces of PGMs and 137 million pounds of cobalt

in the measured and indicated mineral resource categories, Nickel Shäw is one of the largest

undeveloped nickel projects in North America not controlled by a major mining company.

The PFS contemplates that the Nickel Shäw open pit would be mined using conventional open

pit methods, with a LOM of over 19 years. From the open pit the ore would be trucked to a primary

crusher located adjacent to the pit and conveyed out of the valley t o a concentrator designed to

process 45,000 tonnes per day (“tpd”) of ore. The ore would be fed into a conventional Ni -Cu-

PGM flotation concentrator designed to produce a bulk Ni-Cu-PGM concentrate “Bulk conc” or

alternatively into split concentrates. The split concentrates would be a Ni concentrate “Ni conc”

and a Cu concentrate “Cu conc”, as economics dictate. Average annual LO M concentrates

production (“dmt”) is expected to be 103,100 dmt of Bulk conc, 95,000 dmt of Ni conc and 19,600

of dmt Cu conc. Total LOM payable metal production includes the following:

• 614.3M lbs nickel;

• 281.5M lbs copper;

• 21.5 M lbs cobalt;

• 626,500 troy ounces platinum;

• 743,400 troy ounces palladium; and

• 174,400 troy ounces gold.

The tailings would be stored in a tailings storage facility adjacent to the concentrator. Concentrate

would be transported by truck 480 km to the Port of Skagway Ore Terminal. Power will be primarily

sourced from a liquified natural gas (“LNG”) power plant.

Social & Environmental

The Nickel Shäw Project lies within the Kluane First Nation (“KFN”) core area as defined under

the Umbrella Final Agreement between the Government of Canada, Government of Yukon and

the Council of Yukon First Nations. Effective August 1, 2012, an Exploration Cooperation

Agreement was signed between the KFN and the Company. The KFN and the government of the

Yukon Territory have provided very good support for the Nickel Shäw Project.

Ultramafic rocks from the project (in the form of tailings and waste rock) are being assessed for

their ability to capture and store carbon. Test work conducted in 2022 confirmed the presence of

brucite (a magnesium-rich mineral known to react quickly with CO2 in air) in a subset of samples.

On a mass basis, from the ac hieved reactivity in the testwork, this may enable maximum

sequestration of 2.1 kt CO2 per Mt tailings. The C ompany is evaluating further work which will

include the creation of a mineralogy model based on the project’s geochemical database to

assess the s patial distribution of rocks within the Wellgreen deposit that have high potential to

sequester carbon (see news release dated December 15, 2022 for additional details).

Summary of PFS Results

Pre-Tax NPV (5%), IRR $547 million, 7.7%

After-Tax NPV (5%), IRR $143 million, 5.8%

Undiscounted After-Tax Cash Flow (LOM) $1.65 billion

After-Tax Payback Period 12.7 years

Life of Mine (LOM) 19.1 years

Capital Cost

- Initial

- Sustaining

- T otal LOM

$1.7 billion

$0.6 billion

$2.3 billion

Operating Cost $30.22 /mt milled

Mill Throughput 45,000 tpd

Initial 5 Year Annual Average Metal

Production

- Nickel

- Copper

- Cobalt

- Platinum

- Palladium

- Gold

29.1 M lbs

9.1 M lbs

1.1 M lbs

27,400 troy oz

36,200 troy oz

7,700 troy oz

Life of Mine Strip Ratio (W:O) 1.93

Based on the assumed commodity prices noted above, the LOM revenue by metal is as follows:

nickel – 62%; palladium – 14%; copper – 10%; platinum 6%; cobalt – 5% and gold – 3%.

NPV Sensitivities

The discount rate sensitivity is as follows:

Discount Rate After-tax NPV

0% $1.7 billion

5% - base case $143 million

10% ($459) million

Sensitivity to Nickel and Copper Prices

The after-tax NPV ($Million’s) at a 5% discount rate:

Nickel Price (US$)

Copper (US$) $8.00 $9.00 $10.00 $11.00 $12.00 $13.00 $14.00

$ 3.00 (1,003) (633) (306) 14 325 628 925

$ 3.25 (961) (599) (273) 47 357 658 955

$ 3.50 (918) (566) (240) 79 388 689 985

$ 3.75 (876) (532) (207) 111 419 720 1,015

$ 4.00 (834) (498) (174) 143 450 751 1,045

$ 4.25 (796) (465) (141) 175 481 781 1,075

$ 4.50 (762) (431) (108) 207 512 811 1,105

Sensitivity to Energy Power Costs

The pre-tax and after-tax NPV ($Million’s) at a 5% discount rate:

Power Cost ($kWhr)

Base

case

$0.09 $0.11 $0.13 $0.15 $0.17 $0.194 $0.21

Pre-tax NPV

($Million's) 1,106 998 891 784 676 547 461

After-tax NPV

($Million's) 543 467 391 314 237 143 80

Pre-tax IRR 10.4% 9.9% 9.4% 8.9% 8.4% 7.7% 7.3%

After-tax IRR 8.2% 7.7% 7.3% 6.8% 6.4% 5.8% 5.5%

Investment Tax Credit for Clean Technology Manufacturing

The Canadian 2023 federal budget proposed the introduction of a 30% refundable investment tax

credit for investments in eligible property associated with eligible activities for clean technology

manufacturing and processing, as well as critical mineral extraction and proces sing (the “Clean

ITC”). The Clean ITC would apply to investments in certain depreciable property that is used all

or substantially all for eligible activities. This would generally include machinery and equipment,

including certain industrial vehicles and related control systems used in manufacturing,

processing or critical mineral extraction. A portion of the Clean ITC would be recovered if eligible

property is subject to a change in use or sold within a certain period of time.

