Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NAM.V ·

New Age Metals TSX-V: NAM

Corporate Updates

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

New Age Metals Delivers New Positive Preliminary Economic Assessment of

the River Valley Palladium Project

June 29 th, 2023 , Rockport, Canada - New Age Metals Inc. (NAM) (TSX.V: NAM; OTCQB: NMTLF;

FSE: P7J) (“NAM” or the “Company” is pleased to announce the positive results of a new independent

Preliminary Economic Assessment (“PEA”) prepared in accordance with NI 43 -101 for the River V alley

Project, a wholly-owned palladium-platinum-copper deposit located 60 km east-northeast (100 road km) of

Sudbury, Ontario. This new PEA was developed by a group of independent consultants; namely P&E

Mining Consultants Inc. (mining, scheduling , project economics); D.E.N.M . Engineering Ltd. (mineral

processing and metallurgy); Knight Piésold Ltd. (tailings facility, water management, and rock mechanics);

and Story Environmental (environment and community). The Mineral Resource Estimate upon which this

new PEA is based was done by P&E in 2021.

PEA Highlights

• Pre-Tax NPV(5%): $289M; After-Tax: $135M

• Pre-Tax IRR: 16%; Post-tax IRR: 11%

• Annual Production: 2.5 Mt of potential process plant feed at an average grade of 1.19 g/t PdEq and

process recovery of 71.5%, resulting in an average annual payable Pd production of 47,400 oz.

• Total Tonnes Processed over Life of Mine: 38.6 Mt/16 years

• Pre-production Capital Requirement: $268.7M

• Average Unit Operating Cost: $30.98/t

• Assumed Metal Prices: US$2,150/oz Pd, US$1,050/oz Pt, US$1,830/oz Au, US$4.00/lb Cu

• River Valley Process Feed: Treated in an on-site conventional sulphide flotation plant to produce a saleable

PGM-enriched Cu concentrate to be transported off-site for smelting and refining.

• Project Enhancement Opportunities: Increased metal recoveries and expanded Mineral Resources

Harry Barr, NAM Chairman & CEO, stated: “The PEA results released today are positive with a post-tax

NPV(5%) of $134 M CAD, an IRR of 11% and 16 years of palladium, platinum and copper production .

Compared to the 2019 PEA, thi s 2023 PEA envisions a smaller, higher-grade operation with lower

CAPEX, expanded underground mining and reduced open pit mining, and a much -smaller

environmental footprint. These encouraging results are based on the 2021 Mineral Resource Estimate,

which was produced in accordance with current CIM standards and guidelines , to provide feed to an on -

site 2.5 Mtpa process plant. The next steps include targeting areas for drilling to convert Inferred to

Indicated Mineral Resources , expanding current Mineral Resources, the discovery of new

mineralized zones, and to testing of promising new technologies for improved metal recoveries, all

for incorporation into future, more advanced economic studies.”

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

PEA Summary*

The site plan layout for the new River Valley PEA is shown in Figure 1 below.

Figure 1. New PEA site layout plan for the River Valley Palladium Project.

Figure 1 shows five open pits and two underground portals that have been used in the engineering design

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

of the Project, the proposed process plant site, low -grade stockpile, waste rock storage facilities, tailings

storage facility, and site infrastructure. The Project as represented in Figure 1 has an area of 38.8 km2, which

reflects a major reduction from the 126.5 km2 site plan area in the 2019 PEA.

The parameters of the PEA are summarized in Table 1.

Table 1. PEA Summary Parameters

Assumptions

Palladium Price (Base case) US$/oz 2,150

Exchange Rate US$:CDN$ 1.35

Production Profile

Total Tonnes Processed 38,640,000

Process Plant Head Grade PdEq g/t 1.19

Mine Life (years) 16

Daily process plant throughput (tpd) 6,850

Palladium Process Plant Recovery (%) 71.5

Total Payable Palladium Equivalent Ounces 735,000

Average annual Palladium Production Ounces 47,400

Operating Costs ($ per tonne processed)

Unit Average LOM Operating Costs 30.98

Open Pit Mining Costs 12.63

Underground Mining Costs 60.61

Processing Costs 12.69

G&A 2.01

LOM Average Cash Cost US$/oz Pd 1,241

Capital Requirements

Pre-Production Capital Cost ($ M) 268.7

Sustaining Capital Cost (Life of Mine) ($ M) 163.0

Project Economics

Royalties (%) 3

Royalty Payable After $1.5M Buy Down to 1.5% ($ M) 35.4

Taxes (M $) 255.0

Pre-Tax

Cumulative Undiscounted Cash Flow ($ M) 599.0

NPV (5% Discount Rate) ($ M) 289.0

IRR (%) 16

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Payback (years) 6.2

After-Tax

Cumulative Undiscounted Cash Flow ($ M) 344.0

NPV (5% Discount Rate) ($ M) 135.0

IRR (%) 11

Payback (years) 6.9

PEA operating costs and capital costs are presented in Tables 2 and 3.

