New Age Metals Provides Progress Update ON Pre-Feasibility Study of the River Valley Palladium Project

Corporate Updates

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page1

NEW AGE METALS PROVIDES PROGRESS UPDATE ON

PRE-FEASIBILITY STUDY OF THE RIVER VALLEY

PALLADIUM PROJECT

May 4, 2022 Rockport, Ontario - New Age Metals Inc. (TSX.V: NAM; OTCQB: NMTLF; FSE:

P7J.F) (“NAM” or “Company”) is pleased to provide an update on the Pre-Feasibility Study of

the River Valley Palladium Project , one of North Americas largest undeveloped Platinum

Group Metals Projects near Sudbury, Ontario (Figure 1). Progress has been made in

advancing the mineral processing and metallurgical, geomechanical, hydrogeological,

geotechnical, and environmental and community engagement work components of the Pre-

Feasibility Study.

Figure 1. Palladium Mineral Resources in the northern area of the River Valley Palladium Deposit near

Sudbury, Ontario. Mineralized zones ( red) projected to surface. Mineral Resource Estimates using CDN$15/t

NSR cut -off and NSR calculation of 2021 Updated Mineral R esources and Technical Report (P&E, 2021).

Mineral Resources for Pardo Zone have not been estimated due to lack of drilling. The Huronian, Grenville

and Nipissing geological units not shown for illustration clarity.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page2

Mineral Processing and Metallurgical Testing Program

The mineral processing and metallurgical testing program at SGS Canada Inc. (Lakefield) (“SGS”)

is being managed on behalf of NAM by D.E.N.M Engineering Ltd. (Burlington) (“DENM”).

SGS with inputs from DENM and NAM, created Dana and Lismer mineralized zone master

and grade variability composites in February for the key Dana and Lismer Zones (Figure 1).

Grindability testing and initial flotation testwork on Dana and Lismer master

composites commenced in March . The initial flotation testwork is designed to confirm

parameters for the locked cycle testing variability work from the previous 2012 scoping

study level work and the best conditions to move forward. SGS has advised that indicative

metal recoveries should be available by the end of May.

Mineralogical sulphide and platinum metal studies of the Lismer Zones also commenced in

February. In addition to Pd and Pt minerals, the mineralogical study will focu s on

detection of nickel sulphide minerals (mainly pentlandite) and rhodium mineral

(hollingworthite) and other minor PGM phases . In addition, Rh assaying of MinMet

sample drill core commenced in February at GeoLabs (see Company press release dated

March 22, 2022). This work, in conjunction with metal recovery testwork at SGS, will

culminate, for the first time, in robust rhodium recovery determinations for River Valley.

Furthermore, p hysical and chemical studies of the tailings produced during metallurgical

testwork at SGS will be released by the end of July. These studies will be completed at SGS

under the direction of Knight-Piésold, as part of this Pre-Feasibility Study.

Geomechanical-Hydrogeological and Geotechnical Programs

Site investigation work by Knight -Piésold Ltd. (“KP”) was completed in March, which

included bedrock and surficial drilling as well as pit excavations . Two of the five

geomechanical drill holes (KP21-01 at Lismer Ridge Zone and drill hole KP21 -05 at Dana

South Zone – see Figure 1) were logged and sampled by NAM geologists as exploration holes.

Mineralized drill c ore samples were sent to SGS (Lakefield, Ontario ) for initial sample

preparation, and then to SGS Laboratory in Burnaby, BC for assay analysis. The results will

be released when available.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page3

Rock mass quality and structural domains have been determined by KP, based on logging of

oriented drill core , downhole televiewer survey results, laboratory testing, and historical

structural geology mapping and modelling studies. Open slope recommendations were

issued in April for review and comment. Design work has now commenced on site water

management structures. Design work on the tailing storage facilities will follow.

Environmental Baseline Studies and Community Relations Engagement

Story Environmental Inc. (“Story”) continued baseline environmental studies of the River

Valley Property and building effective relationships with local First Nations communities,

for future permit applications and approvals.

