Monument Provides Update on Selinsing Gold Mine in Malaysia
Page 1 of 4
August 21, 2020 News Release Release #13 - 2020
Monument Provides Update on Selinsing Gold Mine in Malaysia
Vancouver, B.C., August 21, 2020, Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) (“Monument” or the
“Company”) provides an update on its wholly owned Selinsing Gold Mine in Pahang State, Malaysia.
CEO and President Cathy Zhai said: “Selinsing is our primary gold producing project. We continue to work hard
on several financing alternatives to upgrade the Selinsing Gold processing plant that will treat sulphide ore,
bringing the new life of mine into production. In the meantime, our operations team is also focused on
sustainability of gold production to bridge the gap during the conversion , enhancement of the sulphide project
design, and carrying out gold concentrate test work to top up the current and future production profile.”
Ms. Zhai continued with a brief on the corporate development: “I would like to take this opportunity to draw our
shareholders’ attention to a bigger picture that may help them understand the background of reported
development activities at Selinsing . Monument's first stage of corporate development has delivered two
portfolios of projects including gold and base metal from a single near production project - Selinsing Gold Mine
acquired 10 years ago. The second stage of corporate development is focused on the gold portfolio , include
Selinsing Gold Sulphide Project development and Murchison Gold Project. Both gold projects have cash
generation capacities subject to initial funding and blue sky potential. This gold portfolio is our foundation and
part of our future. Our base metal portfolio - Mengapur Copper and Iron Project has also provide d us
opportunities and we work on our strategy alternatives on it as well.”
Ms. Zhai commented further: “We believe in vision and persistence that will lead us to achieve our corporate
objectives, and we have made good progress in which we have not only be en evaluating the available
opportunities, but also creating new opportunities that we believe are in the best interests of our shareholders.
We will make an announcement when any opportunity becomes material.”
Gold Production
The Selinsing gold mine has been in commerc ial gold production since 2010, and has produced 312,916 oz of
gold, generating over $423 million in gold revenues and $268 million net cash since startup up to March 31, 2020;
15,048oz of gold were produced in the latest nine month period in fiscal 2020 , increased by 2,862oz or 24%
compared to 12,186oz for the same period of fiscal 2019. The current production strategy is to achieve
sustainability of production with positive cash flow to bridge the gap to start up the new life of mine; it has been
achieved by supplying leachable sulphide ore to the current oxide plant. The mining was carried out on Selinsing
Pit 5/6 and Block 7 for remaining oxide but mainly transitional leachable sulphide ore and a cutback at Selinsing
Pit 4 and Block 7 to gain access to additional oxide material. In Q4, mining activities were conducted at Selinsing
Pit IV south west cutback, Pit V/VI, Buffalo Reef Block 7 and Buffalo Reef North.
Selinsing gold production was temporarily put on hold for approximately eight weeks by the Movement Control
Order issued by the Malaysian government as a preventative measure again st the Covid-19 pandemic.
Production has resumed gradually through remaining fiscal year 2020 since mid-May. The workforce had gone
through a long medical screening process; the milling started using the secondary mill first; and mining did not
resume until June 12th due to the delayed issuance of the blasting permit which badly affected production.
Mining of free dig oxide ore was initiated at Buffalo Reef North to help make up the shortfall.
Construction to raise the tailing storage faci lity (“TSF”) was completed in September 2019 to an elevation of
Page 2 of 4
533.3 mRL to increase TSF capacity for fiscal 2020 production. TSF construction activities to 535.5m RL resumed
in mid-May 2020 to meet 2021 production requirements. TSF construction work is continuing and is expected to
be completed by early September 2020.
Sulphide Gold Project Optimization
At the Selinsing Gold Mine a positive Feasibility Study (FS) was completed by Snowden in January 2019 which
includes the Selinsing deposit, and the adjacent Felda Block 7 and Buffalo Reef deposits. The FS establishes the
economic viability of the project for a six year life of mine through the extension of the existing oxide plant by
adding a flotation and BIOX® plant to process refractory sulphide ore materials. The Company continues to focus
on obtaining financing alternatives for the extension, which is expected to place the Selinsing Sulphide Project
into production within 18 months from the commencement of construction.
