Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MOO.V ·

Moon River Capital Ltd. Announces Robust Positive Preliminary Economic Assessment of Davidson Molybdenum Project

Economic Studies

Moon River Capital Ltd. Announces Robust

Positive Preliminary Economic Assessment of

Davidson Molybdenum Project

HIGHLIGHTS:

Pre-tax net present value ("NPV") of $1.04 billion and Internal Rate of Return ("IRR") of 32% and an

after-tax NPV of $602 million and an IRR of 24% at an 8% discount rate and assuming a long-term

molybdenum("Mo") price of $US47.39 per ('kg") or $US21.50 per pound ("lb");

20-year mine life based on 7,000 tonnes of mill throughput per day or 2.5 million tonnes per year;

Initial capital cost of $575 million including $109 million of contingency;

Annual average production of 4,543,000 kg or 10,015,500 pounds of Mo;

Average cash cost of $21.68 per kg or $9.84 per lb and All-In Sustaining Cost ("AISC") of $22.79

per kg or $10.34 per lb of Mo;

Underground mine, with underground processing facilities, using all electric mining equipment

minimizes the surface footprint, resulting in a very low carbon emitting operation;

A measured and indicated mineral resource of 43,896,000 tonnes grading 0.35% MoS

2

(0.21%

Mo);

A 3.3-year payback;

Life-of-mine direct income and mining taxes in excess of $1 billion;

Does not include potential byproduct contributions from tungsten, rare earth elements, gallium and

copper; and

Additional drilling to support metallurgical test work to determine the economic recoverability of

potential byproduct metals is scheduled to commence when applicable First Nations consultations

have been undertaken and drill permits have been obtained.

An updated PEA will follow.

All dollar amounts are stated in Canadian Dollars unless otherwise noted.

Toronto, Ontario--(Newsfile Corp. - February 22, 2024) - Moon River Capital Ltd.

(TSXV: MOO)

("

Moon

River

" or the "

Company

") is pleased to announce that a Preliminary Economic Assessment ('PEA")

has been completed on the Davidson Molybdenum Project (the "Project") located near Smithers, British

Columbia.

Paul Parisotto, President and Chief Executive Officer, says of the PEA results:

"This study presents a

very convincing case for the rapid development of the Davidson Molybdenum Project.

Its location in

British Columbia is near developed infrastructure, including roads, rail, power, and the nearby town of

Smithers. It would be able to take advantage of the province's hydro-electric power grid.

That, together

with the use of an electric mining fleet, will make Davidson one of the lowest carbon-emitting sources of

molybdenum in the world. As an underground mine, with an underground processing plant and with most

of the tailings used as backfill, the surface footprint of this mining operation will be minimal."

Ian McDonald, Chairman, went on to state: "My involvement with this project first began twenty years ago,

and I truly believe that the time for its development has arrived. These compelling robust economics

together with a Tier One jurisdiction in a mining-friendly province, to produce a product that was included

on Canada's 2021 Critical Mineral List by the federal government, make development of the Project very

attractive at this time."

Join Ian McDonald, Chairman and Paul Parisotto, President and CEO for a LIVE virtual event to learn

more about this PEA, receive a broader market update, and ask questions during the interactive Q&A.

Date and time: Week of February 26th, exact date and time TBD.

Click here to register for the event

The PEA was prepared by A-Z Mining Professionals Ltd. ("AMPL") for Moon River.

The Project, located

in west central British Columbia, is approximately 9 kilometres ("km") northwest of the town of Smithers.

On November 15, 2023, Moon River acquired all of the rights, interests and obligations of Generation

Mining Ltd. under a vending agreement dated April 1, 2016, as amended, entered into with Roda

Holdings Inc. and Mr. Donald Davidson (the "Davidson Agreement"), thus granting Moon River the

exclusive right to access, prospect, develop and mine the Davidson Property and to acquire 100% of the

Davidson Property.

The Project comprises development of an underground mine with potentially

economic mineralization processed in an underground, on-site processing facility, with an estimated 20-

year mine life.

PROJECT DESIGN

The Davidson Deposit is located inside Hudson Bay Mountain and does not outcrop on surface.

The

deposit has an existing portal on the east side of the mountain and over 2,100 metres ('m") of

exploration drifting.

The access road and portal can be seen from the town of Smithers.

The proposed

underground mine access and surface facilities will be located on the west side of the mountain (out of

sight of the town of Smithers) with the existing eastern portal used only for initial development.