The ongoing environmental studies consisted of aquatics, surface water and hydrology field

work on the Property in the late fall of 2021 and winter of 2022. The surface water field work

involved Temagami First Nation personnel. Also, groundwater monitoring wells were

installed in the fall of 2021. In addition, a desktop atmospheric assessment was completed

for the Property in January 2022 .

An Exploration Memorandum of Understanding (“ MOU”) was signed with Nipissing

First Nation in late-January 2022 (see Company press release dated January 26, 2022).

This MOU is in addition to the MOU signed previously with Temagami First Nation in 2014

and amended in 2017. Story assisted with set-up and led a community meeting with

Temagami First Nation in early December 2021 , during which a River Valley Palladium

Project update was presented.

In March 2022, t he Mineral Development Branch confirmed, based on the Project’s early

stage of development, that NAM’s Duty to Consult remains limited to these two First Nation

communities.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page4

Mineral Resources/Reserves, Mining, Infrastructure, Cash Flow Model

The River Valley 2021 Updated Mineral Resource Technical Report by P&E Mining

Consultants Inc (“P&E”) was filed on SEDAR in November 2021 (see Company press release

dated November 19, 2021) . At cut -offs of CDN$15/t NSR (pit constrained) and CDN$50/t

NSR (o ut-of-pit), the Mineral Resource Estimate consists of: 89.9 Mt grading 0.54 g/t Pd,

0.21 g/t Pt, 0.04 g/t Au and 0.06% Cu, or CDN$47.58/t NSR in the Measured and Indicated

classifications; and 94 Mt grading 0.35 g/t Pd, 0.16 g/t Pt, 0.04 g/t Au and 0.06% Cu,

or CDN$31.69/t NSR in the Inferred classification. Contained metal contents are 2.3 Moz

Pd+Pt+Au in the Measured and Indicated classifications and 1.6 Moz Pd+Pt+Au in the

Inferred classification. This Mineral Resource Estimate will underpin the ongoing

Pre-Feasibility Study. The pit constrained Measured & Indicated Mineral Resources total

of 89 Mt grading 0.79 g/t Pd+Pt+Au (2.3 Moz) reported significantly exceeds the potentially

economic portion Mineral Resources total of 78 Mt grading 0.79 g/t Pd+Pt+Au (2.0 Moz)

reported in the 2019 Preliminary Economic Assessment (“PEA”) of River Valley.

The Pre-Feasibility Study as led by P&E will consider optimized mine production and

mineral processing rates, based on th e current, potentially more valuable Updated

Mineral Resource Estimate than that which underpinned the 2019 PEA . Pit slope

recommendations by K night-Piésold have been reviewed and accepted. SGS/DENM are

scheduled to deliver i ndicative m etal recoveries to P&E by the end of May 2022 for NSR

modelling and Mineral Reserve estimation work.

Pre-Feasibility Completion Schedule

NAM announced commencement of the River Valley Pre-Feasibility Study in the spring 2021

(see Company press release dated April 12, 2021). At that time, the Pre-Feasibility Study was

slated for completion in 12 to 14 months. However, the Covid-19 pandemic, difficulties in

finding and retaining experience d labour, a major shortage of suitable drill rigs and

experienced drillers, and backlogged assay laboratories have delayed completion of the PFS

to Q4 of 2022.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page5

About River Valley

The River Valley Palladium Project is located 100 road -km east from the City of

Sudbury . The Project area is linked to Sudbury by a network of all-weather highways,

roads and rail beds and is accessible year -round with hydro grid and natural gas

power nearby. River Valley enjoys the strong support of local communities , like the

village of River Valley, 20 km to the south. A fully executed Memorandum of Understanding

is in place with two local First Nation communities. Environmental baseline studies re -

commenced in 2020 and will continue in 2022.

The 2019 PEA results for the River Valley Palladium Project were announced in a Company

press release dated June 27, 2019. The PEA outlines a 20,000 t/day open pit mine and

processing plant operation producing an average of 119,000 ounces of PdEq per year for a

mine life of 14 years. Using base case metal prices of US$1,200/oz Pd, $1,050/oz Pt and

$3.25/lb Cu, the PEA showed a n after-tax NPV5% of US$138 million and an after-tax IRR of

10%. At a +20% palladium price of $1,440/oz Pd, the after-tax NPV5% increases to $299M

and the after-tax IRR to 15%. The current price of Pd is approximately $2,100/oz Pd.

