Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MOO.V ·

Moon River Moly Ltd. Announces Preliminary Economic Assessment of Potential Restart of 25% Owned Endako Molybdenum Mine

Economic Studies

Moon River Moly Ltd. Announces Preliminary

Economic Assessment of Potential Restart of

25% Owned Endako Molybdenum Mine

HIGHLIGHTS:

Pre-tax net present value (

"NPV"

) of $1.1 billion, internal rate of return (

"IRR"

) of 46%, an after-tax

NPV of $790 million and an IRR of 40% at an 8% discount rate and assuming a long-term

molybdenum ("Mo") price of US$49.73 per kg (US$22.50 per pound ("lb"));

10-year mine life based on 75,000 tonnes of mill throughput per day or 27.3 million tonnes per-

year;

Initial capital cost of $550.9 million including $83.7 million of contingency;

Annual average production of 9.3 million kg or 20.5 million pounds of Mo;

Average cash cost of US$25.60 per kg or US$11.61 per lb and All-In Sustaining Cost (

"AISC"

) of

US$29.85 per kg or US$13.54 per lb of Mo;

Open pit mine with flotation processing facilities on site;

A measured and indicated mineral resource of 335.7 million tonnes grading 0.072% MoS2 (0.0 43

% Mo) (see Table 1.1;

A 2.2-year payback;

Life-of-mine direct income and mining taxes in excess of $609 million;

Potential Project enhancements from the use of ore bucket sorting technology and ore particle

sorting ("OPS") technology.

All dollar amounts are stated in Canadian Dollars unless otherwise noted.

Toronto, Ontario--(Newsfile Corp. - November 21, 2025) - Moon River Moly Ltd.

(TSXV: MOO)

(

"Moon

River"

or the

"Company"

) is pleased to announce the results of a Preliminary Economic Assessment

(

"PEA"

) for the Endako mine complex in British Columbia (the

"Endako Mine"

),

currently on care and

maintenance, comprised of an open-pit molybdenum mine, concentrator, and roaster, located

approximately 190 kilometres west of Prince George, British Columbia. The PEA examines the potential

restart of operations at the Endako Mine

(the

"Project"

).

Paul Parisotto, President and Chief Executive Officer, says of the PEA results: "We are very pleased

with the positive results of the PEA as it presents a very convincing case for the rapid advancement of

the necessary work to restart mining operations at the Endako Mine."

Ian McDonald, Chairman, commented: "My involvement with this Project first began twenty years ago,

and I firmly believe that the time for the restart of production at the Endako Mine has arrived.

The

compelling, robust economics, together with a Tier One jurisdiction in a mining-friendly province, indicate

that the Endako Mine can recapture its position as Canada's largest molybdenum producer."

The PEA was prepared by A-Z Mining Professionals Ltd. (

"AMPL"

) and contemplates the restart of

open pit mining with potentially economic mineralization processed in the existing on-site processing

facilities.

The open pit will produce approximately 26 to 27 million tonnes per year of potentially

economic molybdenum (

"Mo"

) mineralization.

Run of Mine (

"ROM"

) potentially economic mineralization

will be crushed, ground in the SAG mill located in the New Plant (as defined below), ground in ball mills

located in both the New Plant and Old Plant, as described further below, and followed by Mo concentrate

produced by flotation.

The resulting Life of Mine (

"LOM"

) is 10 years.

BACKGROUND

The Endako Mine is a past producing mine with flooded open pits, an original mothballed processing

facility (the

"Old Plant"

) which had processing capacity of approximately 30,000 tonnes per day, a

larger 52,000 tonnes per day processing facility on care and maintenance since 2015 (the

"New

Plant"

) and all support infrastructure and facilities in place (also on care and maintenance).

Both

processing facilities employed flotation recovery producing molybdenum concentrate.

The Endako Mine is located in the Bulkley-Nechako region of central British Columbia, approximately

190 kilometres (km) west of Prince George and about 400 km east of Prince Rupert, British Columbia.

The nearest town is Fraser Lake, about 15 km east of the Endako Mine and is located about 10 km

south of Highway 16 (the Yellowhead Highway) on a paved road.