Table 2. Operating Cost Summary

Operating Cost Unit LoM

Open Pit Mining Cost $/t mined 2.95

Open Pit Mining Cost $/t processed 12.63

Underground Mining Cost $/t processed 60.61

Process Cost $/t processed 12.69

G&A $/t processed 2.01

Unit LoM Average Operating $/t processed 30.98

Table 3. Capital Cost Summary

Development Capital Initial (Y-2, Y-

1) ($ M)

Sustaining

($ M)

Total

LOM

($ M)

Open Pit Development and Equipment 37.0 59.4 96.4

Process Plant 119.2 119.2

On-Site Infrastructure 17.4 17.4

Electrical Powerline 30.0 30.0

Tailings Management Facility 17.0 27.0 44.0

Owner's Costs 10.0 10.0

Underground Mine Development 37.1 37.1

Reclamation Bond and Closure 16.3 16.3

Contingency 29.9 18.1 48.0

Total Capital 268.7 163 431.7

*This PEA was prepared in accordance with National Instrument 43 -101 (“NI 43 -01”) Standards of Disclosure of

Mineral Projects. It was prepared by P&E Mining Consultants Inc. with D.E.N.M . Engineering Ltd., Knight Piésold

Ltd. and Story Environmental. Readers are cautioned that the PEA is preliminary in nature and includes Inferred

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Mineral Resources that are considered too speculative geologically to have the economic considerations applied to

them that would enable them to be classified a s Mineral Reserves, and there is no certainty that the PEA will be

realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic variability. The

Company plans to file the PEA Technical Report (“Technical Report”) on SEDAR at www.sedar.com within 45 days

of the date of this press release. All currency is stated as CDN$ unless indicated otherwise.

Opportunities to Enhance Project Value

Two major opportunities to enhance Project value are: 1) improved metal recovery; and 2) increased

Mineral Resources.

1) Improved Metal Recoveries

HYDROMETALLURGICAL OPTIONS The main focus of this PEA from a processing stand point is

conventional milling and flotation with upgrading of the resultant copper concentrate to a marketable

product. The final concentrate (copper and PGMs) would be shipped to specific smelters to treat the River

Valley product as a part of the revenue stream.

As an alternative to shipping to smelters, pressure leaching and metal precipitation options to recover

platinum group metals (“PGMs”), gold and base metals will be investigated. Several PGM deposits

worldwide are currently being subject to hydrometallurgical testing as a potentially economic alternative to

base metal smelters.

Alternative Flotation Applications. Conventional flotation of the River Valley material has thus far been

unable to produce a high -grade marketable smelter concentrate for maximum net smelter returns.

The expected concentrate grades based on the recent testing at SGS Lakefield were detailed in New Age

Metals press release dated August 9, 2022.

Preliminary scoping work has been completed on the River Valley material utilizing two f lotation

alternatives to produce a higher-grade rougher concentrate and also possible increases in PGM recoveries.

The two technologies being investigated are the Woodgrove flotation and the Glencore (Jameson ) cell

techniques.

Rhodium Recovery & Marketability. Additional work in this area would be beneficial for the Project,

due to the high metal price of rhodium. The testwork recently complete showed the ability to recover

rhodium in the final concentrate, albeit not at a saleable threshold grade for the smelters. Review of the

rhodium mineralogy and process alternatives is recommended.

2) Increased Mineral Resources

The distribution of the current Mineral Resources at River Valley is shown in Figure 2.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Major infill, expansion and exploration drill programs are planned to: 1) convert Inferred to Indicated

Mineral Resources at the Lismer and Varley Zones; 2) expand current Mineral Resources at depth and along

strike at the Dana South, Banshee, Lismer Ridge, Varley and Azen Zones; and 3) test targets and delineate

mineralized zones that show potential for inclusion in future Mineral Resource modelling, particularly in

the footwall to the River Valley Intrusion, as guided by geophysical survey and 3-D geological modelling

results.

The drilling programs are slated to commenced in H2 2023, subject to financing.

Figure 2. Distribution of pit constrained Mineral Resources at $15/t NSR cut -off. The priority mineralized zones for

infill, expansion and exploration drilling are labelled red. Note that the Pine Zone is not exposed at surface.

M&I = Measured and Indicated Mineral Resources , Ind: = Indicated Mineral Resources , Inf = Inferred Mineral

Resources.

PEA Details

Mineral Resources

The details of the 2021 updated Mineral Resource Estimate were announced in a Company press release

dated October 5, 2021. The effective date of the updated Mineral Resource Estimate is September 14, 2021.