About NAM

New Age Metals is a junior mineral exploration and development company focused on the

discovery, exploration and development of green metal projects in North America.

The Company has two divisions; a Platinum Group Metals division and a Lithium/Rare

Element division.

The PGM Division includes the 100% owned, multi -million-ounce Pd+Pt+Au (“3E”), district

scale River Valley Project, one of North America’s largest undeveloped Platinum Group

Metals Projects, situated 100 km by road east of Sudbury, Ontario. The Company completed

a positive Preliminary Economic Assessment on the Project in 2019 and, is fully

financed to complete a Pre-Feasibility Study on the Project in 2022. In addition to River

Valley, the Company owns 100% of the Genesis PGM -Cu-Ni Project in Alaska, and has plans

to complete a surface mapping and sampling program in 2022.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page6

The Lithium Division is one of the largest mineral claim holders in the Winnipeg River Pegmatite

Field, where the Company is exploring for hard rock lithium and various rare elements such as

tantalum and rubidium. In 2021 drone geophysics were completed on at least five of the

Company’s seven projects and in March 2022 the maiden drill results on the Company’s Lithium

Two Project were announced. On September 28, 2021 , the Company announced a

partnership with Mineral Resource Limited (MRL, ASX: MIN), the wor ld’s fifth largest

lithium producer to explore and develop the Company’s lithium project portfolio.

NAM is currently finalizing the 2022 exploration budget and management believes that

2022 will include the most aggressive exploration on the projects to da te.

Our philosophy is to be a project generator with the objective of optioning our projects with

major and junior mining companies through to production. The Company is actively seeking

an option/ joint venture partner for its road-accessible Genesis PGM-Cu-Ni project in Alaska

and for all or part of our Lithium Division in Manitoba.

Investors are invited to visit the New Age Metals website at www.newagemetals.com where

they can review the company and its corporate activities. Any questions or comments can be

directed to [email protected] or Harry Barr at [email protected] or call 613

659 2773.

Opt-in List

If you have not done so already, we encourage you to sign up on our website

(www.newagemetals.com) to receive our updated news.

Qualified Persons

The contents contained herein that relate to Exploration Results and Mineral Resources for

the River Valley Project is based on information compiled, reviewed or prepared by

Dr. William Stone, P.Geo., a consulting geoscientist for New Age Metals. Dr. Stone is the

Qualified Person as defined by National Instrument 43-101 and has reviewed and approved

the technical content of this news release.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page7

On behalf of the Board of Directors

“Harry Barr”

Harry G. Barr

Chairman and CEO

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchang e )

accepts responsibility for the adequacy or accuracy of this release. Cautionary Note Regarding Forward Looking Statements: This rele a se

contains forward -looking statements that involve risks and uncertainties. These statements may differ materially from actual future

events or results and are based on current expectations or beliefs. For this purpose, statements of historical fact may be deemed to be

forward-looking statements. In addition, forward -looking statements include statements in which the Company uses words such as

“continue”, “efforts”, “expect”, “believe”, “anticipate”, “confident”, “intend”, “strategy”, “plan”, “will”, “estimate”, “project”, “goal”, “target”,

“prospects”, “optimistic” or similar expressions. These statements by their nature involve risks and uncertainties, and actual results m a y

differ materially depending on a variety of important factors, including, among others, the Company’s ability and continuation of efforts to

timely and completely make available adequate current public information, additional or different regulatory and legal requirements a nd

restrictions that may be imposed, and other factors as may be discussed in the documents filed by th e Company on SEDAR

(www.sedar.com), including the most recent reports that identify important risk factors that could cause actual results to differ from those

contained in the forward-looking statements. The Company does not undertake any obligation to review or confirm analysts’ expectations

or estimates or to release publicly any revisions to any forward-looking statements to reflect events or circumstances after the date here of

or to reflect the occurrence of unanticipated events. Investors should not place undue reliance on forward-looking statements.