Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MOO.V ·

Moon River Moly Announces Robust Updated Positive Preliminary Economic Assessment of Davidson Molybdenum-Copper-Tungsten Project Demonstrating Improved Economics

Economic Studies

Moon River Moly Announces Robust Updated

Positive Preliminary Economic Assessment of

Davidson Molybdenum-Copper-Tungsten

Project Demonstrating Improved Economics

HIGHLIGHTS:

Pre-tax net present value ("

NPV

") of $1.747 billion and Internal Rate of Return ("

IRR

") of 42% and

an after-tax NPV of $1.034 billion and IRR of 32% at an 8% discount rate, assuming long-term

prices of US$49.59 per kilogram ("

kg

") or US$22.50 per pound ("

lb

") of molybdenum ("

Mo

");

US$8.93 per kg or US$4.06 per lb. of copper ("

Cu

") and US$300 per metric tonne unit ("

MTU

") or

US$13.60 per lb of tungsten ("

W

"); and a CAD:US dollar exchange rate of $0.74;

20-year mine life based on 10,000 tonnes of mill throughput per day or 3.65 million tonnes per

year;

Initial capital cost of $672.3 million including $106.3 million of contingency;

Annual average production of 6,020,000 kg or 13,243,000 pounds of Mo; 679,600 kg or

1,498,500 lbs of Cu and 151.7 tonnes or 334,300 lbs of W;

Average cash cost of $22.11 per kg or $10.03 per lb of Mo and All-In Sustaining Cost ("

AISC

") of

$22.80 per kg or $10.34 per lb of Mo, net of Cu and W production credits;

Underground mine, with underground processing facilities, using primarily battery powered mining

equipment minimizes the surface footprint, resulting in a very low carbon emitting operation;

A measured and indicated ("

M & I"

) mineral resource of 80,756,000 tonnes grading 0.304%

MoS

2

(0.182% Mo) and 0.037% Cu and an inferred ('

inferred

") mineral resource of 83,100,000

tonnes grading 0.036% WO

3

;

A 2.3-year payback;

Life-of-mine direct income and mining taxes in excess of $1.743 billion; and

The break-even cut-off grade for the mine, excluding credits from copper and tungsten revenue, is

0.11% MoS

2

.

This results in a potentially mineable M&I MoS2 and Cu resource, in excess of 436

million tonnes for a potential mine life of ~120 years.

For the purposes of the updated Preliminary

Economic Assessment ("

PEA

"), a cut-off grade of 0.22% MoS

2

was used and this would give the

Project a 20-year mine life.

All dollar amounts are stated in Canadian Dollars unless otherwise noted.

Toronto, Ontario--(Newsfile Corp. - December 23, 2025) - Moon River Moly Ltd.

(TSXV: MOO)

(OTCQB: MRIVF)

("

Moon River

" or the "

Company

") is pleased to announce that an updated PEA has

been completed on the Davidson Molybdenum-Copper-Tungsten-Project (the "

Proje

ct" or "

Davidson

Property

") located near Smithers, British Columbia.

Paul Parisotto, President and Chief Executive Officer, says of the updated PEA results: "We are very

encouraged from the results of the updated PEA. The major differences between the initial PEA issued

in February 2024, and this updated PEA are an increase in daily production from 7,000 tonnes per day

to 10,000 tonnes per day and the inclusion of revenue from tungsten and copper production. Additionally,

the potential to increase the mine life to more than 100 years is very positive."

Ian McDonald, Chairman, went on to state: "My involvement with this Project first began over twenty

years ago, and I truly believe that the time for its development has arrived. These robust economics

together with its location in a Tier One jurisdiction in a mining-friendly province, to produce products that

are included on Canada's 2021 Critical Mineral List, near developed infrastructure, including roads, rail,

power, and the nearby town of Smithers are definite benefits. Additionally, to be able to take advantage

of the province's hydro-electric power grid, allows for the use of an efficient electric mining fleet, and will

make the Davidson Property one of the lowest carbon-emitting sources of molybdenum in the world. As

an underground mine, with an underground processing plant and with most of the tailings used as

backfill, the surface footprint of this mining operation will be minimized."

