MITHRIL TO ACQUIRE THE LA DURA GOLD-SILVER PROPERTY ADJACENT TO

ITS FLAGSHIP COPALQUIN PROPERTY, DURANGO STATE, MEXICO

Melbourne, Australia and Vancouver, Canada – December 5, 2025 - Mithril Silver and Gold Limited

("Mithril” or the "Company") (TSXV: MSG) (ASX: MTH) (OTCQB: MTIR F) is pleased to announce the

execution of a Purchase Option to acquire the La Dura gold-silver property close to Mithril’s flagship

and district scale Copalquin property, both in Durango State, Mexico.

• The La Dura property consists of 5 contiguous mining concessions for a total area of 2,052

hectares, located less than 5 km from the town of El Durazno and less than 20 km from the

Company’s flagship Copalquin District property

• The La Dura property hosts several historic mines and workings with the most notable being the

4 level La Dura gold-silver mine with a 60 tonne per day processing facility

• The property has a large historic database of mining records and data from various sampling

campaigns from 1990’s to 2018. The mine last operated in 2013

• The Company has an exclusive option to purchase 100% interest in the concessions at any time

over 4 years by paying US$4 million to the vendor1

• The Company will maintain the La Dura mining concessions in good standing and has committed

to complete LiDAR and aerial magnetic surveys over the property in the first year and a minimum

spend of US$200,000 on exploration work in the second year. The LiDAR survey is scheduled to

be flown over the property this month followed by the aerial magnetic survey in early 2026. There

are no further exploration expenditure commitments

• The acquisition of the La Dura property expands our land holding close to our flagship Copalquin

District property, where drilling is progressing at Targets 1 and 5, with Target 3 drilling scheduled

to commence in January 2026 . The first half of 2026 will be a pivot al period in the rapid

advancement of the Copalquin District as we progress target expansion drilling and continue our

geologic development of the feeder system responsible for the widespread gold and silver

mineralisation across this large district.

“The historic La Dura mine was a notable past producer, and the local geology provides potential to

host gold and silver mineralisation across the 20 km 2 mining concession area ”, said John Skeet,

Managing Director & CEO. “La Dura lies within the same geologic locality as our flagship Copalquin

property and is only 5 kilometres from our existing support office in the town of El Durazno . The

upcoming LiDAR and aerial magnetic surveys will provide an initial assessment of the prospectivity

across the 20 km2 concession area ahead of detailed mapping, sampling and future drill testing.

Mithril has a strong foundation of knowledge at La Dura, with management having completed

exploration work on the property in 2017–2018. The team’s proven technical strengths and discovery

experience at Copalquin position the Company well to unlock value at La Dura.”

1 See details of the Transaction Terms on the following pages

ASX: MTH

TSXV: MSG

OTCQB: MTIRF

December 05, 2025

www. mithrilsilvergold.com

| 2

Figure 1 Mithril’s Copalquin and La Dura property locations in Durango State, Mexico

About the La Dura Project

La Dura consists of 5 contiguous mining concessions with a total area of 2,052 hectares and located in

Durango State, Mexico , 5 km from the town of El Durazno and 20 km from Mithril’s flagship Copalquin

property.

The property hosts a significant Au ‐Ag sheeted to stockwork vein system associated with NW striking

faults in Tertiary rhyolite. Mineralization occurs on surface along 650 metres of strike and has been mined

in the San Manuel shoot at the La Dura historic mine, to about 140 metres depth. Veins are characterised

by low sulphide mineralisat ion with minimal to no alteration of the host rhyolite tuff. Historically, the

veins have been exploited and explored solely on the progress of the underground workings and assaying.

The project warrants property scale mapping, wide spaced soil sampling and channel sampling to

develop targets for drill testing. LiDAR and aerial magnetic surveys are planned as precursors to a field

programme.

The veins at the various workings appear to be hosted by Upper Series volcanic rocks and may have

significant depth potential should they extend into the lower series andesitic rocks at some greater

depth.

ASX: MTH

TSXV: MSG

OTCQB: MTIRF

December 05, 2025

www. mithrilsilvergold.com

| 3

Figure 2 The upper level of the La Dura mine historic workings at the La Dura property

Transaction Terms

Upon execution of the Purchase Option Agreement (POA) Mithril will pay to the vendor US$25,000 and

issue to the vendor 50,000 ordinary Mithril shares. The shares will be subject to a four-month hold period.

