Murchison Minerals Ltd. News Release May 8, 2018

Corporate Updates

1 | Page 

MURCHISON   MINERALS   LTD.      NEWS   RELEASE      May   8,   2018  

NEWS RELEASE 

MURCHISON PROVIDES UPDATE ON 2018 DRILL PROGRAM AT BRABANT‐MCKENZIE PROJECT 

May 8, 2018 (Toronto, Ontario): Murchison Minerals Ltd. (the “Company”) (MUR‐TSXV) is pleased to provide an exploration 

update for the Brabant‐McKenzie project located 175 km northeast of La Ronge in Saskatchewan. The Company completed 

its winter drill program at the end of March for a total 12,431 metres in 25 holes. The program focused on three drill targets, 

the Brabant‐McKenzie Deposit (the "Deposit”), Anomaly C and Anomaly D.  

Brabant‐McKenzie Deposit 

The drill program on the Deposit was designed to potentially expand the tonnage of the current inferred resource and, where 

possible, infill and upgrade inferred resources to the indicated category. The program was also designed, where possible, to 

identify higher grade areas of the Deposit. The Company completed 19 diamond drill holes for a total of 9,004 metres from 

three drill pads ‐ A, B and C. (See Figure 1 and Table 1) 

Four holes were drilled from Pad A and focused on the untested areas on the northern edge of the Deposit.  

Six holes were drilled from Pad B and were designed to test both the lateral areas of the Deposit as well as a polymetallic 

zone located stratigraphically above the main mineralized zones. This zone could not be included in the November 2017 NI 

43‐101 resource estimate as the continuity of mineralization was not fully understood.   The program’s objective for these 

holes was to demonstrate enough mineral continuity in the zone to allow for the potential calculation of a resource estimate. 

Nine holes were drilled from Pad C and focused laterally and on the previously untested area down dip from the bottom of 

the  Deposit  at  approximately  600  metres  towards  last  year’s  BM17‐09  drill  hole  where  mineralization  was  intercepted  at 

approximately 950 metres. 

Figure 1. View of 2018 Drill Hole Traces on Brabant‐McKenzie Deposit 

+ 

Anomaly C and Anomaly D 

Anomaly C and D were identified as new drill targets from the 2017 geophysical and prospecting programs. The Company 

completed approximately 3,427 metres in six diamond drill holes on both targets. See Figure 2, Figure 3 and Table 1. 

A B C

2017 Indicated Resource of zinc

equivalent greater than 5%

2017 Inferred Resource of

zinc equivalent greater than

5%

View of 2018 Diamond Drill Holes in Plane of

Mineralization

Approximate outline of

geological model

A

B

C

Test of Northern edge of mineralization

Test of West and down dip extent

of mineralization

Test of Stratigraphic Hanging Wall –

containing polymetallic mineralization

Drill hole trace

2 | Page 

MURCHISON   MINERALS   LTD.      NEWS   RELEASE      May   8,   2018  

Anomaly C conductor plate is located approximately 1.4 kilometres south of the Deposit. Approximately 1,215 metres were 

completed  in  two  drill  holes  on  this  target.  The  plate  top  edge  begins  at  approximately  300  metres  below  surface.  The 

program  was  designed  to  test  the  highest  conductivity  and  any  associated  sulphide  mineralization  within  the  modelled 

conductor plate.  

Figure 2. View of 2018 Drill Hole Traces on Anomaly C 

Anomaly D conductor plate is a near‐surface target located approximately 1.5 kilometres southeast of the Deposit. The plate 

top  edge  begins  at  20  metres  below  surface.  Anomaly  D  is  a  high  conductivity  target  (2,300  seimens)  and  similar  in 

dimensions  to  the  Deposit,  measuring  approximately  800  metres  by  800  metres.  The  Company  completed  approximately 

2,212 metres in four drill holes from two drill pads. The program was designed to test for sulphide mineralization associated 

with increasing conductivity at depth within the modelled conductor plates. 