To minimise the surface footprint of the whole operation, the processing plant will be located

underground in specially designed and excavated openings at the top elevation of the mining zones.

This

eliminates having to move mineralized material from the underground to a surface processing plant 8 km

away.

This also eliminates material for processing being trucked on surface and the need for a source of

backfill material from surface as well.

The mill tailings will provide a ready source of material for

backfilling mined areas and significantly reduces the size of the tailings management facility on surface.

The mine will utilise already proven rubber-tired, battery-powered and automated mining equipment

wherever possible to minimize manpower requirements, underground ventilation volumes, mine air

heating costs and CO

2

emissions.

Surface infrastructure required would include:

Upgrading of access road

Powerline construction

Electrical substations and distribution

Site roads and materials handling area

Maintenance shop/offices/dry/warehouse complex (temporary)

Two cement storage silos

Water supply system and water treatment plant

Dry stack tailings impoundment area

Development waste storage

Landfill site

Sewage disposal site

The mine will employ 207 persons in the operation.

During pre-production, a contractor workforce will be

employed, most on a fly-in/fly-out work rotation with major population centres in Canada.

During

production no fly-in/fly-out personnel are included in the plan.

There is a history of mining in the region

and many skilled workers in the area currently work from Smithers that has a population of 5,400 people

and many support services.

MINE PLAN

Underground mining methods will be utilised to extract the potentially economic mineralization of the

deposit. An underground internal ramp from the bottom to the top of the mining zone will access mining

areas and the underground processing plant facility. In total, some 34,000 m of development will be

required to bring the deposit into production.

The mining method to be employed would be Longhole Open Stoping with cemented paste (densified

tailings) backfill to maximise recovery of potentially economic mineralization.

Dilution of 5% has been

included in the mined potentially economic mineralization at a grade of 0.18% MoS

2

.

The mineralized zone is large and irregular shaped, with higher grade concentrations towards the centre

of the mineralized zones being mined. The mine would produce 7,000 tonnes per day of potentially

economic mineralization.

The mineralized zone geometry is highly amenable to bulk mining of large

tonnage stopes with inherent economies of scale and low mining costs.

The stopes will be approximately

160,000 tonnes each.

Figure 1 Underground Mine Design

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/198827_e1a1afec84bd8880_001full.jpg

Potentially economic mineralization removed from stopes by load-haul-dump (LHD) units will be sent by

ore passes to jaw crushers at the bottom of the mine and then to a secondary cone crusher.

The crushed

potentially economic mineralisation will be conveyed to a vertical lift conveyor system which feeds the

fine ore bin connected to the underground processing facility.

Other underground facilities will include:

Paste backfill plant

Equipment maintenance shops and underground warehouses

Explosives storage magazines

Refuge stations

Fuel bays

Materials storage areas

Main dewatering sumps

Offices

Warehousing facilities

PROCESSING

The processing plant, located completely underground, will be a conventional flotation plant producing a

molybdenum concentrate for shipment to smelters.

The potentially economic mineralization from the mine vertical lift conveyor system would feed the

grinding circuit consisting of two ball mills operating in parallel.

Flotation of the molybdenum concentrate

will comprise a rougher/scavenger circuit followed by two stages of concentrate cleaning, with regrind.

The concentrate stream from flotation will be filtered and dried for shipment to a smelter. The processing

plant is expected to have a recovery rate of 92% molybdenum into concentrate.

Large processing equipment (crushers and grinding mills) will be located in individual opening rooms

and interconnected with piping.

Other smaller equipment will be installed in groupings in other opening

rooms.

The construction cost of an underground plant is not significantly different from that for a plant

located on surface.

The tailings will be primarily made into paste backfill for backfilling of stopes with the balance pumped to

a dry stack tailings facility where the water is removed, and tailings stacked in a near dry form in a

permanent storage facility.

MINERAL RESOURCES

Mineral Resources used for the PEA were based on the latest resource estimates calculated and

reported in a study completed by AMPL and presented in an NI 43-101 Technical Report entitled

"National Instrument NI 43-101 Technical Report for the Davidson Project Resources Update" dated

September 13, 2023 and filed on Sedar+.

Category

Cut-off

Grade MoS

2

Tonnes

Grade

MoS

2

Grade

Mo

Contained

Mo kg.

Contained

Mo lbs.

