Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

NAM.V ·

NAM Files NI 43-101 Technical Report for Preliminary Economic Assessment on the River Valley PGE Project, Sudbury, Ontario, Canada

Resource Estimates Technical Reports (NI 43-101) Economic Studies

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page1

NAM Files NI 43-101 Technical Report for Preliminary Economic Assessment on

the River Valley PGE Project, Sudbury, Ontario, Canada

August 8th, 2019 Rockport, Canada – New Age Metals Inc. (NAM or the Company) (TSX.V: NAM; OTCQB:

NMTLF; FSE: P7J.F) Harry Barr, Chairman & CEO, stated; “We are pleased to announce that we have filed

our National Instrument 43-101 Technical Report on the Preliminary Economic Assessment (PEA) on the

Company’s 100% owned River Valley PGM Project in Sudbury, Ontario Canada (River Valley or the Project)

titled “Technical Report, Updated Mineral Resource Estimate and Preliminary Economic Assessment of

the River Valley Project” with an Effective Date of June 27, 2019, on SEDAR at www.sedar.com. The PEA

demonstrates positive economics for a large-scale open pit mining operation, with 14 years of Palladium

and Platinum production.”

(*) Cautionary statement NI 43 -101: The PEA was prepared in accordance with National Instrument 43 -

101 Standards of Disclosure for Miner al Projects ("NI 43 -101"). Readers are cautioned that the PEA is

preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be

categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources

that are not Mineral Reserves do not have demonstrated economic viability.

All currency is stated as CDN$ unless stated otherwise.

PEA Highlights (CDN$ unless otherwise noted):

▪ Life of mine (LOM) of 14 years, with 6 million tonnes annually of potential process plant feed at an

average grade of 0.88 g/t Palladium Equivalent (PdEq) and process recovery rate of 80%, resulting

in an annual average payable PdEq production of 119,000 ounces

▪ Pre-Production capital requirements: $495 M

▪ Undiscounted cash flow before income and mining taxes of $586M

▪ Undiscounted cash flow after income and mining taxes of $384M

▪ Average unit operating cost of $19.50/tonne over the life-of-mine

▪ LOM average operating cash cost of $971 per ounce (US$709/oz) and all-in sustaining cash cost of

$972 per ounce (US$709/oz) at a 1.37 CDN: USD exchange rate.

▪ A mining contractor will be engaged for the open pit mining

▪ Pre-tax NPV (5%): $261M, After-tax NPV (5%): $138 M

▪ Pre-tax IRR: 13%, After-tax IRR: 10%

▪ Assumed metal prices of US$1, 200/oz Pd, US$1,050/oz Pt, US$1,350/oz Au, US$3.25/lb Cu,

US$8.00/lb Ni, US$35/lb Co

▪ Using a + 20% Pd price sensitivity (to the base case of US$1,200/oz Pd) US$1,440 /oz Pd returns a

pre-tax IRR of 19% and an after tax-IRR of 15%.

▪ River Valley process plant feed will be treated by a conventional sulphide flotation process plant to

produce a single saleable PG E concentrate that will be transported to the Sudbury area for

smelting/refining

▪ Potential for up to 325 jobs at the peak of production

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page2

Project Economics and Sensitivities

The economic results of the PEA are summarized in Table 1 on an after-tax basis. The sensitivities and the

impact of cash flows have been calculated for +/- 20% variations against the base case.

Table 1: Project Economics Sensitivity. All values shown are on an after-tax basis.