In May 2020, the preparation of the next five years’ operation projection was undertaken to deliver a production
schedule based on the Resources and Reserves reconciliation. Its aim is to maximize the economic return at an
operation level according to the FS and changes in gold price level. Under which, the leachable sulphide materials
will be continued to feed into the curren t oxide treatment plant, while non-leachable sulphides will be fed into
the sulphide treatment plant once converted. The operating plan is to facilitate the timing of financing.
The engagement of a single major equipment supplier was under consideration, with options for process
guarantees, increased automation and control expected to improve recovery and reduce operating costs.
The consideration includes, but is not limited to, reduction of the completion time for long lead items such as
stainless steel for BIOX® based applications, the provision of HV power supply, BIOX® agitators, flota tion cells
and thickeners; the refinement of sulphide gold project plan to reach maximum feasible return; improvements
to the layout to make better use of the local topography, to shrink the overall plant footprint and to reduce the
capital cost by reducing structural steel requirements and shortening the length of pipe and cable racks.
R&D Work
Bioleach Batch Amenability Tests (BAT) was carried out to investigate the response of Buffalo Reef and Selinsing
flotation concentrate to the adapted locally sourced bacteria inoculum. Training of the laboratory technicians
continued in the site bioleaching laboratory to monitor the condition, adjusting the parameters and checking the
progress of the BAT test s. BAT test s carried out on Buffalo Reef flotation concentrate s achieved sulphide
oxidations between 97 - 99% and gold leachability of 94% on the bioleach residues. Sulphide oxidation of 97%
was reported from a BAT test on a composite flotation concentrate of Buffalo Reef , Felda Block 7 and Selinsing
ore; gold leachability was 91%. The test resul ts supported the previous BIOX® test work conducted for the
feasibility study.
In order to feed leachable sulphide materials to the current oxide treatment plant, Sulphide Leachability Testwork
is being performed including 2019 metallurgical drilling at the Selinsing and Buffalo Reef pits for investigating the
leachability of transitional sulphide ore through the current CIL circuit by adding lead nitrate and blending with
super low-grade ore (Au at 0.35-0.50 g/t grade range).
The majority of samples showed good leachability with a gold recovery above 70% at Selinsing Pit 5. Testwork
was also conducted on a sample of stockpiled Selinsing Pit 4 sulphide ore, previously rejected due to low
leachability using direct CIL bottle rolled test. The sample was tested using gravity separation and followed by a
CIL bottle roll test. Gravity concentration using a Knelson concentrator gave a recovery of 39% and CIL test work
on the gravity tailings recovered a further 38% for an overall 77% recovery; adding lead nit rate to the leach
improved the CIL recovery to 47% and overall recovery to 85% . Transitional sulphide ore from Buffalo Reef pits
however, did not respond well to gravity separation followed by CIL test even after the addition of lead nitrate.
Testwork has been carried out on third party gold concentrate materials. The intent is to open up the upside for
gold production at Selinsing Gold Mine through both oxide and sulphide plants. Certain high grade concentrate
Page 3 of 4
samples were tested in the laboratory by conventional gravity and CIL methods. Gravity recovery was 47% and
CIL recovered a further 29% for a total recovery of 76%. Batch trial processing is intended to be performed for
100 tonnes of concentrates fed through the Selinsing processing plant. Other samples are also under review.