The updated PEA was prepared by A-Z Mining Professionals Ltd. ("

AMPL

") for Moon River.

The

Project, located in west central British Columbia, is approximately nine kilometres ("

km

") northwest of

the town of Smithers.

On November 15, 2023, Moon River acquired all of the rights, interests and

obligations of Generation Mining Ltd. under a vending agreement dated April 1, 2016, as amended,

entered into with Roda Holdings Inc. and Mr. Donald Davidson, thus granting Moon River the exclusive

right to access, prospect, develop and mine the Davidson Property and to acquire 100% of the

Davidson Property.

The Project comprises development of an underground mine with potentially

economic mineralization processed in an underground, on-site processing facility, with an estimated 20-

year mine life.

PROJECT DESIGN

The Davidson Deposit is located inside Hudson Bay Mountain and does not outcrop on surface.

The

deposit has an existing portal on the east side of the mountain and over 2,100 metres ("

m

") of

exploration drifting.

The access road and portal can be seen from the town of Smithers.

The proposed

underground mine access and surface facilities will be located on the west side of the mountain (out of

sight of the town of Smithers) with the existing eastern portal used only for initial development.

To minimise the surface footprint of the whole operation, the processing plant will be located

underground in specially designed and excavated openings at the top elevation of the mining zones.

This

eliminates having to move mineralized material from the underground to a surface processing plant 8 km

away.

This also eliminates material for processing being trucked to surface and the need for a source of

backfill material from surface as well.

The mill tailings will provide a ready source of material for

backfilling mined areas and significantly reduces the size of the tailings management facility on surface.

Additionally, the incorporation of dry stacked tailings eliminates need for a traditional hydraulic tailings

storage facility.

The mine will utilise already proven rubber-tired, battery-powered and automated mining equipment

wherever possible to minimize manpower requirements, underground ventilation volumes, mine air

heating costs and CO

2

emissions.

Surface infrastructure required would include:

Upgrading of access road

Powerline construction

Electrical substations and distribution

Site roads and materials handling area

Maintenance shop/offices/dry/warehouse complex (temporary)

Two cement storage silos

Water supply system and water treatment plant

Dry stack tailings dewatering plant and impoundment area

Development waste storage

Landfill site

Sewage disposal site

The mine will employ 238 persons once in full operation.

During pre-production, a contractor workforce

will be employed.

There is a history of mining in the region and many skilled workers in the area currently

work from Smithers that has a population of 5,400 people and many support services.

MINE PLAN

Underground mining methods will be utilised to extract the potentially economic mineralization of the

deposit. An underground internal ramp from the bottom to the top of the mining zone will access mining

areas and the underground processing plant facility. In total, some 36,000 m of pre-production

development will be required to bring the deposit into production.

The mining method to be employed would be Longhole Open Stoping with cemented paste (densified

tailings) backfill to maximise recovery of potentially economic mineralization.

Dilution of 5% has been

included in the mined potentially economic mineralization at a grade of 0.20% MoS

2

.

The mineralized zone is large and irregular shaped, with higher grade concentrations towards the centre

of the mineralized zones being mined. The mine would produce 10,000 tonnes per day of potentially

economic mineralization.

The mineralized zone geometry is highly amenable to bulk mining of large

tonnage stopes with inherent economies of scale and low mining costs.

The stopes will be approximately

160,000 tonnes each.

Figure 1 Underground Mine Design

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/278892_6d9fac0cd4fac82b_001full.jpg

Potentially economic mineralization removed from stopes by load-haul-dump (LHD) units will be sent by

ore passes to jaw crushers at the bottom of the mine, to a coarse ore bin and then to secondary and

tertiary cone crushers below the coarse ore bin.

The crushed potentially economic mineralisation will be

conveyed to a vertical lift conveyor system which feeds the fine ore bin connected to the underground

processing facility.