Figure 3. View of 2018 Drill Hole Traces on Anomaly D 

Electromagnetic Conductor Plates

Drill hole trace

Topographic Surface

Electromagnetic Conductor Plates

Drill hole trace

Topographic Surface

3 | Page 

MURCHISON   MINERALS   LTD.      NEWS   RELEASE      May   8,   2018  

Over  900  core  samples  were  sent  for  assay  during  the  program  and  submitted  to  SRC  Laboratories  in  Saskatoon, 

Saskatchewan. Further QAQC will be undertaken by ALS Labs in Vancouver.  

The Company plans to release the full results once all assays are received and will also provide context and a comprehensive 

analysis of the results. 

Qualifying Statement  

The foregoing scientific and technical disclosures have been reviewed by Kent Pearson, P. Geo., Finley Bakker, P. Geo. and 

Martin St‐Pierre, P. Geo., are qualified persons as defined by National Instrument 43‐101. Mr. Bakker and Mr. St‐Pierre are 

independent consultants to Murchison Minerals Ltd. and the Brabant‐McKenzie Project. Mr. Pearson is President and Chief 

Executive Officer of Murchison Minerals Ltd. 

About the Brabant‐McKenzie Project 

The  Brabant‐McKenzie  project  is  located  175  km  Northeast  of  La  Ronge,  Saskatchewan  and  approximately  3 km  from  the 

community  of  Brabant  Lake.  The  area  is  accessed  year  round  via  Highway  102  and  is  serviced  by  grid  power.  The  project 

consists of one mining lease which hosts the Deposit and an additional 13 contiguous mineral claims totaling 5,731 hectares 

which cover approximately 16 km of strike length over favourable geological horizons, multiple known mineralized showings 

and identified geophysical conductors.  

The  Brabant‐McKenzie  Deposit  hosts  an  indicated  resource  of  1.5  million  tonnes  grading  7.46%  Zn,  0.70%  Cu,  0.39%  Pb, 

31.16 g/t Ag, 10.09% Zn Eq and an inferred resource of 4.5 million tonnes grading 5.99% Zn, 0.62% Cu, 0.39% Pb, 19.39 g/t 

Ag, 7.99% Zn Eq as disclosed in the report dated November 25, 2017 and filed on SEDAR on March 13, 2018.  

About Murchison Minerals Ltd. 

Murchison Minerals Ltd. is a Canadian based exploration company focused on the exploration and development of the 100% 

owned Brabant‐McKenzie zinc‐copper project in North‐Central Saskatchewan. The Company also has a diversified portfolio of 

properties  including  the  HPM  nickel/copper/cobalt  project  in  Quebec  and  gold  projects  in  the  Pickle  Lake  area  of 

northwestern Ontario. 

Additional  information  about  Murchison  Minerals  and  its  exploration  projects  can  be  found  on  the  Company’s  website  at 

www.murchisonminerals.com.  

For further information, please contact: 

Kent Pearson, President and Chief Executive Officer  

or 

Erik H. Martin, Chief Financial Officer 

[email protected] 

(416) 350‐3776 

Forward‐Looking Information 

Certain information set forth in this news release may contain forward‐looking information that involves substantial known 

and unknown risks and uncertainties. This forward‐looking information is subject to numerous risks and uncertainties, certain 

of  which  are  beyond  the  control  of  the  Company,  including,  but  not  limited to,  the  impact of  general  economic  conditions, 

industry  conditions,  and  dependence  upon  regulatory  approvals.  Readers  are  cautioned  that  the  assumptions  used  in  the 

preparation of such information, although considered reasonable at the time of preparation, may prove to be imprecise and, 

as such, undue reliance should not be placed on forward‐looking information. The parties undertake no obligation to update 

forward‐looking information except as otherwise may be required by applicable securities law. 

Neither  TSX  Venture  Exchange  nor  its  Regulation  Services  Provider  (as  that  term  is  defined  in  policies  of  the  TSX  Venture 

Exchange) accepts responsibility for the adequacy or accuracy of this release.