The Option payment schedule is as follows:

• At the 12 month anniversary pay the vendor US$30,000

• At the 18 month anniversary pay the vendor US$30,000

• At the 24 month anniversary pay the vendor US$50,000

• At the 30 month anniversary pay the vendor US$50,000

• At the 36 month anniversary pay the vendor US$50,000

• At the 42 month anniversary pay the vendor US$50,000

At any time during the 48-month term, Mithril may purchase 100% interest in the La Dura concession by

paying the vendor US$4,000,000 . Payment of any remaining 6 monthly payments subsequent to the

purchase is not required. The vendor may elect to receive all or part payment of the USD $4m purchase

price provided the Mithril 20 day VWAP share price is greater than or equal to the equivalent of USD1.00

ASX: MTH

TSXV: MSG

OTCQB: MTIRF

December 05, 2025

www. mithrilsilvergold.com

| 4

per share. Mithril may elect to make the payment in cash only and not be obligated to make any part of

the payment in shares.

Mithril commits to complete LiDAR and aerial magnetic surveys over the concession areas during the

first 12 months and a minimum direct exploration spend of US$200,000 during the second 12 months.

If Mithril purchases the La Dura concessions, the vendor will be entitled to a NSR on production of

2.5%. The NSR can be reduced to 1% by paying the vendor US$2,500,000

ABOUT THE COPALQUIN GOLD SILVER PROJECT

The Copalquin mining district is located in Durango State, Mexico and covers an entire mining district of

70km2 containing several dozen historic gold and silver mines and workings, ten of which had notable

production. The district is within the Sierra Madre Gold Silver Trend which extends north-south along the

western side of Mexico and hosts many gold and silver districts.

Multiple mineralisation events, young intrusives thought to be system-driving heat sources, widespread

alteration together with extensive surface vein exposures and dozens of historic mine workings, identify

the Copalquin mining district as a major epithermal centre for Gold and Silver.

Within 15 months of drilling in the Copalquin District, Mithril delivered a maiden JORC mineral resource

estimate demonstrating the high -grade gold and silver resource potential for the district. This maiden

resource is detailed below (see ASX release 17 November 2021)^ and a NI 43-101 Technical Report filed

on SEDAR+

• Indicated 691 kt @ 5.43 g/t gold, 114 g/t silver for 121,000 oz gold plus 2,538,000 oz silver

• Inferred 1,725 kt @ 4.55 g/t gold, 152 g/t silver for 252,000 oz gold plus 8,414,000 oz silver

(using a cut-off grade of 2.0 g/t AuEq*)

• 28.6% of the resource tonnage is classified as indicated

Table 1 Mineral resource estimate El Refugio – La Soledad using a cut-off grade of 2.0 g/t AuEq*

Tonnes

(kt)

Tonnes

(kt)

Gold

(g/t)

Silver

(g/t)

Gold Eq.*

(g/t)

Gold

(koz)

Silver

(koz)

Gold Eq.*

(koz)

El Refugio Indicated 691 5.43 114.2 7.06 121 2,538 157

Inferred 1,447 4.63 137.1 6.59 215 6,377 307

La Soledad Indicated - - - - - - -

Inferred 278 4.12 228.2 7.38 37 2,037 66

Total Indicated 691 5.43 114.2 7.06 121 2,538 157

Inferred 1,725 4.55 151.7 6.72 252 8,414 372

* In determining the gold equivalent (AuEq.) grade for reporting, a gold:silver price ratio of 70:1 was determined, using the

formula: AuEq grade = Au grade + ((Ag grade/70) x (Ag recovery/Au recovery)). The metal prices used to determine the 70:1 ratio

are the cumulative average prices for 2021: gold USD1,798.34 and silver: USD25.32 (actual is 71:1) from kitco.com.

For silver equivalent (AgEq.) grade reporting, the same factors as above are used with the formula AgEq grade = Ag grade + (( Au

grade x 70) x (Au recovery/Ag recovery))

At this early stage, the metallurgical recoveries were assumed to be equal (93%). Subsequent preliminary metallurgical test work

produced recoveries of 91% for silver and 96% for gold (ASX Announcement 25 February 2022) and these will be used when the

resource is updated in the future. In the Company’s opinion there is reasonable potential for both gold and silver to be extracted

and sold.