Other underground facilities will include:

Paste backfill plant

Equipment maintenance shops and underground warehouses

Explosives storage magazines

Refuge stations

Fuel bays

Materials storage areas

Main dewatering sumps

Offices

Warehousing facilities

PROCESSING

The processing plant, located completely underground, will be a conventional flotation plant producing

molybdenum, tungsten and copper concentrates for shipment to smelters.

The potentially economic mineralization from the fine ore bin will feed two grinding lines, each consisting

of one rod mill, one ball mill, and a set of cyclones for classification.

Each grinding line cyclone overflow

stream will feed a dedicated molybdenum rougher flotation line using tank cells, with rougher concentrate

advancing to molybdenum cleaning and tails continuing to pyrite flotation.

Molybdenum rougher concentrate will be cleaned in a circuit using four stages of column flotation and

one stage of stirred-mill regrinding to produce a final concentrate.

The molybdenum final concentrate

stream will be thickened, filtered, dried, and packaged for shipment to a smelter while first cleaner tails

molybdenum values will be scavenged in tank cells.

Byproduct copper will be recovered from the molybdenum cleaner scavenger flotation tails stream using

tank cells for copper rougher flotation and a column cell for cleaning.

Copper rougher tails will report to

the final tailings thickener, while copper concentrate will be thickened and filtered prior to shipment to a

smelter.

Pyrite flotation will be used to prepare molybdenum rougher flotation tails for tungsten recovery, with

flotation occurring in tank cells.

The pyrite flotation concentrate will report to the final tails thickener, while

the remaining desulphurised tailings will report to batch centrifugal gravity concentrators for recovery of

scheelite.

The concentrate from the centrifuges will be sorted into fine and coarse fractions using high-

frequency slurry screens, with each stream feeding a dedicated set of shaking tables for cleaning.

Tungsten concentrate will be filtered and packaged for shipment to a refinery, while tungsten tailings will

report to the final tailings thickener.

The tailings thickener underflow will be primarily made into paste backfill for backfilling of stopes, with the

balance pumped to a dry stack tailings facility on surface.

At the dry stack tailings facility, the tailings will

be filtered for water removal, with the filter product being stacked in a near dry form for permanent

storage and the water removed being sent to surface storage pond for re-use in the processing plant.

The processing plant is expected to have a recovery rate of 94.4% molybdenum, 52.4% copper and

15.5% tungsten into concentrate.

The proposed processing plant will be arranged to fit in a long room.

Grinding mills will be located at one

end of the room, with grinding cyclone overflow gravitating to molybdenum rougher flotation and

subsequently through pyrite flotation.

The molybdenum cleaner flotation and byproduct recovery circuits

will be located at the opposite end of the room from the grinding circuits.

The construction cost of an

underground plant is not significantly different from that for a plant located on surface.

MINERAL RESOURCES

The data used to generate the resource calculation was reviewed and approved by F. Bakker P.Geo.

This included a site visit by Mr. Bakker (July 30, 2024, to August 26, 2024). Sampling methods, QAQC

programs and databases were examined. In addition, he supervised a diamond drill program that was

used to gather metallurgical samples. Mr. Bakker is of the opinion that the accuracy of the data was

sufficient for a mineral resource statement.

The mineral resource was calculated utilizing commercial 3D Block Modelling Software (HxGN Mine

Plan

tm

3D). For the current mineral resource estimate, a mineralized solid was constructed around a

roughly designed and manually constrained 0.1% MoS

2

grade shell to constrain the estimate. In addition,

the model utilized geostatistics (variograms) to better confine mineralized limits. This resource model

was used for determining the mineral resources estimate and to undertake an underground mine

production plan.

The effective date of the mineral resource is December 23, 2025, the date of this news release.

Mr. Bakker is unaware of any known legal, political, environmental, or other risks that could materially

affect the potential development of the mineral resources or mineral reserves.

With the exception of tungsten, inferred mineral resources were not included in the PEA economic

analysis. The PEA is preliminary in nature and includes inferred mineral resources that are considered

too speculative geologically to have the economic considerations applied to them that would enable

them to be categorized as mineral reserves. There is no certainty that the PEA will be realized.

