2014 Exploration & Development Update for Murray Brook Zinc‐Lead‐Silver Deposit, Bathurst Mining Camp, New Brunswick Exploration Update on the Bathurst Option Joint Venture Zinc Project, New Brunswick

Property Options & Staking Partnerships & JV

NEWS RELEASE

2014 Exploration & Development Update for Murray Brook Zinc‐Lead‐Silver  TSX.V: ELN OTC Pink: ELNOF FRANKFURT: E7QN Deposit, Bathurst Mining Camp, New Brunswick 

Exploration Update on the Bathurst Option Joint Venture Zinc Project,   New Brunswick 

  • Drilling currently underway with one rig in the Bathurst Mining Camp
  • Prospective DIAGNOS CARDS, geophysical and stratigraphic targets continue to be drill tested

February 25, 2014, Vancouver, BC; El Nino Ventures Inc. (“ELN” and the “Company”) (TSX.V: ELN; OTC Pink: ELNOF; Frankfurt: E7Q) is pleased to provide an update on the exploration program for the Bathurst Option Joint Venture Project (BOJV) with Votorantim Metals Canada Inc. and Glencore Canada Corporation (formerly Xstrata Canada Corporation).  The BOJV area of interest covers much of the world‐class Bathurst Mining  Camp  in  north‐central  New  Brunswick  (Figure  1).  Votorantim  Metals  Canada  Inc.  is  Project Operator.

2013 Exploration Program Results 

During 2013, fifteen holes were drilled for a total of 4780.7 metres at a cost of roughly $1.5 million. The holes were drilled to test prospective DIAGNOS CARDS, airborne and ground geophysical and stratigraphic targets in the BOJV Project area (Figure 2). The drill targets are distributed throughout the Bathurst Mining Camp.

Significant results were obtained from two diamond drill holes, MB‐13‐01 and SA‐13‐21, both of which intersected mineralization of interest.  MB‐13‐01 was drilled to test a ground gravity target just to the west of the Murray Brook polymetallic massive sulphide property, in the northwest corner of the BOJV.  The hole intersected 248 metres of weak mineralization consisting of pyrrhotite + pyrite ± chalcopyrite from 230 metres to end of hole at 578 metres, entirely in sedimentary rocks.  As a result, the hole was extended from  578  metres  to  821  metres.  It  remained  in  sedimentary  rocks  and  commonly  carried  5‐10% disseminated pyrrhotite.  The best assayed interval was 13 metres grading 0.18% Zn, 0.08% Pb, 0.10% Cu and  1.74  g/t  Ag  from  428  metres  down  hole  (Table  1).    The  hole  was  down‐hole  surveyed  with  an electromagnetic probe for off‐hole conductors.  The results indicated a couple of deeper responses which might reflect weak stringer mineralization.  No off‐hole response was received that could be interpreted as massive sulphide.

ELN News Release  Page 1 of 5  February 25, 2014

The other hole of interest, SA‐13‐21, was drilled to test a CARDs/geophysical target at Sevogle Airstrip in the south central part of the BOJV.  The hole intersected felsic volcanics from 45 metres to 300 metres down  hole,  with  several  short  intervals  of  quartz  +  chalcopyrite  +  sphalerite  +  galena  mineralization between 60 metres and 300 metres down hole.  The best assay result is 0.5 metres grading 2.9% Zn, 2.4% Pb and 0.04% Cu from 60 metres down hole (Table 1).

Table 1: Assay results for 2013 BOJV Project Drill Program.

Best Assay Intervals for DDH MB‐13‐1 ‐ Mt. Fowler
Cut‐off 0.05% Zn
DDHFromToIntervalAg g/tAu g/tCu%Pb%Zn%
MB‐13‐01408.00409.001.000.35<0.0010.020.380.55
MB‐13‐01428.00441.0013.001.740.0370.100.080.18
MB‐13‐01450.00459.009.001.980.0280.020.070.19
MB‐13‐01460.00462.002.001.230.1100.010.010.15
MB‐13‐01468.00471.003.002.560.0310.050.080.17
MB‐13‐01568.00569.001.006.40<0.0010.020.390.67
Best Assays for DDH SA‐13‐21 ‐ Sevogle Airstrip
SampleFromToIntervalAg g/tAu g/tCu%Pb%Zn%
57851360.0060.500.5020.50.0460.042.382.87
578555137.30137.650.352.10.0030.020.080.45
578562150.95151.400.452.30.0010.010.120.20
578570169.00169.500.500.7<0.0010.100.010.04
578575‐6184.70185.000.302.80.2730.030.160.37
578581213.00214.001.002.40.0020.020.210.24
578583214.44215.000.564.30.0520.080.100.11
578612292.00293.001.001.00.0170.050.010.14

Note: no significant assay results for the other 13 holes drilled in the 2013 program.

2014 Exploration Program Plans 

After a holiday hiatus, drilling resumed on the BOJV with a single rig in January.  The program planned is for up to thirteen holes to be drilled for a total of 3000 metres at a cost of approximately $350,000. Two holes  are  to  be  drilled  at  Sevogle  Airstrip,  and  six  holes  in  the  area  between  the  Murray  Brook  and Restigouche massive sulphide deposits and the remaining four or five holes to be drilled elsewhere.  The drill program will be in two phases: a winter program to end in the second half of February where drill holes are close to existing infrastructure and the remainder in the spring.  Subject to outcomes and results, the  next  steps  in  follow‐up  exploration  could  be  continued  direct  drilling  of  targets,  and  ground  and borehole geophysical surveys performed to optimize drill set‐ups.  The five year option earn‐in period for Votorantim Metals Canada Inc. currently ends in July 2014.