^ The information in this report that relates to Mineral Resources or Ore Reserves is based on information provided in the

following ASX announcement: 17 Nov 2021 - MAIDEN JORC RESOURCE 529,000 OUNCES @ 6.81G/T (AuEq *), which includes

the full JORC MRE report, also available on the Mithril Resources Limited Website.

The Company confirms that it is not aware of any new information or data that materially affects the information included in the

original market announcement and that all material assumptions and technical parameters underpinning the estimates in the

ASX: MTH

TSXV: MSG

OTCQB: MTIRF

December 05, 2025

www. mithrilsilvergold.com

| 5

relevant market announcement continue to apply and have not materially changed. The company confirms that the form and

context in which the Competent Person’s findings are presented have not been materially modified from the original market

announcement.

Mining study (conceptual) and metallurgical test work supports the development of the El Refugio -La

Soledad resource with conventional underground mining methods indicated as being appropriate and

with high gold -silver recovery to produce metal on -site with conventional processing. The average vein

width is approximately 4.5 metres.

Mithril is currently exploring in the Copalquin District to expand the resource footprint, demonstrating its

multi-million-ounce gold and silver potential. Mithril has an exclusive option to purchase 100% interest in

the Copalquin mining concessions by paying US$10M on or any time before 7 August 2028.

-ENDS-

Released with the authority of the Board.

For further information contact:

John Skeet

Managing Director and CEO

[email protected]

+61 435 766 809

NIKLI COMMUNICATIONS

Corporate Communications

[email protected]

[email protected]

The Australian Securities Exchange has not reviewed and does not accept responsibility for the accuracy

or adequacy of this release.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of

the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Competent Persons Statement - JORC

The information in this announcement that relates to metallurgical test results, mineral processing and

project development and study work has been compiled by Mr John Skeet who is Mithril’s CEO and

Managing Director. Mr Skeet is a Fellow of the Australasi an Institute of Mining and Metallurgy. This is a

Recognised Professional Organisation (RPO) under the Joint Ore Reserves Committee (JORC) Code.

Mr Skeet has sufficient experience of relevance to the styles of mineralisation and the types of deposits

under consideration, and to the activities undertaken, to qualify as a Competent Person as defined in the

2012 Edition of the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration

Results, Mineral Resources and Ore Reserves. Mr Skeet consents to the inclusion in this report of the

matters based on information in the form and context in which it appears. The Australian Securi ties

Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this

release.

The information in this announcement that relates to sampling techniques and data, exploration results

and geological interpretation for Mithril’s Mexican project, has been compiled by Mr Darren LeFort who

is Mithril’s Exploration Manager. Mr LeFort is a member of the Engineers and Geoscientists of British

Columbia and a Certified Professional Geologist (P.Geo). This is a Recognised Professional Organisation

(RPO) under the Joint Ore Reserves Committee (JORC) Code.

Mr LeFort has sufficient experience of relevance to the styles of mineralisation and the types of deposits

under consideration, and to the activities undertaken, to qualify as a Competent Person as defined in the

2012 Edition of the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration

ASX: MTH

TSXV: MSG

OTCQB: MTIRF

December 05, 2025

www. mithrilsilvergold.com

| 6

Results, Mineral Resources and Ore Reserves. Mr LeFort consents to the inclusion in this report of the

matters based on information in the form and context in which it appears.

The information in this announcement that relates to Mineral Resources is reported by Mr Rodney

Webster, former Principal Geologist at AMC Consultants Pty Ltd (AMC), who is a Member of the

Australian Institute of Geoscientists. The report was peer reviewed by Andrew Proudman, Principal

Consultant at AMC. Mr Webster is acting as the Competent Person, as defined in the 2012 Edition of the

Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral

Resources and Ore Reserves, for the reporting of the Mineral Resource estimate. A site visit was carried

out by Jose Olmedo a geological consultant with AMC, in September 2021 to observe the drilling, logging,

sampling and assay database. Mr Webster consents to the inclusion in this report of the matters based

on information in the form and context in which it appears

Qualified Persons – NI 43-101

Scientific and technical information in this Report has been reviewed and approved by Mr John Skeet

(FAUSIMM, CP) Mithril’s Managing Director and Chief Executive Officer. Mr John Skeet is a qualified

person within the meaning of NI 43-101.

Samples are sent to ALS Gl obal with sample preparation performed in Chihuahua City, Mexico and

assaying of sample pulps performed in North Vancouver, BC, Canada