Monument Begins Gold Concentrate Shipments at Selinsing Gold Mine
P a g e 1 | 4
June 23, 2023 News Release Release #06-2023
Monument Begins Gold Concentrate Shipments at Selinsing Gold Mine
Vancouver, B.C., June 23, 2023, Monument Mining Limited (TSX -V: MMY and FSE: D7Q1) ( "Monument"
or the "Company") is pleased to announce the first gold concentrate shipments and sales from the newly
constructed flotation plant at the Selinsing Gold Mine.
President and CEO Cathy Zhai commented, "This is a momentous occasion for us as we begin to ship and
sell gold concentrates from the flotation plant. T he initial offtake of 2,000 dry metric tonnes (“DMT”) of
concentrate from Selinsing marks the beginning of a gold concentrate revenue stream and restores our
operating cash flow. We would like to give thanks to our hard -working operation teams, backroom
administration support personnel and our business partners to make this happen."
Figure 1. Loading Concentrate for Transport Figure 2. Concentrate Shipment at Weighbridge
Gold Concentrate Shipments and Sales
Significant interest has been received from potential buyers of the Selinsing gold concentrate. All export
and transport permits have been received and the first truckloads of concentrate were shipped from the
Selinsing warehouse on June 18th, 2023 to Johor Free Trade Zone. To date 490 DMT of concentrate have
been dispatched out of an initial offtake of 2,000 DMT. Weighing, sampling and moisture determination
of the delivered concentrate is being conducted at the Johor Free Trade Zone by an appointed
internationally recognized survey company.
An additional 3,000 DMT of concentrate is currently available for sale. The Company intends after a trial
shipment to gradually increase the number of trucks to speed up the logistic process in selling backlogged
product. In the future concentrates will be shipped to buyers on a routine basis. The backlog was caused
by a lengthy initial administrative process for obtaining all relevant permits and organizing logistics. Over
the last six months, the Company has built a logistic team and sales chain at the Selinsing Project.
P a g e 2 | 4
Commercial Production Update
The flotation plant operation is improving with up to 99% of design capacity achieved during June 2023,
and overall 83% capacity achieved for the 30 day period up to June 17th 2023. Torn filter cloths remained
an issue with new cloths still awaited from the filter press supplier McLanahan. New HDPE pipework was
received to upgrade the concentrate thickener underflow pipeline. A similar upgrade was planned for the
flotation cleaner concentrate pipeline which emerged as a bottleneck with increasing flotation mass pull.
Figure 3: Selinsing Flotation Plant
Flotation recovery has shown a steady improvement as increasing proportions of newly mined transition
and fresh ore were processed. Daily recoveries in excess of 80% have been recorded during June 2023,
although an average of 68% recovery month to date was caused by some poorly performing old transition
ore processed at the start of the month.
Construction of the concentrate shed continued with the main roof completed and the perimeter
concrete wall approximately 50% done. Work continued extending the lean -to roof to the filter press
building. The bagging system has been prepared for shipping to Malaysia.
Mining Update
Mining of Buffalo Reef Stage 1 BRC2 and BRC3 pits continued with both transition and fresh ore delivered
to the ROM pad and maintained around one month’s supply of ore feed to the flotation processing plant.
A new drill rig was delivered in June 2023 with nine grade control drilling rigs now operational; a tenth
unit is scheduled for delivery in August 2023. The mining operation is aiming to achieve and maintain a
three-month supply of ore at the ROM.
Construction of the explosive’s depot progressed well with delivery of the bulk emulsion gassing container
and the connection to mains power completed. This is to remove dependency on explosives delivery from
the sole dominant supplier in the country due to their shortfall of trucks over the past several months.
The isotainer storage tanks are due for delivery in late June 2023 and the explosives depot will be
commissioned in early July 2023.
Work started on the conversion of the old core shed to an expanded sample preparation facility capable
P a g e 3 | 4
of processing up to 700 grade control samples per day , which will remove another major bottleneck in
the mining cycle.
Risks
Other operation risks in related to mining and processing processes are under continuous evaluation to
improve the performance.
The Company closely monitors u ncontrollable risk factors with building and operation of the flotation
plant including but not limited to : change of market conditions, change of gold prices, operation risks
including critical parts shortages which may cause a longer than expected ramp up period, and changes in
regulatory restrictions in relation to arsenic level contained in gold concentrate.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that 100%
owns and operates the Selinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison
area of Western Australia. It has 20% interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200 people in both regions and is committed
to the highest standards of environmental management, social responsibility, and health and safety for
its employees and neighboring communities.
Cathy Zhai, President and CEO
Monument Mining Limited
Suite 1580 -1100 Melville Street
Vancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 [email protected]
"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies
of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
Disclaimer Regarding Forward-Looking Statements
This news release includes statements containing forward -looking information about Monument, its business and future plans
("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future
events that are not historical facts and include the Company's plans with respect to its mineral projects, expectations regar ding
the completion of the ramp -up period to target production level at Selinsing and the timing thereof, expectations regarding the
Company’s continuing ability to source explosives from suppliers, expectations regarding completion of the proposed storage shed
and ammonium nitrate depot and the timi ng thereof, and the timing and results of the other proposed programs and events
referred to in this news release. Generally, forward -looking information can be identified by the use of forward -looking
terminology such as "plans", "expects" or "does not e xpect", "is expected", "budget", "scheduled", "estimates", "forecasts",
"intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certa in
actions, events or results "may", "could", "would", "mig ht" or "will be taken", "occur" or "be achieved". The forward -looking
statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or
achievements to differ materially from those expressed or implied by the forward -looking statements. These risks and certain
other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social
uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of
development activities, including those related to the ramp -up process at Selinsing and the completion of the proposed storage
shed and ammonium nitrate depot; uncertainties and risks rela ted to the Company’s ability to source explosives from suppliers;
foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and
P a g e 4 | 4
analysis of the Company and the technical reports on the Comp any's projects, all of which are available under the profile of the
Company on SEDAR at www.sedar.com. Material factors and assumptions used to develop forward -looking statements in this
news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows
which may be generated from the operations, general economic factors and other factors that may be beyond the control of
Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding
the future price of gold of other minerals; the timing and amount of estimated future production; assumptions regarding the
timing and results of development activities, including the ramp -up process at Sel insing and the completion of the proposed
storage shed and ammonium nitrate depot; expectations that the Company will continue to be able to source explosives from
suppliers in a timely manner; costs of future activities; capital and operating expenditures; success of exploration activities; mining
or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis
of the Company and the technical reports on the Company's projects, all of which ar e available under the profile of the Company
on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results
to differ materially from those contained in forward -looking statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. The Company does not undertake to update any forward -looking statements, except in
accordance with applicable securities laws.