MURCHISON MINERALS LTD. NEWS RELEASE

News Release

Murchison Minerals Provides Exploration Update on The Ongoing PYC

Drill Program at its 100% -owned HPM Project

November 18, 2021 (Burlington, Ontario) : Murchison Minerals Ltd. (“Murchison” or the “Company”)

(TSXV: MUR) is pleased to announce that to-date it has successfully completed seven drill holes totalling

1,599 metres of the currently ongoing drill program at the Haut-Plateau de la Manicouagan (“ HPM”)

project located in Quebec. Thus far drilling has tested approximately 550 metres of the 1.95 kilometre

airborne electromagnetic anomaly resulting in significant pyrrhotite with minor chalcopyrite

mineralization observed in all seven holes. The observed sulphide is consistent with the mineralization

mapped on surface (see August 16 news release). The sulphide consists of metre-scale massive to semi-

massive pyrrhotite as well as intermittent breccias and disseminations over tens of metres within a dark

fine grained gabbroic unit . A handheld portable Niton XRF confirms the presence of nickel, copper and

cobalt within the sulphide intervals and assays are pending.

The ongoing drill program is expected to continue throughout the month of November with the objective

of defining additional mineralization along strike at PYC. The PYC target is considered highly prospective

and is located only eight km from rail and power access. Pending assay res ults, Murchison anticipates

completing additional drilling at PYC in the future to further define the full extent of the mineralization ,

as well as to drill test some of Murchison’s other high-priority exploration targets such as Syrah, Dix and

Barre de Fer.

President and Chief Executive Officer Troy Boisjoli comments:

“We are very pleased with the PYC drilling results to-date, they are another step in defining the district

scale Ni-Cu-Co potential at the HPM project. In parallel to drilling at PYC we continue to develop the

portfolio of high-potential prospects at HPM . To support this process, the Company has engaged the

services of Lightfoot Geoscience to help define the camp scale potential at HPM.”

Vice President of Exploration John Shmyr comments:

“This current drill program has exceeded our expectations demonstrating that the PYC mineralization has

excellent continuity along strike and at depth. We are very excited to see mineralization observed in all the

current holes from this program and we are more than pleased with the results thus far of the inaugural

drill campaign at HPM.”

2 | P a g e

MURCHISON MINERALS LTD. NEWS RELEASE

Figure 1: Location map of the 2021 Drill Collars overlain on the PYC geophysical anomaly.

Table 1 Collar Information

UTM Projected Coordinate System: NAD83 UTM Zone 19N.

Drill Hole Easting

UTM*

Northing

UTM*

Elevation

(m)

Azimuth

(⁰ North)

Dip

( ⁰ )

EOH

(m)

PYC21-001 613090 5722052 908 46 -49 152

PYC21-002 613090 5722052 908 46 -75 257

PYC21-003 613024 5722126 898 43 -51 128

PYC21-004 613024 5722126 898 57 -79 449

PYC21-005 613445 5721845 902 216 -46 170

PYC21-006 613445 5721845 902 216 -70 285

PYC21-007 613494 5721806 905 193 -45 158

3 | P a g e

MURCHISON MINERALS LTD. NEWS RELEASE

Figure 2: Semi-massive and breccia pyrrhotite mineralization observed in hole PYC21-001

Figure 3: Close-up of pyrrhotite and chalcopyrite mineralization within hole PYC21-001.

PYC Drill Program

The 2021 fall HPM drill campaign consists of one helicopter-supported drill supplied by Logan Drilling

Group of Stewiacke, Nova Scotia. Work crews are based at the nearby Station Uapishka . The program is

focused on testing the subsurface of the PYC mineral ized body that assayed as high as 0.79% Ni, 0.14%

Cu, and 0.15% Co from grab samples collected during the spring 2021 prospecting program. The surface

mineralization at PYC has been observed on surface over a strike length of 1.7 km with potential 1.95

km strike length indicated by recent electromagnetic airborne geophysics. The mineralization on surface

has been systematically sampled to confirm to a 42 metre-width in two steeply dipping parallel lenses (28

4 | P a g e

MURCHISON MINERALS LTD. NEWS RELEASE

metres- and 31 metres-wide) that were separated by 30 metres of unmineralized gabbro within one

location.