Measured

>0.25

24,269,000

0.37

0.22

53,800,000

118,609,000

Indicated

>0.25

19,627,000

0.32

0.19

37,600,000

82,894,000

M&I

>0.25

43,896,000

0.35

0.21

92,100,000

201,503,000

Inferred

>0.25

11,907,000

0.30

0.18

21,400,000

47,179,000

1

.

Mineral Resources were estimated using the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

2

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability."

3

.

The PEA mine plan and economic model include numerous assumptions and the use of Inferred Resources.

Inferred Resources are

considered to be too speculative geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves and to be used in an economic analysis except as allowed for by NI 43-101 in PEA studies. There is no guarantee that

Inferred Resources can be converted to Indicated or Measured Resources, and as such, there is no guarantee the economics described

herein will be achieved.

4

.

The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

5

.

The approximate 2-year trailing average (to January 31, 2024) metal price for molybdenum US$47.40 per ('kg") or US$21.50 per pound ("lb")

was used in estimating the Mineral Resources and a CAD:US Dollar exchange rate of $0.74 was used.

6

.

A description of the key assumptions, parameters, and methods used to estimate the resources, and any known risks, as well as the data

verification processes, are contained in the technical report entitled "National Instrument NI 43-101 Technical Report for the Davidson Project

Resources Update" dated September 13, 2023 and filed on SEDAR+.

CAPITAL EXPENDITURES

The estimated project total pre-production capital expenditure, inclusive of contingencies and working

capital, is approximately $575 million.

A summary of project pre-production capital expenditures is

presented in the following table.

Pre-Production Capital Expenditure

Component

Year -3

($'000)

Year -2

($'000)

Year -1

($'000)

Year 1

($'000)

Total

($'000)

Exploration

$

1,000

$

1,000

$

1,000

$

3,000

Mine

$

34,377

$

52,739

$

50,440

$

24,124

$

161,680

Equipment Leasing

$

9,441

$

8,952

$

8,462

$

26,855

Processing Plant

$

70,000

$

50,125

$

35,000

$

155,125

Underground Infrastructure

$

4,886

$

1,815

$

23,375

$

30,077

Surface Infrastructure & Mobile Equipment

$

23,636

$

1,463

$

13,361

$

38,461

Tailings Management Facilities

$

9,150

$

9,150

Owner's Costs

$

3,700

$

3,700

$

3,700

$

11,099

Contingency

$

18,039

$

35,685

$

34,513

$

20,625

$

108,862

Working Capital

$

20,679

$

20,679

Mine Closure

$

10,000

$

10,000

Total Pre-Production Capital Expenditures

$

90,193

$

178,425

$

182567

$

123,803

$

574,987

OPERATING COSTS

The estimated total average operating cost (excluding smelting and refining) for the mine is

approximately $38.24 per tonne of potentially economic mineralization. This equates to $21.68 per kg of

Mo ($9.84 per lb).

The following table presents a summary of life of mine average operating costs per

tonne.

Life of Mine Average Operating Costs

Co

mponent

C

ost

Diamond Drilling - Infill

$

0.50

Underground Mining

$

21.07

Processing

$

10.94

Tailings Management Facility

$

1.34

Mine Indirects

$

1.29

Surface Department

$

0.90

General & Administration

$

2.20

Total Minesite Operating Cost

$

38.24

ECONOMIC ANALYSIS

The expected cash flow estimates are calculated using the forecast mine plan, operating costs, and

capital expenditures incorporating expected long-term metal prices based on the two-year trailing

average of molybdenum on the London Metals Exchange of US $47.39 per kg or US$21.50 per pound.

A summary of the expected parameters used for the financial analysis is presented below.

Parameters Used in Financial Analysis

Parameter

Long term Metal Price

$US47.39/kg or $US21.50/lb.

CAD:US Dollar Exchange Rate

$0.74

Diluted Potentially Economic Resource

49,125,000 tonnes

Dilution

5% (with adjacent mineralization grade)

Average Millhead Grade

0.34% MoS

2

Recovery

92%

Payability

97%

Pre-Production Capital Expenditures

$575 million

Total Sustaining Capital Expenditures

$79 million

Working Capital included in Pre-Production Capex

$21 million

Reclamation & Closure Costs

$10 million

Estimated Operating Costs

$38.24/tonne

Life of Project

20 years

The overall level of accuracy of this study is approximately ±40%.

The Project's expected investment and returns based on the base case cashflow parameters for the

project are shown below.