On May 30, 2024, Moon River completed the indirect acquisition of a 25% interest in the Endako Mine

from Sojitz Corporation (

"Sojitz"

), a Japanese multi-national company. The Endako Mine is jointly

owned by Moon River (25%) and Centerra Gold Inc. (

"Centerra"

) (75%) and operates through a joint

venture company. While Centerra is aware that this PEA was being prepared for Moon River, it has

neither participated in nor endorsed the work.

PROJECT RESTART PLAN

The restart mining plan comprises:

1

.

Mining measured and indicated potentially economic mineralization, located mainly in the walls

and floors, of the existing Endako and Denak open pits.

2

.

Rebuilding existing blast hole drills and rope shovels from the past operation and lease major

mining equipment and purchase smaller support equipment for the mine.

3

.

Relocating the existing primary crusher and a second new crusher to outside of the new ultimate

open pit limits.

4

.

Adding pumping capacity to split the mill feed between the New Plant and the Old Plant ball mills

and add extra rougher flotation capacity to the New Plant to allow for the planned higher throughput.

5

.

Refurbishing a portion of the Old Plant grinding circuit to provide an extra 20,000 - 25,000 tonnes

per day grinding capacity and connecting this grinding circuit to the New Plant flotation circuit.

6

.

Refurbishing of major equipment and refurbishing or replacing smaller equipment components (as

required) in the processing plants.

7

.

Construction of a new concentrate dewatering and drying circuit and building.

8

.

Construction of a tailings sand plant to produce cycloned tailings to facilitate tailings dams height

and storage capacity increases to meet the restart mine plan.

9

.

Refurbishing and/or upgrading, as required, of the site infrastructure buildings, facilities, and

services.

10

.

Construction of a water treatment plant (

"WTP"

) to treat all contact water (water from disturbed

areas of the mine) not recycled in the mining and processing operations.

11

.

Reconfiguring and installation of water pipelines to store and remove water (water from the

disturbed areas of the mine) not recycled in the mining and processing operations.

12

.

Construction of water pipelines from TP-1 to the WTP and from the WTP to the discharge to the

environment location on the Endako River.

13

.

Sale of molybdenum concentrate to domestic and international smelters.

Mining would employ open pit techniques using conventional rubber tired, diesel-powered mobile

equipment, track mounted drills, and rope shovels.

The LOM measured and indicated potentially economic mineralization production is scheduled at

approximately 26 to 27 million tonnes per year.

The mine schedule prioritizes mining of higher-grade

material from within the open pits for the first approximately 10 years. The LOM strip ratio is favourable

at 0.68 tonnes of waste per 1 tonne of potentially mineable resources.

The mine schedule is based on the optimised pit shell with mining recovery and mining dilution rates of

95% and 5%, respectively.

Mining will be performed on a 24 hour, 7 days per week basis. Mining equipment will be a combination

of leased and owned.

The potentially mineable resources from the open pit optimisation were used to develop the mine plan,

which would extract 273 million tonnes at an average grade of 0.075% MoS2 (0.045% Mo) after dilution

and mining losses.

PROCESSING

Recovery of a molybdenum concentrate from potentially economic mineralization will be achieved using

the refurbished existing processing plant facilities.

The addition of new processing equipment is

required for concentrate leaching, dewatering, and drying. The processing plant will have a capacity to

treat 75,000 tonnes per day or 27 million tonnes per annum.

The existing in-pit primary crusher and a new second crusher, located close to the New Plant, will

process the potentially economic ROM mineralization. The crushed potentially economic mineralization

will be ground in the SAG mill located in the New Plant followed by grinding in ball mills located in both

the New Plant and the Old Plant.

The grinding products from the Old Plant and the New Plant will be combined at the beginning of the New

Plant flotation circuits.

Concentrate will be produced by rougher/scavenger flotation, primary concentrate

regrinding, first cleaner/scavenger flotation, secondary concentrate regrinding, secondary cleaner

flotation, and final concentrate thickening.

Final concentrate leaching and product dewatering and drying will be performed in a new facility

constructed on the footprint of the existing ultra-pure plant (to be demolished).

The forecast average processing plant molybdenum recovery is 75.7%.