Project Sensitivity Analysis

Pd Price Sensitivity

% -20% -15% -10% -5% Base Case +5% +10% +15% +20%

US$/oz 960 1,020 1,080 1,140 1,200 1,260 1,320 1,380 1,440

NPV (CDN$ M) -23 16 59 98 138 179 220 260 300

IRR (%) 4 6 7 8 10 11 12 13 15

OPEX Sensitivity

% -20% -15% -10% -5% Base Case +5% +10% +15% +20%

Cost Per Tonne 16 17 18 18 19 20 21 22 23

NPV (CDN$ M) 212 194 175 157 138 120 102 83 68

IRR (%) 14 12 11 10 10 9 8 7 7

CAPEX Sensitivity

% -20% -15% -10% -5% Base Case +5% +10% +15% +20%

CAPEX (CDN$ M) 397 422 446 471 496 521 546 570 595

NPV (CDN$ M) 284 248 212 175 138 102 64 28 -6

IRR (%) 14 13 12 11 10 8 7 6 5

Updated Mineral Resource Estimate

The pit constrained Updated Mineral Resource Estimate which formed the basis of the PEA, is set out in

Table 2 and was prepared by WSP under the supervision of Todd McCracken, P. Geo., an "Independent

Qualified Person", as defined in NI 43-101. The effective date of this Updated Mineral Resource Estimate

is January 9, 2019. The Updated Mineral Resource database contains 710 boreholes with 106,554 assays

records in the database, and 2,642 surface channel samplings. The Updated Mineral Resource Estimate

was completed on the Dana North, Dana South, Pine, Banshee, Lismer, Lismer Extension, Varley, Azen,

Razor, and Riv er Valley Extension Zones, using the ordinary kriging (OK) methodology on a capped and

composited borehole dataset consistent with industry standards. Validation of the results was conducted

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page3

thought the use of visual inspection, swath plots and global stat istical comparison of the model against

inverse distance squared (ID2) and nearest neighbour (NN) models.

Table 2: Pit Constrained Updated Mineral Resource Estimate for River Valley PGM Project - Effective Date

June 27, 2019.

Class PGM + Au (oz) PdEq (oz) PtEq (oz)

Measured 1,394,000 1,701,000 1,701,000

Indicated 983,000 1,166,000 1,166,000

Meas +Ind 2,377,000 2,867,000 2,867,000

Inferred 841,000 1,059,000 1,059,000

Notes:

1. CIM definition standards were followed for the Mineral Resource Estimate.

2. The 2018 Mineral Resource models used Ordinary Krig ing grade estimation within a three -dimensional block model with

mineralized zones defined by wireframed solids.

3. A base cut-off grade of 0.35 g/t PdEq was used for reporting Mineral Resources in a constrained pit and 2.00 g/t PdEq was

used for reporting the Mineral Resources under the pit.

4. Palladium Equivalent (PdEq) calculated using (US$): $ 950/oz Pd, $ 950/oz Pt, $ 1,275/oz Au, $ 1,500/oz Rh, $ 2.75/lb Cu,

$5.25/lb Ni, $36/lb Co.

5. Numbers may not add exactly due to rounding.

6. Mineral Resources that are not Mineral Reserves do not have economic viability

7. The Inferred Mineral Resource in this estimate has a lower level of confidence tha n that applied to an Indicated Mineral

Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral

Resource could be upgraded to an Indicated Mineral Resource with continued exploration.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page4

About NAM’S PGM Division

NAM’s flagship project is its 100% owned River Valley PGM Project ( NAM Website – River Valley

Project) in the Sudbury Mining District of Northern Ontario (100 km east of Sudbury, Ontario). Recently

the Company announced the results of the first PE A (see News Release – June 27th, 2019) completed on

the River Valley Project. The PEA has been developed by various independent consultants – P&E Mining

Consultants Inc. (P&E) was responsible for the open pit mining, surface infrastructure, tailings facility, and

project economics; DRA Americas Inc. (“DRA”) was responsible for all metallurgical test work and

processing aspects of the Project; and WSP Canada Inc. (“WSP”) was responsible for the Mineral Resource

Estimate. The PEA is a preliminary report, however, it has demonstrated that there are potentially positive

economics for a large -scale mining open pit operation, with 14 years of Palladium and Platinum

production.

