Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MT.V ·

M3 Metals Provides an Update and Property Disclosure for the Daggett Lithium Project, near Barstow, California

Mergers & Acquisitions

M3 Metals Provides an Update and Property

Disclosure for the Daggett Lithium Project,

near Barstow, California

Vancouver, British Columbia--(Newsfile Corp. - October 2, 2023) -

M3 Metals Corp. (TSXV: MT) (FSE:

XOV) ("M3 Metals" or the "Company").

On May 9, 2023, the Company announced that it had entered

into a mineral property option agreement (the "Agreement") to acquire up to an eighty (80%) percent

interest in the Daggett Lithium Project (the "Property"), a mineral property prospective for lithium and

located in San Bernardino County, California.

The Agreement, dated effective May 8, 2023, is between the Company and IMEx Consultants Inc. (the

"Vendor").

The Agreement provides that the Company can earn a sixty (60%) percent interest in the

Property by: (i) issuing 2,000,000 shares to the Vendor and paying to the Vendor the sum of

USD$150,000 upon regulatory approval of the Agreement; and (ii) making USD$400,000 in exploration

expenditures on the Property within twelve (12) months of regulatory approval of the Agreement.

The

Company can acquire an additional twenty (20%) percent interest, for a total eighty (80%) interest in the

Property by issuing an additional 2,000,000 shares to the Vendor and making an additional

USD$2,000,000 in exploration expenditures on the Daggett Lithium Property within thirty-six (36) months

of regulatory approval of the Agreement.

The Agreement is subject to the regulatory approval of the TSX Venture Exchange (the "Exchange").

Because the transaction can result in the creation of a new control person, IMEx Consultants Inc.,

approval of the Agreement is further subject to the written consent of shareholders holding over 50% of

the current issued and outstanding shares of the Company. The transactions contemplated in the

Agreement constitute a Fundamental Acquisition (as that term is defined in the policies of the Exchange)

and, as such, require completion of a technical report on the Property prior to receipt of regulatory

approval.

The technical report has been submitted for review by the Exchange and the Company hopes

to move forward with the Fundamental Acquisition shortly.

Trading in the shares of the Company is

expected to resume between October 4-6, 2023.

No finder's fees are payable in connection with the Agreement and the Agreement is an arm's length

transaction.

There are no royalties or underlying option or other agreements related to the Property.

ABOUT THE DAGGETT LITHIUM PROJECT

The Property is comprised of 96 staked BLM and San Bernardino County registered lode mining claims

(the "Lakshmi Claims") covering 2,641 acres (761 hectares). The Lakshmi Claims encompass a 9km

strike length of exposed Barstow Formation clay-rich sediments containing anomalous levels of lithium.

The Barstow area, located in the central Mojave Desert hosts numerous historic and current mines and

exploration projects. To the east of the Daggett Lithium Project, the now-inactive Hector Borate Mine

was most recently operated by N.L. Industries Corp. ) ("N.L."). N.L. and its predecessors produced

hectorite, a lithium-magnesium smectite clay for use in specialty applications. Currently, adjacent to that

site, 5E Advanced Materials, Inc. is finalizing permitting while commissioning a new borate solution

mining and refining operation.

Borates play a big part in the history of mining in the Barstow region, with commercial borate mining and

refining operations dating from the 1880's in the nearby Calico Mountains, and even a small borate

mining operation within the Lakshmi claims group. The Calico borate mines were active until the 1920's,

at which time the Pacific Coast Borax Company commenced operations at their giant sodium borate

deposit at Boron, California. Another active project in the area includes the Waterloo Mine Silver Project,

currently operated by Apollo Silver Corp.

With its close association with borate mineralization and proximity to the Hector Mine, the Daggett

Project is similar in occurrence to projects in advanced development in a similar geologic and tectonic

setting in Nevada. The Project is well located in regard to infrastructure being within a very short distance

from major highway, rail and energy corridors. It is also lies in close proximity to the town of Barstow, CA

with available accommodations and labor.

IMEx Consultants Inc. ("IMEx"), the vendor of the Daggett Lithium Project, first sampled the project area

in March of 2022. Based on past experience in the area exploring for borate minerals, IMEx was aware

that the fine-grained sediments of the area contain anomalous levels of both boron and lithium.

IMEx

prospected the favorable sediments using a SciApps hand-help spectrometer (LIBS) to detect lithium

contents of as much as 1,995ppmLi. Duplicate samples were submitted to the SGS laboratory in Lima,

Peru and confirmed anomalous Li levels.