The following tables present the mineral resource estimate for the Davidson Property at various cut-off

grades.

The mineral resource estimate has been recalculated to include both copper and tungsten values in the

Davidson Property and is included in the updated PEA.

TABLE 1:

MEASURED MINERAL RESOURCES for MoS

2

and Copper

Category

Cut-off Grade

%MoS

2

Tonnes

Grade

MoS

2

Grade

%Mo

Grade

%Cu

Contained

Mo kg

Contained

Cu kg

Measured

>0.100

128,457,000

0.203

0.122

0.036

156,354,000

46,630,000

Measured

>0.110

118,655,000

0.211

0.127

0.037

150,180,000

43,546,000

Measured

>0.120

107,899,000

0.221

0.132

0.037

142,836,000

40,138,000

Measured

>0.130

97,680,000

0.231

0.138

0.038

135,217,000

36,923,000

Measured

>0.140

88,115,000

0.242

0.145

0.039

127,519,000

33,924,000

Measured

>0.150

79,982,000

0.251

0.151

0.039

120,444,000

31,193,000

Measured

>0.160

72,442,000

0.262

0.157

0.039

113,472,000

28,470,000

Measured

>0.170

65,205,000

0.272

0.163

0.040

106,354,000

25,821,000

Measured

>0.180

58,803,000

0.283

0.170

0.040

99,681,000

23,462,000

Measured

>0.190

53,103,000

0.294

0.176

0.040

93,390,000

21,294,000

Measured

>0.200

47,928,000

0.304

0.182

0.040

87,361,000

19,315,000

Measured

>0.210

42,771,000

0.316

0.189

0.041

81,036,000

17,322,000

Measured

>0.220

38,418,000

0.328

0.196

0.041

75,458,000

15,559,000

Measured

>0.230

34,406,000

0.340

0.204

0.041

70,051,000

13,969,000

Measured

>0.240

30,973,000

0.352

0.211

0.041

65,232,000

12,606,000

Measured

>0.250

27,866,000

0.364

0.218

0.041

60,691,000

11,369,000

Measured

>0.260

25,079,000

0.376

0.225

0.041

56,439,000

10,232,000

Measured

>0.270

22,584,000

0.388

0.232

0.041

52,488,000

9,192,000

Measured

>0.280

20,417,000

0.400

0.240

0.041

48,931,000

8,310,000

Measured

>0.290

18,456,000

0.412

0.247

0.041

45,591,000

7,512,000

Measured

>0.300

16,786,000

0.424

0.254

0.041

42,642,000

6,798,000

Measured

>0.310

15,242,000

0.436

0.261

0.040

39,825,000

6,143,000

Measured

>0.320

13,869,000

0.448

0.269

0.040

37,243,000

5,575,000

1

.

Mineral Resources were estimated using the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

2

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3

.

The PEA mine plan and economic model include numerous assumptions and the use of Inferred Resources.

Inferred Resources are

considered to be too speculative geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves and to be used in an economic analysis except as allowed for by NI 43-101 in PEA studies. There is no guarantee that

Inferred Resources can be converted to Indicated or Measured Resources, and as such, there is no guarantee the economics described

herein will be achieved.

4

.

The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

5

.

The approximate 3-year trailing average (to November 30, 2025) metal price for molybdenum of US$49.59 per kg or US$22.50 (rounded

down) per lb),US$300 per MTU or US$13.60 per pound W, and US$8.93 per kg or US$4.06 per pound Cu was used in estimating the Mineral

Resources and a CAD:US Dollar exchange rate of $0.74 was used.

6

.

A description of the key assumptions, parameters, and methods used to estimate the resources, and any known risks, as well as the data

verification processes, will be contained in this Technical Report.