INFRASTRUCTURE

Existing infrastructure includes:

1

.

access roads, BC power grid-power supply to site, nearby railway line and fresh water supply

network;

2

.

primary crushing plant; (to be moved);

3

.

one new processing plant capable of processing 52,000 tonnes/day;

4

.

one old decommissioned processing plant capable of processing 30,000 tonnes/day;

5

.

tailings management facility with 2 disposal areas TP-1 and TP-3;

6

.

reclaim water ponds;

7

.

administration, warehouse, change house, laboratory, mine shops and buildings; and

8

.

one reclaimed tailings disposal area TP-2; and

9

.

two non-operational roasters.

Refurbishing and upgrading of all facilities, other than the existing roasters which will remain non-

operational, will be required and are included in the restart plan and cost estimates.

MANPOWER

The operation would employ a total of approximately 500 hourly and staff personnel.

ENVIRONMENT AND PERMITTING

The Endako Mine is in compliance with all necessary permits for its status as an operation on care and

maintenance.

A restart of mining operations will necessitate the reactivation and refreshing of all

necessary water and operating permits.

Additionally, an amendment to the existing tailings management

facility permit will be required, prior to production.

This will allow placement of classified tailings to

increase the dam heights, in order to accommodate LOM tailings disposal. It is anticipated that the

required permits for a restart of mining operations will be obtained as a matter of course.

PROJECT SCHEDULE

The Endako Mine restart schedule requires approximately 1.5 to 2 years from the approval of restart to

the start of production.

During the first year, detailed engineering on the open pit mining, processing

plants reconfiguration and upgrades, support facilities refurbishment and upgrades, preparation and

awarding of contractor and supplier major contracts will be completed.

Construction and start of

commissioning will require an additional year.

MINERAL RESOURCE

The data used to generate the resource calculation was reviewed and approved by F. Bakker P.Geo.

This included two site visits (April 2025 and September 2025) by the author. Sampling methods, QAQC

programs and databases were examined.

As the database contains approximately 360,000 individual

assays and over 290,000 drill holes (reverse circulation, diamond drill and blast holes) it was not

possible to verify the entire data set due to the volume of data and as many of the holes no longer exist.

The assay data was verified by comparing to Endako written reports, filed assessment reports and

month end statements and work undertaken by previous authors. The author is of the opinion that the

accuracy of the data was sufficient for a mineral resource statement.

The mineral resource was calculated utilizing commercial 3D Block Modelling Software (HxGN Mine

Plan

tm

3D). The model utilized geological domains based on geostatistics, lithology, a grade limit

design of approximately 0.01% MoS2 and limits imposed by both existing pit walls and potentially new

pit wall limits.

This resource model was used for determining the mineral resources estimate and to

undertake open pit optimisation of a mine production plan utilizing the potentially mineable resource.

The effective date of the mineral resource is the upcoming publication date of the PEA.

The author is unaware of any known legal, political, environmental, or other risks that could materially

affect the potential development of the mineral resources or mineral reserves as this was an existing

operating mine.

Table 1.1 presents the mineral resource estimate for the Endako Mine at various cut-off grades.

Inferred

mineral resources were not included in the PEA economic analysis.