Geophysical modelling of the PYC area from the 2021 airborne electromagnetic geophysical data has

produced maxwell plate models that approximate the sulphide mineralization and extend to a depth of

300 metres (potential depth limit of the modelling for a vertical conductor). The planned drill holes are

designed to test the geophysical modelling.

About Lightfoot Geoscience Inc.

Peter Lightfoot Ph.D. and P.Geo ., is the President and Chief Geologist at Lightfoot Geoscience Inc. Mr.

Lightfoot is a skilled geologist with significant experience in the minerals industry (Inco and Vale), Ontario

Geological Survey, and academia. He was responsible for technical aspects of exploration, research and

development portfolio, strategic studies of the nickel market, and mentoring geoscience staff.

Qualifying Statement

The foregoing scientific and technical disclosures on the HPM project have been reviewed by John Shmyr,

P.Geo., VP Exploration, a registered member of the Professional Engineers and Geoscientists of Saskatchewan

and current holder of a special authorization with the Ordre des Géologues du Québec. Mr. Shmyr is a

Qualified Person as defined by National Instrument 43-101.

About the HPM Project

The HPM project is located east of the Manicouagan Cra ter, the site of a major meteorite impact estimated

to be 215 million years old. The extensive water reservoir supports five hydro-power installations. The existing

Quebec Cartier rail line, located 8 kilometres west of the PYC project area, links Labrador City to Port Cartier

and Sept Iles, two major iron ore port facilities.

The project is within the H aut-Plateau de la Manicouagan area . The claims host prospective gabbroic,

ultramafic and anorthositic bodies within the Manicouagan metamorphic complex and are associated with

significant nickel -copper-cobalt mineralization identified by a total of 32 diamond drill holes (6,479 m)

completed in 2001-2 and 2008-9.

The majority of the past drilling at HPM targeted the Barre de Fer geophysical conduc tor and confirmed the

known nickel-copper-cobalt mineralization approximately 300 metres along strike and to a depth of about

280 metres. The mineralization remains open at depth and partially along strike.

5 | P a g e

MURCHISON MINERALS LTD. NEWS RELEASE

Figure 4: HPM Location Map.

About Murchison Minerals Ltd. (TSXV: MUR)

Murchison is a Canadian‐based exploration company focused on nickel -copper-cobalt exploration at the

100%-owned HPM project in Quebec and the exploration and development of the 100%-owned Brabant Lake

zinc‐copper‐silver project in north‐central Saskatchewan. The Company also holds an option to earn 100%

interest in the Barraute VMS exploration project also located in Quebec, north of Val d’Or. Murchison

currently has 153.2 million shares issued and outstanding.

Additional information about Murchison and its exploration projects can be found on the Company’s

website at www.murchisonminerals.com. For further information, please contact:

Troy Boisjoli, President and CEO or Erik H Martin, CFO

Tel: (416) 350‐3776

[email protected]

CHF Capital Markets

Thomas Do, IR Manager

Tel: 416-868-1079 x 232

6 | P a g e

MURCHISON MINERALS LTD. NEWS RELEASE

[email protected]

Forward‐Looking Information

Certain information set forth in this news release may contain forward‐looking information that involves substantial known an d unknown risks and uncertainties.

This forward‐looking information is subject to numerous risks and uncertainties, certain of whic h are beyond the control of the Company, including, but not limited

to, the impact of general economic conditions, industry conditions, and dependence upon regulatory approvals. Readers are cau tioned that the assumptions used in

the preparation of such information, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance s hould not

be placed on forward‐looking information. The parties undertake no obligation to update forward‐looking information excep t as otherwise may be required by

applicable securities law.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exc hange) accepts responsibility for the

adequacy or accuracy of this release.