Peranggih Trial Mining
At Peranggih, a new oxide exploration target 14 km north of the Selinsing Gold Mine, trial mining was carried out
from February 22 to March 3, 2020, under which the bulk sample was extracted from the higher mineralized
area (please refer to Monument’s News Release on April 20, 2020) . The bulk sample material was fed into the
existing Selinsing oxide gold processing plant to confirm the average grade of the close -spaced drilled area, to
quantify the presence of coarse gold and to test the metallurgical performance at plant scale. The trial mining
generated a positive cash flow (News Release, April 20, 2020) . After the successful trial mi ning program at
Peranggih, the Operational Mining Scheme report (“OMS”) was amended to include Peranggih mining activities,
and upon approval by the Department of Mineral and Geosciences the mining activities at Peranggih will be
permitted under the Mineral Development Act 2004 and State Mineral Enactment 2001.
Additional grade control drilling was carried out n ear-surface ore delineation at Peranggih . The initial 5,00 2m
stage 1 drilling commenced in June 2020 and was completed on July 6th 2020 to define the extensions of the
known mineralization along strike to the Northeast and Southwest of the Peranggih trial mining area. 2,493
drilling samples at 2m internals and 135 QAQC samples were assayed, the results have shown a total mineralized
material of 72,111 tons at 0.88 g/ t with 2,040 oz contained gold from the surface of Peranggih central and
southern zone down to 10m deep. The gold mineralization is associated with qua rtz breccia and tuff breccia
material in a north west trending structures. The mineralization is still open down dip and along strike.
There is currently no NI 43-101 mineral resource estimate established anywhere on the Peranggih Gold Prospect.
There is no certification as to the accuracy of the results and readers should use caution in their use and
interpretation. The mineralized materials will be extracted to feed into the mill when the grade control results
are confirmed as satisfactory.
The grade control activities are expected to continue during the next quarter and beyond.
The scientific and technical information in this press release has been prepared by Azman Taib, B.Eng. (Mineral
Resource), Metallurgist at Selinsing Gold Mine and by Adrian Woolford, B.Sc., (Hons), Chief Geologist of
Monument Mining Limited; reviewed and approved by Michael John Kitney, MAICD, MSc., MAusIMM, and Roger
Stangler, MEng, FAusIMM, MAIG, both Qualified Persons as defined by NI 43-101, retained by Golder Associates
Pty Ltd.
About Monument
Monument Mining Limited (TSX -V: MMY, FSE:D7Q1 ) is an established Canadian gold producer that owns and
operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is
advancing several exploration and development projects including the Mengapur Copper and Ir on Project, in
Pahang State of Malaysia, and the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra
in the Murchison area of Western Australia. The Company employs approximately 202 people in both regions
and is committed to the highest standards of environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEO
Monument Mining Limited
Suite 1580 -1100 Melville Street
Vancouver, BC V6E 4A6
Page 4 of 4
FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 [email protected]
"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
Forward-Looking Statement
This news release includes statements containing forward-looking information about Monument, its business and future plans (“forward-
looking statements”). Forward -looking statements are statements that involve expectations, plans, objectives or future events that are
not historical facts and include the Company’s plans with respect to its mineral projects and the timing and results of proposed programs
and events referred to in this news release. Generally, forward -looking information can be identified by the use of forward -looking
terminology such as " plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends",
"anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results
"may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward -looking statements in this news release are
subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ ma terially from those
expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to
general business, economic, competitive, geopolitical and social uncertainties; uncertainties r egarding the results of current exploration
activities; uncertainties in the progress and timing of development activities; foreign operations risks; other risks inheren t in the mining
industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company’s
projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Material factors and assumptions used
to develop forward -looking statements in this news relea se include: expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from the operations, general economic factors and other factor s that
may be beyond the control of Monument; assumpt ions and expectations regarding the results of exploration on the Company’s projects;
assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; the e xpected
timing and results of development and exploration activities; costs of future activities; capital and operating expenditures; success of
exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management
discussion and analysis of the Company and the technical reports on the Company’s projects, all of which are available under the profile
of the Company on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual
results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-
looking statements. The Company does not undertake to update any forward -looking statements, except in accordance with applicable
securities laws.