Table 1.1

Mineral Resources

MEASURED

RESOURCE

INDICATED

RESOURCE

MEASURED AND

INDICATED

INFERRED

RESOURCE

ZONE

TONNES

%MoS2

TONNES

%MoS2

TONNES

%MoS2

TONNES

%MoS2

Total

>=

0.010

237,413,000

0.0468

435,641,000

0.049

673,054,000

0.048

164,564,000

0.038

Total

>=

0.015

206,183,000

0.0522

409,652,000

0.052

615,835,000

0.052

144,091,000

0.037

Total

>=

0.020

183,642,000

0.0565

382,707,000

0.054

566,349,000

0.055

128,689,000

0.040

Total

>=

0.025

157,962,000

0.0621

347,564,000

0.057

505,526,000

0.059

112,503,000

0.043

Total

>=

0.030

138,289,000

0.0671

311,767,000

0.061

450,056,000

0.063

93,871,000

0.046

Total

>=

0.035

117,593,000

0.0733

271,696,000

0.065

389,289,000

0.067

76,928,000

0.050

Total

>=

0.040

100,673,000

0.0794

234,981,000

0.069

335,654,000

0.072

60,127,000

0.054

Total

>=

0.045

85,723,000

0.0860

187,826,000

0.074

273,549,000

0.078

45,770,000

0.060

Total

>=

0.050

73,121,000

0.0927

158,985,000

0.079

232,106,000

0.084

34,961,000

0.066

Total

>=

0.055

62,662,000

0.0996

132,436,000

0.085

195,098,000

0.090

27,753,000

0.072

Total

>=

0.060

54,246,000

0.1061

112,264,000

0.090

166,510,000

0.095

22,864,000

0.077

Total

>=

0.065

46,871,000

0.1131

93,091,000

0.096

139,962,000

0.102

18,903,000

0.083

Total

>=

0.070

40,936,000

0.1198

78,354,000

0.101

119,290,000

0.108

15,875,000

0.087

Total

>=

0.075

35,776,000

0.1267

64,680,000

0.107

100,456,000

0.114

13,276,000

0.092

Total

>=

0.080

31,269,000

0.1339

54,004,000

0.113

85,273,000

0.121

11,042,000

0.097

The highlighted resource at a cutoff grade of 0.040%MoS2, (excluding inferred resources) is the long

term potentially economic mineralization that could be available for mining.

This cutoff grade was used in

determining the mining plan which reflects the mining and processing rate of approximately 27 million

tonnes per year at an overall LOM operating cost of $11.84.

The 0.040% MoS2 cutoff was chosen as it

has an in-situ value of $12.14 per tonne, which is slightly above the LOM mining cost. (Grade/100 x 2204

lbs/tonne x conversion to Mo (0.599%) x Mill Recovery (75.7%) x $22.5 (price/lb) x1.35 (US$ Exchange

rate) = $12.14/tonne).

There are no mineral reserves for the Endako Mine.

Mineral resources that are not mineral reserves do

not have demonstrated economic viability.

CAPITAL EXPENDITURES

Pre-production capital expenditures for the Project Base Case are estimated to total $493.7 million. The

total capital expenditure includes contingencies from 20% to 30%. The breakdown of capital

expenditures is presented in Table 1.2 below.

Table 1.2

Pre-production Capital Expenditures - Estimates

Component

Total Expenditures

($ million)

Mine

$35.1

Equipment Lease Deposit and Purchases

$23.3

Processing Plant

$89.2

Tailings Management Facilities

$150.1

Surface Infrastructure

$13.2

Non- Mining Mobile Equipment

$5.0

Water Management

$31.5

Water Treatment

$52.7

Owner's Costs

$10.0

Contingency

$83.7

Total

$

493.7

In addition to the capital expenditures, working capital of $57.2 million, based on 3 months of operating

costs, has been estimated.

LOM sustaining capital requirements of $3.2 million are estimated.

This comprises upgrades to the

processing plant and surface infrastructure.

Mining equipment is to be leased to own for the LOM.

The

tailings management facility dam raising costs are included in operating costs as the tailings will be

used to increase dam heights as part of the tailings facility management plan.

OPERATING COSTS

The estimated total average Base Case operating cost (excluding smelting and refining) is

approximately $11.84 per tonne of potentially mineable resources or the equivalent (exchange rate of

CAD$: US$ =1.35) or US$11.61 per pound of molybdenum. Table 1.3 below, presents a summary of the

LOM average operating costs for each department on a cost per tonne of potentially mineable resources

basis.

Table 1.3

Project Operating Costs Summary

Component

Cost/tonne

($)

Mining

$5.45

Processing and Tailings

$5.53

Surface Department, Environmental, and G&A

$0.86

Total Operating Cost per Tonne

$11.84

Total Operating Cost per Pound of Molybdenum

US$11.61

FINANCIAL RESULTS

The financial returns (Table 1.4) from the potentially mineable resources are presented for the expected

parameters and costs at a molybdenum long term three-year trailing average price of US$49.73 per kg

(US$22.50 per pound lb.) of molybdenum oxide, at an exchange rate of CAD$ 1.00 = US$0.74.