As of this date, there are no specific details regarding the proposed Clean ITC and has not been

legislated. Based on assumptions on the capital that could be eligible for the ITC, if the Company

was able to utilize the 30% Clean ITC, the Company estimates that the after-tax NPV for the

Project at a 5% discount rate would improve from $143 million to $336 million and the after -tax

IRR would improve from 5.8% to 7.2%.

CAPEX and OPEX

The initial capital expenditure contemplated in the PFS , to be incurred over the three-year pre-

production period of the Project, amounts to approximately $1.7 billion, with the sustaining capital

over the remainder of LOM amounts to approximately $0.6 billion. The LOM capital expenditure

is summarized as follows:

Capital ($Million’s)

Pre-Production Sustaining Total LOM

Open Pit 399 205 604

Processing 510 5 515

Infrastructure 353 258 611

Indirects 245 58 303

Environmental - 52 52

Contingency 180 60 240

Total 1,687 638 2,325

Operating Costs

The LOM operating costs are summarized as follows:

$/mt Milled

Processing 17.32

Mining 7.30

G&A 2.43

Sub-total 27.05

Concentrate Trucking 2.34

Carbon Tax 0.83

Total 30.22

Future Opportunities and Value Enhancements

The PFS also identified a number of potential optimizations to the Project. These include:

• Working with energy providers and Yukon government and other stakeholders on an energy

strategy to reduce the costs for the project;

• Additional metallurgical testwork to improve overall recoveries of all payable metals where a

1% recovery improvement represents approximately an after-tax $111 M improvement to the

NPV at a 5% discount rate; and

• Continue drilling on the Arch target to define the potential resource w hich could provide the

opportunity for an early project higher grade feed that may improve overall financial results.

About Nickel Creek Platinum Corp.

Nickel Creek Platinum Corp. (TSX: NCP; OTCQB: NCPCF) is a Canadian mining exploration and

development company advancing its 100% -owned Nickel Shäw Project (“Project”). The Project

has exceptional access to infrastructure, located three hours west of Whitehorse via the paved

Alaska Highway, which further offers year -round access to deep-sea shipping ports in southern

Alaska.

The Company is led by a management team with a proven track record of successful discovery,

development, financing and operation of large-scale projects. Our vision is to create value for our

shareholders by becoming a leading North American nickel, copper, cobalt and PGM producer.

Qualified Persons

The PFS was overseen by AGP and the technical information disclosed in this news release was

reviewed and approved by Gordon Zurowski of AGP. Mr. Zurowski is a " qualified person" as

defined in NI 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”) and an

independent consultant to the Company. The scientific and technical information disclosed in this

news release in relation to metallurgical testing, including with respect to 2022-23 variability

testwork, was reviewed and approved by Gordon Marrs, P. Eng., of XPS who is a " qualified

person" as defined in NI 43-101 and an independent consultant to the Company.

All other scientific and technical information disclosed in this news release was reviewed and

approved by Cameron Bell , Nickel Creek's Geological Consultant and a " qualified person" as

defined in NI 43-101. Please see the technical report (September 2018) filed under the Company's

profile at www.sedar.com, for a description of the Company's data verification and QA/QC

procedures.

Cautionary Note Regarding Forward-Looking Information

This news release includes certain information that may be deemed "forward-looking information".

Forward-looking information can generally be identified by the use of forward-looking terminology

such as "may", "will", "expect", "intend", "believe", "continue", "plans" or similar terminology, or

negative connotations thereof. All information i n this release, other than information of historical

facts, including, without limitation, regarding the results of technical test work, the estimated

mineral resource, the prospect of any future potential economic viability of the Project, future

commodity prices and the potential for them to improve, that a feasibility study will ever be

commenced and completed, the potential to identify additional mineralization beyond the known

resource, timing of further work on the Project, future demand for nickel and copper concentrates,

future demand for battery products, statements concerning the availability and impact of the Clean

ITC, the ability of the Company to identify additional opportunities to create shareholder value,

and general future plans and objectives for the Company and the Project, are forward-looking

information that involve various risks and uncertainties. Although the Company believes that the

expectations expressed in such forward-looking information are based on reasonable

assumptions, such expectations are not guarantees of future performance and actual results or

developments may differ materially from those in the forward-looking information.

This news release also contains references to estimates of mineral resources. The estimation of

mineral resources is inherently uncertain and involves subjective judgments about many relevant

factors. Mineral resources that are not mineral reserves do not have demonstrated economic

viability. The accuracy of any such estimates is a function of the quantity and quality of available

data, and of the assumptions made and judgments used in engineering and geological

interpretation, which may prove to be unreliable and depend, to a certain extent, upon the analysis

of drilling results and statistical inferences that may ultimately prove to be inaccurate. Mineral

resource estimates may have to be re-estimated based on, among other things: (i) fluctuations in

nickel, copper or other mineral prices; (ii) results of drilling; (iii) results of metallurgical testing and

other studies; (iv) changes to proposed mining operations, including dilution; (v) the evaluation of

mine plans subsequent to the date of any estimates; and (vi) the possible failure to receive or

maintain required permits, approvals and licences.

For more information on the Company and the key assumptions, risks and challenges with respect

to the forward-looking information discussed herein, and about our business in general, investors

should review the Company's most recently filed annual information form, and other continuous

disclosure filings which are available at www.sedar.com. Readers are cautioned not to place

undue reliance on forward-looking information. The Company does not undertake to update any

forward-looking information, except in accordance with applicable securities laws.

Nickel Creek Contact:

Stuart Harshaw

President & Chief Executive Officer

1-416-304-9318

[email protected]