On April 4th, 2018 , NAM signed an agr eement with one of Alaska’s top geological consulting

companies. The companies stated objective is to acquire additional PGM and Rare Metal projects in

Alaska. On April 18 th, 2018, NAM announced the right to purchase 100% of the Genesis PGM Project,

NAM’s first Alaskan PGM acquisition related to the April 4th agreement. The Genesis PGM Project is a road

accessible, under e xplored, highly prospective, multi -prospect drill ready Palladium (Pd) - Platinum (Pt)-

Nickel (Ni)- Copper (Cu) property. A comprehensive report on previous exploration and future phases of

work was completed by Avalon Development of Fairbanks Alaska in August 2018 on Genesis.

On August 29 , 2018 , the Avalon report was submitted to NAM, management is actively seeking an

option/joint-venture partner for this road accessible PGM and Multiple Element Project using the

Prospector Generator business model. See our latest press release dated July 25, 2019 which details the

current summer work program for the Genesis Project.

About NAM’S Lithium Division

The Company has eight pegmatite hosted Lithium Projects in the Winnipeg River Pegmatite Field,

located in SE Manitoba. Three of the projects are drill ready. The Company has applied for a drill permit

for its Lithium Two Project and expects the final permit t o be granted by the end of July. This Pegmatite

Field hosts the world class Tanco Pegmatite that has been mined for Tantalum, Cesium and Spodumene

(one of the primary Lithium minerals) in varying capacities, since 1969. NAM’s Lithium Projects are

strategically situated in this prolific Pegmatite Field. Presently, NAM is the largest mineral claim holders

for Lithium in the Winnipeg River Pegmatite Field. On January 15th 2018, NAM announced an agreement

with Azincourt Energy Corporation (see Jan 15, 2018 , Feb 22 nd, 2018 and April 11 th, 2018 , May 2 nd,

2018 Press Releases.

New Age Metals TSX-V: NAM OTCQB: NMTLF

Field Office: 59 Burtch’s Lane, Rockport, ON, Canada, K0E 1V0 [email protected]

+1.613. 659.2773 www.newagemetals.com

Page5

Qualified Persons and NI 43-101 Disclosure

The PEA was prepared under the supervision of Eugene Puritch, P.Eng. of P&E Mining Consultants Inc. The

Updated Mineral Resource Estimate was prepared by Todd McCracken, P.Geo. of WSP Canada Inc.

Metallurgical test work and process plant design and cost estimates were prepared by Jim Kambossos, P.

Eng. of DRA Americas Inc. All three are independent Qualified Persons in accordance with NI 43-101. Mr.

Puritch has reviewed and approved the technical information in this news release. Michael Neumann,

P.Eng., Managing Director for NAM is the Company Qualified Person as defined by National Instrument

43-101 and has reviewed and approved the technical content of this news release.

On behalf of the Board of Directors

“Harry Barr”

Harry G. Barr, Chairman and CEO

For further information on New Age Metals, please contact Harry Barr at 613-659-2773,

or [email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward Looking Statements: This release contains forward-looking statements that involve risks and

uncertainties. These statements may differ materially from actual future events or results and are based on current expectations

or beliefs. For this purpose, statements of historical fact may be deemed to be forward-looking statements. In addition, forward-

looking statements include statements in which the Company uses words such as “continue”, “efforts”, “expect”, “beli eve”,

“anticipate”, “confident”, “intend”, “strategy”, “plan”, “will”, “estimate”, “project”, “goal”, “target”, “prospects”, “optimistic” or

similar expressions. These statements by their nature involve risks and uncertainties, and actual results may diff er materially

depending on a variety of important factors, including, among others, the Company’s ability and continuation of efforts to timely

and completely make available adequate current public information, additional or different regulatory and legal requirements

and restrictions that may be imposed, and other factors as may be discussed in the documents filed by the Company on SEDAR

(www.sedar.com), including the most recent reports that identify important risk factors that could cause actual results to differ

from those contained in the forward-looking statements. The Company does not undertake any obligation to review or confirm

analysts’ expectations or estimates or to release publicly any revisions to any forward -looking statements to reflect even ts or

circumstances after the date hereof or to reflect the occurrence of unanticipated events. Investors should not place undue

reliance on forward-looking statements.