ELN News Release  Page 2 of 5  February 25, 2014

Figure 1. Land tenure map showing the location of properties in the Bathurst Option Joint Venture Project as of February 21, 2014. The BOJV includes 920 units in 26 claims totalling 20,019 hectares.  The amount changes as some claims are dropped and others staked.  El Nino maintains a 50% interest in another 1,177 units in 8 claims totalling 25,612 hectares.

Figure 2. Collar locations for diamond drill holes drilled on the BOJV Project area in 2013 and 2014.

Note the location of MB‐13‐1 in the northwest corner or the area, which is in the Mt. Fowler area near the Murray Brook Project, and SA‐13‐21 in the south central part of the area.

ELN News Release  Page 3 of 5  February 25, 2014

Qualified Persons Statement 

This news release has been reviewed and approved for technical content by William Stone, Ph.D., P.Geo. and a Qualified Person under the provisions of National Instrument 43‐101.

About El Niño Ventures Inc. Bathurst Projects 

El Niño Ventures Inc. has two active projects in the Bathurst Mining Camp: 1) the Bathurst Option Joint Venture (see below) and 2) Murray Brook (see company website);

About Bathurst Option Joint Venture Project 

The  BOJV  Project  is  a  Tri‐Party  Agreement  with  Xstrata  Canada  Corporation  (now  Glencore  Canada Corporation) and Votorantim Metals Canada Inc. covering much of the area of the Bathurst Mining Camp in  northeastern  New  Brunswick  (Figure  1).    The  project  commenced  in  July  2009.  Votorantim  Metals Canada Inc. can earn 50% by spending $10 million over 5 years and can further increase its interest to 70% by spending an additional $10 million over 2 more years. Exploration expenditures to date by Votorantim Metals Canada Inc. total about $6.8 million.

BOJV project originally consisted of 4712 claims owned 50% ELN and 50% Glencore Canada Corporation and 2907 claims owned 100% by Glencore Canada Corporation, together with an Area of Interest in which ELN  and  Glencore  Canada  Corporation  hold  equal  interest.    Due  to  the  Area  of  Interest,  the  BOJV generates new projects for ELN at no initial cost.  An example of such project generation for ELN is the Murray Brook Project.

Votorantim Metals Canada Inc. Statement 

Technical details in this news release were provided by Votorantim Metals Canada Inc. whose professional geologists conduct operations consistent with mineral industry best practices.  Votorantim Metals Canada Inc.  accepts  no  responsibility  for  this  news  release  or  any  inferences  made  from  the  technical  details provided herein.

About Votorantim Metals Canada Inc. 

Votorantim  Metals  Canada  Inc.  is  a  subsidiary  of  Votorantim  Metais,  a  company  that  is  part  of  the Votorantim Group and was founded in Brazil in 1918. The Votorantim Group operates in twenty countries and  has  over  40,000  employees.    Votorantim  Metais  is  the  largest  electrolytic  nickel  producer  in  Latin America and one of the world's leaders in the production of zinc, aluminum and nickel. Votorantim Metals Canada Inc. is operator of the Bathurst Option and Joint Venture, which, in conjunction with Glencore Canada Corporation and El Nino Ventures, is actively exploring for base metal deposits within the Bathurst Mining Camp.

ELN News Release  Page 4 of 5  February 25, 2014

About El Nino Ventures Inc. 

El Niño Ventures Inc. is an international exploration company, focused on exploring for zinc, copper, lead, and silver in New Brunswick, Canada and copper in the Democratic Republic of Congo ("DRC").

On Behalf of the Board of Directors,

Harry Barr 

Chairman & CEO 

El Niño Ventures Inc. 

Further Information: Tel: +1 604 685 1870 Fax: +1 604 685 8045 Email: [email protected] or visit www.elninoventures.com

650‐555 West 12th Avenue, City Square, West Tower, Vancouver, B.C., Canada, V5Z 3X7

Neither  the  TSX  Venture  Exchange  nor  its  Regulation  Services  Provider  (as  that  term  is  defined  in  the  policies  of  the  TSX  Venture  Exchange)  accepts responsibility for the adequacy or accuracy of this release.

Cautionary  Note  Regarding  Forward  Looking  Statements.  This  release  contains  forward‐looking  statements  that  involve  risks  and  uncertainties.    These statements may differ materially from actual future events or results and are based on current expectations or beliefs.  For this purpose, statements of historical fact may be deemed to be forward‐looking statements.  In addition, forward‐looking statements include statements in which the Company uses words such as “continue”,  “efforts”,  “expect”,  “believe”,  “anticipate”,  “confident”,  “intend”,  “strategy”,  “plan”,  “will”,  “estimate”,  “project”,  “goal”,  “target”,  “prospects”, “optimistic” or similar expressions.  These statements by their nature involve risks and uncertainties, and actual results may differ materially depending on a variety of important factors, including, among others, the Company’s ability and continuation of efforts to timely and completely make available adequate current  public  information,  additional  or  different  regulatory  and  legal  requirements  and  restrictions  that  may  be  imposed,  and  other  factors  as  may  be discussed in the documents filed by the Company on SEDAR (www.sedar.com), including the most recent reports that identify important risk factors that could cause actual results to differ from those contained in the forward‐looking statements.  The Company does not undertake any obligation to review or confirm analysts’ expectations or estimates or to release publicly any revisions to any forward‐looking statements to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.  Investors should not place undue reliance on forward‐looking statements.

ELN News Release  Page 5 of 5  February 25, 2014