Figure 1: Map showing the location of the Daggett Lithium project "Lakshmi" claims in relation to the

city of Barstow, with nearby intersecting rail, highway, power and gas corridors.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/5509/182583_5e571b32241b9a7e_001full.jpg

M3M contemplates two phases (Phase I and Phase II) of exploration work, environmental baseline

studies and a permitting program at a cost of US$350,000 for Phase I and US$600,000 for Phase II to

bring the Daggett Project to the drilling stage, as outlined in the table, below and with Phase II being

contingent on results obtained in Phase I:

Table 1: Daggett Lithium project Phase I budget and schedule.

Activity

Budget (US$)

Schedule

Phase I:

Mapping

Sampling

350,000 (total)

40,000

60,000

Oct. 23 - May 24

Oct. 23 - May 24

Jan. 24 - May 24

Geophysics (ERT/TEM)

G&A / Other Costs

Phase II

Baseline Studies

Bureau of Land Management (EA)

NEPA Review Work

US Legal (Environmental / BLM / NEPA)

G&A / Other Costs

150,000

100,000

600,000 (total)

150,000

150,000

100,000

50,000

150,000

Apr. 24 - May 24

Oct. 23 - May 24

May 24 - May 25

May 24 - Apr. 25

Sept. 24 - Apr. 25

July 24 - May 25

May 24 - May 25

May 24 - May 25

M3M anticipates filing on SEDAR a technical report (the "Report") titled "Daggett Lithium Project",

authored by Mr. Jerry L. Aiken, BSc., Professional Geologist (WA) and SME Registered Member which

has been prepared for M3 Metals Corp. dated effective September, 2023.

The Report will contain

additional details and disclosure concerning the Daggett Lithium Project.

UPDATE ON DISPOSITION OF GREAT TEXAS SPRING PROPERTY CLAIMS

In its news releases of July 26, 2023 and September 21, 2023 (the "News Releases"), the Company

announced that it had entered into a mineral property option and joint venture agreement (the

"Agreement") with Surge Battery Metals Inc. ("Surge"), a TSX Venture Exchange listed company and

described an amendment to the Agreement.

The Agreement, as amended, grants Surge the option (the

"Option") to earn up to an eighty (80%) percent interest in and to certain recently staked claims in

Nevada (the "Great Texas Spring Property Claims") on the terms and conditions described in the News

Releases.

The Company has applied for TSX Venture Exchange approval of the disposition (the "Disposition") of

the Great Texas Spring Property Claims.

Approval of the Disposition is subject both to that TSX Venture

Exchange approval and is further subject to the written consent of shareholders holding over 50% of the

current issued and outstanding shares of the Company.

The technical disclosure in this news release regarding the Daggett Lithium Project has been reviewed

by Mr. Jerry L. Aiken, BSc, Professional Geologist (WA) and SME Registered Member.

Mr. Aiken is a

Qualified Person as that term is defined in NI 43-101.

ABOUT M3 METALS CORP.

M3 Metals Corp. is a Canadian listed Company, focused on creating shareholder value through

discoveries and strategic development of mineral properties in North America. For additional

information please visit M3 Metals website at

www.m3metalscorp.com

. You may also email

[email protected]

or call investor relations at (604) 669-2279.

M3 METALS CORP.

"Kosta Tsoutsis"

Kosta Tsoutsis, CEO

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS

THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS

RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

This news release may contain certain "Forward-Looking Statements" within the meaning of the

United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities

laws.

When or if used in this news release, the words "anticipate", "believe", "estimate", "expect",

"target, "plan", "forecast", "may", "schedule" and similar words or expressions identify forward-looking

statements or information.

These forward-looking statements or information may relate to future prices

of commodities, accuracy of mineral or resource exploration activity, reserves or resources, regulatory

or government requirements or approvals (including environmental, habitat and other similar

requirements or approvals), the reliability of third party information, continued access to mineral

properties or infrastructure, currency risks including the exchange rate of US$ for CDN$,

changes in

exploration costs and government royalties or taxes in Canada, the United States, California or other

jurisdictions and other factors or information. Such statements represent the Company's current views

with respect to future events and are necessarily based upon a number of assumptions and estimates

that, while considered reasonable by the Company, are inherently subject to significant business,

economic, competitive, political and social risks, contingencies and uncertainties. Many factors, both

known and unknown, could cause results, performance or achievements to be materially different from

the results, performance or achievements that are or may be expressed or implied by such forward-

looking statements. The Company does not intend, and does not assume any obligation, to update

these forward-looking statements or information to reflect changes in assumptions or changes in

circumstances or any other events affections such statements and information other than as required

by applicable laws, rules and regulations.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/182583