At cut-offs of CDN$15/t NSR (pit constrained) and CDN$50/t NSR (out -of-pit), the Mineral Resource

Estimate consists of: 89.9 Mt grading 0.54 g/t Pd, 0.21 g/t Pt, 0.04 g/t Au and 0.06% Cu, or CDN$47.58/t

NSR in the Measured and Indicated classifications; and 94 Mt grading 0.35 g/t Pd, 0.16 g/t Pt, 0.04 g/t Au

and 0.06% Cu, or CDN$31.69/t NSR in the Inferred classification. Contained metal contents are 2.3 Moz

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Pd+Pt+Au in the Measured and Indicated classifications and 1.6 Moz Pd+Pt+Au in the Inferred

classification Table 4.

Notes: Class = Classification, Meas + Ind = Measured and Indicated classifications.

1 Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

2. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation,

socio-political, marketing, or other relevant issues.

3. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated

Mineral Resource and must not be converted to a Mineral Reserv e. It is reasonably expected that the majority of

the Inferred Mineral Resource could potentially be upgraded to an Indicated Mineral Resource with continued

exploration.

4. The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and

Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices

Guidelines (2019) prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM

Council.

5. The Mineral Resource Estimate is based on US$ metal prices of $1,850/oz Pd, $900/oz Pt, $1,600/oz Au, $3.00/lb

Cu, $16/lb Co, $6.50/lb Ni, $8,000/oz Rh, $18.50/oz Ag. The US$:CDN$ exchange rate used was 0.75.

6. The NSR estimates use flotation recoveries of 80% for Pd, 80% for Pt, 80% for Au, 85% for Cu, 25% for Co, 90%

for Ni, 80% for Rh and 65% for Ag and smelter payables of 80% for Pd, 80% for Pt, 85% for Au, 85% for Cu, 50%

for Co, 90% for Ni, 80% for Rh and 65% for Ag.

7 The pit optimization used a mining cost of $2.25/t mined, combined processing and G&A costs of CDN$15/t, and

pit slopes of 50º. The out -of-pit Mineral Resources used underground mining, processing and G&A cost of

CDN$50/t.

8 Out-of-pit Mineral Resources were determined to be potentially extractable with the longhole mining method.

The predominant contribution of Pd + Pt to the NSR value (86%) is particularly noteworthy, given the rarity

of such primary platinum-group metal deposits in secure and established global mining jurisdictions.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

The Mineral Resource Estimate is sensitive to the selection of reporting NSR cut-off values for pit

constrained Mineral Resources. At a cut-off of $CDN25/t NSR, pit constrained Mineral Resources

are presented in Table 5.

Mining: OP & UG

The River V alley Project is planned to be mined by both open pit and underground methods. Initial mining

would be by open pit at the northwest end of the Deposit, close to the proposed process plant site.

A series of five open pits would be mined, starting at Dana North Zone and progressing in a southeasterly

direction to the Varley Zone. The Dana North Pit contains approximately half of the mineralized process

plant feed. Higher grade underground mineralization is planned to be mined during production years two

to seven, a nd will total approximately 3 Mt of process plant feed. The underground mining method is

planned to be sublevel longhole stoping with cemented rock backfill.

The average open pit strip ratio is envisaged to be 3.4:1 over the life -of-mine. It is anticipated that a fleet

of 90 t haul trucks, 10 m 3 excavators, and 254 mm diameter hole rotary drills will be utilized, following

industry standard conventional open pit mining techniques.

Mineral Processing

The new PEA annual process feed rate to the River Valley process plant will be 2.5 Mtpy (6,850 mtpd) of

mineralized material. The process plant remains as previously designed to produce a single copper sulphide

and PGM concentrate. The dewatered and dried concentrate would be hauled off-site for smelting.

Simplified process plant details are as follows:

1. Run-of-Mine (ROM) to be crushed in a single primary jaw crusher to 150 mm sizing (380 mtph);

2. SAG mill in closed circuit with a recycle pebble crusher and ball mill to produce flotation feed (310 mtph);

3. Rougher flotation, regrinding of the associated conc entrate, three-stage cleaning circuit to produce the final

concentrate;

4. Concentrate dewatering, filtering, drying for shipping to the smelter;

5. Tailings thickening prior to pumping to the tailings management facility (TMF);

6. Standard process water recovery w ould be from the associated thickeners and return water from the TMF

area. Make-up water for the process would be from one the lakes on the Property; and

7. Power for the facility will be provided by a dedicated 44 kV feeder line from Crystal Falls T ransformer

Station.

Initial discussions with Hydro One (suppler and builder) have been completed regarding options, capital and

$/kwh estimates.