The Endako Mine is forecast to produce approximately 9.3 million kilograms (20.5 million pounds) per

year of molybdenum metal in concentrate. Life of Mine total molybdenum metal in concentrate production

is 93.3 million kilograms (205.2 million lbs.).

Table 1.4

Base Case Financial Returns

Pre-Tax

After-Tax

Pre-production CAPEX ($ millions)

$493.7

$493.7

Undiscounted Net Revenue ($ millions)

$5,854

$5,854

Undiscounted Total Cash Flow ($ millions)

$2,087

$1,478

NPV (5%) - millions

$1,405

$996

NPV (8%) - millions

$1,116

$790

IRR

46%

40%

Payback Period

2.2 years

2.2 years

SENSITIVITY ANALYSIS

Sensitivity analysis was performed for molybdenum price, capital expenditures, operating costs, mined

grades and exchange rate for ranges up to ±20%.

The Project is sensitive to changes in metals prices

and reasonably sensitive to changes in all the other variables.

The sensitivity analysis results are shown in Table 1.5 and 1.6 and Figure 1.1 and 1.2.

Financial results

are most sensitive to grade, exchange rate and molybdenum price changes and least sensitive to capital

expenditures and operating costs.

Table 1.5

Sensitivity Analysis for After-Tax NPV

Parameter

After-Tax NPV 8% ($ million)

Parameter

-20%

-15%

-10%

-5%

0%

5%

10%

15%

20%

Mined Grade

114

313

473

635

790

945

1100

1254

1409

Molybdenum Price

-302

-31

265

526

790

1061

1344

1641

1948

Operating Costs

1071

1001

931

862

790

719

649

573

502

Capital Costs

865

846

828

808

790

771

753

734

716

US$:CAD$ Exchange Rate

273

407

536

666

790

915

1038

1161

1284

Table 1.6

Sensitivity Analysis for After-Tax IRR

Parameter

After-Tax IRR (%)

-20%

-15%

-10%

-5%

0%

5%

10%

15%

20%

Mined Grade

14

21

28

34

40

46

52

58

64

Molybdenum Price

-7

7

19

30

40

51

62

73

84

Operating Costs

52

49

46

43

40

37

35

31

28

Capital Costs

50

48

45

43

40

38

37

35

33

US$:CAD$ Exchange Rate

19

25

30

36

40

45

50

55

59

Figure 1.1

Graph of Net Present Value (NPV) at 8% Discount Rate

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/275365_figure1.1.jpg

Figure 1.2

Graph of IRR Sensitivity Analysis

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/275365_figure1.2.jpg

POTENTIAL PROJECT ENHANCEMENTS

Preliminary assessment of shovel/excavator whole bucket ore and waste differentiation has been

investigated.

This would potentially facilitate better in-pit grade control and minimize waste rock sent to

the processing plant for beneficiation.

In-bucket sensors determine if a loaded bucket of material is ore

or waste, for placing in the appropriate truck for transport to the primary crusher or waste storage areas.

OPS technology, whereby rock exiting the primary crushers can be screened for an optimum size, should

be further investigated.

There is currently a 5-tonne representative sample of rock from the Endako pit

undergoing testing at a reputable vendor and manufacturer of OPS equipment.

RECOMMENDATIONS

Based on this PEA, Endako Mine restart recommendations are:

Complete a Feasibility Study for mine restart using a mining and processing rate of approximately

75,000 tonnes per day (27 million tonnes per year) of potentially economic mineralization.

For the Feasibility Study, develop a new geology block model for use in resources estimation,

using geological data owned by the joint venture company. A new model should be constructed

using metric measures consistent with present Canadian practice and to avoid potential errors

with conversions using a mix of Metric and Imperial measures.

Undertake diamond drilling on nearby known targets of potential resources to expand potentially

mineable resources and increase the LOM.

Develop an updated or new detailed water management model which would include hydrology and

tailings management facility leachate seepage data and forecasts.

Investigate the use of excavator/shovel bucket ore sensing technology and OPS technology for

inclusion in the Feasibility Study.

Non-IFRS Financial Measures