TABLE 2:

INDICATED MINERAL RESOURCES for MoS

2

and Copper

Category

Cut-off Grade

%MoS

2

Tonnes

Grade Mo

S

2

Grade

%Mo

Grade

%Cu

Contained

Mo kg

Contained

Cu kg

Indicated

>0.100

360,595,000

0.159

0.095

0.028

343,434,000

102,048,000

Indicated

>0.110

317,987,000

0.166

0.100

0.029

316,568,000

90,626,000

Indicated

>0.120

270,065,000

0.176

0.105

0.029

283,904,000

79,129,000

Indicated

>0.130

229,447,000

0.185

0.111

0.030

253,574,000

68,146,000

Indicated

>0.140

192,639,000

0.194

0.116

0.030

223,858,000

58,177,000

Indicated

>0.150

158,417,000

0.205

0.123

0.031

194,338,000

48,476,000

Indicated

>0.160

130,259,000

0.216

0.129

0.031

168,300,000

40,250,000

Indicated

>0.170

107,639,000

0.227

0.136

0.031

146,038,000

33,691,000

Indicated

>0.180

88,553,000

0.238

0.142

0.031

126,084,000

27,806,000

Indicated

>0.190

72,355,000

0.250

0.150

0.032

108,222,000

23,009,000

Indicated

>0.200

60,443,000

0.261

0.156

0.032

94,351,000

19,281,000

Indicated

>0.210

50,863,000

0.271

0.162

0.032

82,626,000

16,429,000

Indicated

>0.220

42,338,000

0.283

0.169

0.033

71,694,000

13,929,000

Indicated

>0.230

35,902,000

0.293

0.176

0.033

63,032,000

11,884,000

Indicated

>0.240

30,579,000

0.303

0.182

0.033

55,573,000

9,938,000

Indicated

>0.250

26,202,000

0.313

0.188

0.032

49,172,000

8,463,000

Indicated

>0.260

22,474,000

0.323

0.193

0.032

43,482,000

7,192,000

Indicated

>0.270

18,572,000

0.335

0.201

0.033

37,301,000

6,073,000

Indicated

>0.280

15,548,000

0.347

0.208

0.033

32,326,000

5,177,000

Indicated

>0.290

12,867,000

0.360

0.216

0.035

27,762,000

4,452,000

Indicated

>0.300

10,932,000

0.372

0.223

0.035

24,353,000

3,837,000

Indicated

>0.310

9,292,000

0.384

0.230

0.035

21,362,000

3,289,000

Indicated

>0.320

8,123,000

0.394

0.236

0.036

19,161,000

2,884,000

1

.

Mineral Resources were estimated using the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

2

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3

.

The PEA mine plan and economic model include numerous assumptions and the use of Inferred Resources.

Inferred Resources are

considered to be too speculative geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves and to be used in an economic analysis except as allowed for by NI 43-101 in PEA studies. There is no guarantee that

Inferred Resources can be converted to Indicated or Measured Resources, and as such, there is no guarantee the economics described

herein will be achieved.

4

.

The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

5

.

The approximate 3-year trailing average (to November 30, 2025) metal price for molybdenum of US$49.59 per kg or US$22.50 (rounded

down) per lb),US$300 per MTU or US$13.60 per pound W, and US$8.93 per kg or US$4.06 per pound Cu was used in estimating the Mineral

Resources and a CAD:US Dollar exchange rate of $0.74 was used.

6

.

A description of the key assumptions, parameters, and methods used to estimate the resources, and any known risks, as well as the data

verification processes, will be

contained in the Technical Report.

TABLE 3:

MEASURED + INDICATED MINERAL RESOURCES for MoS

2

and Copper

Category

Cut-off Grade

%MoS

2

Tonnes

Grade

MoS

2

Grade

%Mo

Grade

%Cu

Contained

Mo kg

Contained

Cu kg

Measured + Indicated

>0.100

489,053,000

0.171

0.102

0.030

499,789,000

148,679,000

Measured + Indicated

>0.110

436,642,000

0.178

0.107

0.031

466,748,000

134,173,000

Measured + Indicated

>0.120

377,964,000

0.188

0.113

0.032

426,740,000

119,267,000

Measured + Indicated

>0.130

327,127,000

0.198

0.119

0.032

388,792,000

105,069,000

Measured + Indicated

>0.140

280,754,000

0.209

0.125

0.033

351,377,000

92,101,000

Measured + Indicated

>0.150

238,399,000

0.220

0.132

0.033

314,782,000

79,669,000

Measured + Indicated

>0.160

202,701,000

0.232

0.139

0.034

281,772,000

68,720,000

Measured + Indicated

>0.170

172,844,000

0.244

0.146

0.034

252,392,000

59,512,000

Measured + Indicated

>0.180

147,356,000

0.256

0.153

0.035

225,765,000

51,268,000

Measured + Indicated

>0.190

125,459,000

0.268

0.161

0.035

201,614,000

44,304,000

Measured + Indicated

>0.200

108,371,000

0.280

0.168

0.036

181,712,000

38,596,000

Measured + Indicated

>0.210

93,634,000

0.292

0.175

0.036

163,662,000

33,751,000

Measured + Indicated

>0.220

80,756,000

0.304

0.182

0.037

147,152,000

29,489,000

Measured + Indicated

>0.230

70,308,000

0.316

0.189

0.037

133,083,000

25,852,000

Measured + Indicated

>0.240

61,552,000

0.328

0.196

0.037

120,805,000

22,544,000

Measured + Indicated

>0.250

54,068,000

0.339

0.203

0.037

109,864,000

19,833,000

Measured + Indicated

>0.260

47,554,000

0.351

0.210

0.037

99,923,000

17,424,000

Measured + Indicated

>0.270

41,156,000

0.364

0.218

0.037

89,789,000

15,265,000

Measured + Indicated

>0.280

35,965,000

0.377

0.226

0.038

81,258,000

13,487,000

Measured + Indicated

>0.290

31,323,000

0.391

0.234

0.038

73,353,000

11,964,000

Measured + Indicated

>0.300

27,718,000

0.404

0.242

0.038

66,996,000

10,635,000

Measured + Indicated

>0.310

24,534,000

0.416

0.249

0.038

61,187,000

9,432,000

Measured + Indicated

>0.320

21,992,000

0.428

0.256

0.038

56,404,000

8,459,000

1

.

Mineral Resources were estimated using the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

2

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3

.

The PEA mine plan and economic model include numerous assumptions and the use of Inferred Resources.

Inferred Resources are

considered to be too speculative geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves and to be used in an economic analysis except as allowed for by NI 43-101 in PEA studies. There is no guarantee that

Inferred Resources can be converted to Indicated or Measured Resources, and as such, there is no guarantee the economics described

herein will be achieved.

4

.

The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

5

.

The approximate 3-year trailing average (to November 30, 2025) metal price for molybdenum of US$49.59 per kg or US$22.50 (rounded

down) per lb),US$300 per MTU or US$13.60 per pound W, and US$8.93 per kg or US$4.06 per pound Cu was used in estimating the Mineral

Resources and a CAD:US Dollar exchange rate of $0.74 was used.

6

.

A description of the key assumptions, parameters, and methods used to estimate the resources, and any known risks, as well as the data

verification processes, will be contained in this Technical Report.

TABLE 4:

INFERRED RESOURCES for MoS

2

and Copper

Category

Cut-off Grade

%MoS

2

Tonnes

Grade

MoS

2

Grade

%Mo

Grade

%Cu

Contained

Mo kg

Contained

Cu kg

Inferred

>0.100

29,114,000

0.1504

0.0900896

0.0213

26,229,000

6,201,000

Inferred

>0.110

24,995,000

0.158

0.094642

0.0204

23,656,000

5,099,000

Inferred

>0.120

20,359,000

0.1679

0.1005721

0.0202

20,475,000

4,113,000

Inferred

>0.130

16,734,000

0.1773

0.1062027

0.0196

17,772,000

3,280,000

Inferred

>0.140

14,233,000

0.185

0.110815

0.0193

15,772,000

2,747,000

Inferred

>0.150

11,574,000

0.1943

0.1163857

0.019

13,470,000

2,199,000

Inferred

>0.160

9,094,000

0.2052

0.1229148

0.0176

11,178,000

1,601,000

Inferred

>0.170

7,257,000

0.2156

0.1291444

0.0172

9,372,000

1,248,000

Inferred

>0.180

6,059,000

0.2237

0.1339963

0.0154

8,119,000

933,000

Inferred

>0.190

4,873,000

0.2334

0.1398066

0.0141

6,813,000

687,000

Inferred

>0.200

3,494,000

0.2484

0.1487916

0.0126

5,199,000

440,000

Inferred

>0.210

2,861,000

0.2583

0.1547217

0.0132

4,427,000

378,000

Inferred

>0.220

2,444,000

0.2657

0.1591543

0.0131

3,890,000

320,000

Inferred

>0.230

2,037,000

0.2736

0.1638864

0.0141

3,338,000

287,000

Inferred

>0.240

1,725,000

0.2813

0.1684987

0.0144

2,907,000

248,000

Inferred

>0.250

1,591,000

0.2845

0.1704155

0.0134

2,711,000

213,000

Inferred

>0.260

1,447,000

0.2873

0.1720927

0.0129

2,490,000

187,000

Inferred

>0.270

1,072,000

0.2952

0.1768248

0.0144

1,896,000

154,000

Inferred

>0.280

477,000

0.3209

0.1922191

0.0179

917,000

85,000

Inferred

>0.290

357,000

0.3337

0.1998863

0.0156

714,000

56,000

Inferred

>0.300

246,000

0.3522

0.2109678

0.0218

519,000

54,000

Inferred

>0.310

190,000

0.3663

0.2194137

0.0249

417,000

47,000

Inferred

>0.320

180,000

0.3693

0.2212107

0.0237

398,000

43,000

1

.

Mineral Resources were estimated using the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

2

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3

.

The PEA mine plan and economic model include numerous assumptions and the use of Inferred Resources.

Inferred Resources are

considered to be too speculative geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves and to be used in an economic analysis except as allowed for by NI 43-101 in PEA studies. There is no guarantee that

Inferred Resources can be converted to Indicated or Measured Resources, and as such, there is no guarantee the economics described

herein will be achieved.

4

.

The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

5

.

The approximate 3-year trailing average (to November 30, 2025) metal price for molybdenum of US$49.59 per kg or US$22.50 (rounded

down) per lb),US$300 per MTU or US$13.60 per pound W, and US$8.93 per kg or US$4.06 per pound Cu was used in estimating the Mineral

Resources and a CAD:US Dollar exchange rate of $0.74 was used.

6

.

A description of the key assumptions, parameters, and methods used to estimate the resources, and any known risks, as well as the data

verification processes, will be contained in this Technical Report.

TABLE 5:

INFERRED RESOURCES for WO

3

Category

Cut-off Grade

%MoS

2

Tonnes

Grade

% WO

3

Contained

WO

3

kg

Inferred

>0.100

518,167,000

0.02988995

154,880,000

Inferred

>0.110

461,637,000

0.03016908

139,272,000

Inferred

>0.120

398,323,000

0.03097485

123,380,000

Inferred

>0.130

343,861,000

0.03150943

108,349,000

Inferred

>0.140

294,987,000

0.03215335

94,848,000

Inferred

>0.150

249,973,000

0.03275059

81,868,000

Inferred

>0.160

211,795,000

0.03320204

70,320,000

Inferred

>0.170

180,101,000

0.03373683

60,760,000

Inferred

>0.180

153,415,000

0.03402611

52,201,000

Inferred

>0.190

130,332,000

0.03452003

44,991,000

Inferred

>0.200

111,865,000

0.03489613

39,037,000

Inferred

>0.210

96,495,000

0.03536832

34,129,000

Inferred

>0.220

83,200,000

0.03582775

29,809,000

Inferred

>0.230

72,345,000

0.03613186

26,140,000

Inferred

>0.240

63,277,000

0.03602033

22,793,000

Inferred

>0.250

55,659,000

0.03601538

20,046,000

Inferred

>0.260

49,001,000

0.03593993

17,611,000

Inferred

>0.270

42,228,000

0.03651392

15,419,000