Expected Project Returns

Pre-Tax

After Tax

Undiscounted Net Revenue

$

5.8 billion

$

5.8 billion

Undiscounted Total Cash Flow

$

3.0 billion

$

1.9 billion

NPV at 5%

$

1.5 billion

$

931 million

NPV at 8%

$

1.0 billion

$

602 million

NPV at 10%

$

815 million

$

447 million

IRR

32%

24%

Payback Period

3.3 Years

SENSITIVITY ANALYSIS

Sensitivity analyses were performed for capital expenditures, operating costs, mined grades, metal

prices and currency exchange rates using 25% positive and negative variations. The Project is most

sensitive to the mined grade, metal price and the exchange rate and less sensitive to capital and

operating costs.

The results of the sensitivity analysis for positive and negative changes of 25% in key

project parameters are presented in the following tables and graphs.

Sensitivity Analysis Net Present Values ($CAD million)

Parameter

After Tax NPV 8%

-25%

Base Case

25%

Capital Cost

705

602

498

Operating Cost

732

602

471

Mined Grade

219

602

984

Metal Price

217

602

986

Exchange Rate

219

602

984

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/198827_davidson.jpg

Note:

The lines for Grade, Metal price and Exchange Rate are virtually the same and overlay each other.

Sensitivity Analysis IRR

Parameter

After Tax IRR

-25%

Base Case

25%

Capital Cost

31%

24%

19%

Operating Cost

26%

24%

21%

Mined Grade

15%

24%

31%

Metal Price

14%

24%

31%

Exchange Rate

15%

24%

31%

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/7009/198827_davidsonirr.jpg

Note:

The lines for Grade and Metal Price are virtually the same and overlay each other.

Non-IFRS Financial Measures

The Company has included certain terms or performance measures commonly used in the mining

industry that are not defined under International Financial Reporting Standards ("IFRS") in this news

release.

These include Operating Costs, Cash Cost, AISC, Pre-Production Capital Expenditures,

Sustaining Capital Expenditures, Life of Mine Average Operating Costs. Non-IFRS measures do not

have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to

similar measures employed by other companies.

The data presented are intended to provide additional

information and should not be considered in isolation or as a substitute for measures prepared in

accordance with IFRS. Non-IFRS financial measures used in this news release and common to the

mining industry are defined.

Operating Costs include mining, processing, general and administrative, concentrate transportation

costs, treatment and refining charges, etc.

Cash costs include on-site mining costs plus on-site G&A, royalties/production taxes and

permitting/community costs related to current operations, less by-product credits, if any.

AISC include total cash costs plus reclamation costs, exploration and study costs, sustaining capital

exploration/development and sustaining capital expenditure."

POTENTIAL BY-PRODUCT OPPORTUNITY

As disclosed in the Company's press release dated January 24, 2024, the Company plans to undertake

preliminary metallurgical studies and obtain fresh samples from drill core to begin detailed metallurgical

testing, when applicable First Nations consultations are undertaken and drill permits obtained, to

determine whether the Rare Earth Elements, ("REEs"), tungsten, gallium and copper contained in the

Project are economically recoverable and can contribute to the economics of the Project.

REEs comprise 17 nearly indistinguishable silvery-white soft heavy metals. Compounds containing

REEs have diverse applications in electrical and electronic components, lasers, glass, magnetic

materials, and industrial processes.

They are deemed important for the world energy transition, being

used in wind turbines, electric vehicles, photovoltaic cells and fluorescent lighting.

They are also used in

LED lights, colour monitors and medical equipment. REEs were included on the Government of

Canada's Critical Mineral List released in 2021, and more recently were listed along with five other

metals as potentially qualifying for the draft Critical Minerals Tax Credit for new mine construction.

Several of the REEs are on the U.S. Department of Energy's and European Union's critical mineral lists.

Most of the world's REEs are produced in China, with the United States and Australia each supplying

smaller amounts.

Tungsten has a wide variety of uses, mainly in the production of hard materials - namely tungsten

carbide, in steel alloys and as a lubricant.

Gallium is a key component of semi-conductors and LED

lights. Both metals are on the critical mineral lists in the United States, Canada and the European Union.

Next Steps

The Company will commence additional metallurgical test work when applicable First Nations

consultations are undertaken and drill permits are obtained, to determine the economic recoverability of

potential byproduct contributions, followed by an updated PEA.

Technical Report & Qualified Persons