Monument Announces Update at the Selinsing Gold Mine in Malaysia

Corporate Updates

P a g e 1 | 4

January 18, 2024 News Release Release #01-2024

Monument Announces Update at the Selinsing Gold Mine in Malaysia

Vancouver, B.C., January 18, 2024, Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument"

or the "Company") is pleased to announce an update at Selinsing Gold Mine where the Company recently

achieved commercial production of its newly constructed flotation processing plant.

President and CEO Cathy Zhai commented, "We are very pleased with the continued progress and

optimization of the Selinsing Sulphide gold flotat ion plant. The production is expected to be stabilized in

the 2024 calendar year and cash flow sustained. Longer term off take contracts are in progress. Export

permits continue to be renewed every six months with government support. Gold prices are above the

$2,000 per ounce level in the new year which is in our favor.”

Ms. Zhai emphasizes: “In 2024 we will provide further training to our senior management with a value-

added approach to lead to excellent performance. Our corporate focus in 2024 is business development

in Malaysia, Western Australia and elsewhere . W e are positioning Monument to be a fully funded

producing company with upside growth potential to realize shareholder value in the marketplace.”

Figure 1: Selinsing Flotation Plant

At the opening of th is new year, the production objective of Selinsing Gold Mine is to streamline and

optimize the flotation plant and operations to achieve the best financial performance. The Company

continues to improve operational efficiencies through consolidating Selinsing operating activities and

resources, and removal of bottlenecks including: plant performance improvements, mining cycle

harmonization, tailing storage facilities (TSF) upgrade, refining the gold concentrate warehousing,

shipping and sales process, and security enhancements.

P a g e 2 | 4

Plant Process Improvements

The flotation plant achieved the design capacity of

119 tph in early December 2023, however mill feed

rate continues to be hampered by the bottleneck at

the McLanahan filter press . Recent improvements

to the filter press operation have included the

installation of pressure regulators to reduce the

compressed air pressure for the core blow and cake

dry cycles; the pressure reduction has certainly

reduced the frequency of filter cloth failure. Torn

filter cloths have been replaced as required by local

and internationally sourced cloths. Worn filter

plates are being repaired locally and new units have

been ordered from the manufacturer and are

expected to arrive at site in March 2024.

Ongoing plant improvements included an upgrade

to the concentrate thickener underflow pipeline to

the filter press surge tank. One of the concentrate

thickener overflow pumps was replaced with a

bigger pump along with a new pipeline; a standby

pump will be installed once refurbishment work is

completed. Modifications to the cleaner flotation

circuit were initiated to allow cleaning of the first

rougher co ncentrate to produce a cleaner final

concentrate during processing of transition ore

types.

Figure 2. Flotation Control Cabin

Figure 3. Atomic Absorption Spectrometer at

Assay Laboratory

Flotation recovery continued to be variable due to the inconsistent quality of the transition ores

processed. New flocculant was received for the water recovery thickener, allowing the flotation circuit to

operate at the design pH 9.0-9.5. Dosing of the sulphidising agent sodium sulphide continued along with

copper sulphate as activator. Some daily recoveries of over 80% and sometimes 90% were recorded, with

reconciled recovery of 73.6% reported for December 2023.

Construction of the concentrate shed has been completed and t he lighting power suppl y connected.

Roofing was installed over the rougher and cleaner flotation cells. The one tonne bulk bagging system was

delivered to Port Klang and transported to the Selinsing site. The contract for the new flotation tailings

hopper was awarded and fabrication initiated; civil works commenced in mid-December 2023 and

installation of the tailings hopper and associated pipework is scheduled in the 1st week of February 2024.

The procurement plan and strategies have been tabled for review focusing on critical spare parts for the

sulphide flotation plant and by allocating resources to enhance this improvement with the aim to avoid

any unforeseen stoppage of plant operations.

Mining and Ore Stockpile Buildup

Mining of Buffalo Reef pits continued with Stages 1 and 2 mined at BRC2 and BRC3 pits and Stage 1 started

at BRC4. Delivery of fresh and transition ore continued and the run of mine (ROM) stockpile was increased

to 255,000 tonnes, which is over three months’ processing plant capacity, at the end of December 2023

P a g e 3 | 4

and critically ahead of the imminent Northeast monsoon season.

A new three-year mining contract was negotiated with the long-term mining contractor Minetech, starting

January 1st, 2024 . Ten grade control drilling rigs are currently operational and performing well ; the

Minetech fleet of eight excavators and around forty dump trucks have shown good availability.

To smooth mining cycle, capacity of the preparation lab has been reviewed and improved with two new

pulverisers installed at the new sample preparation laboratory. The ventilation system has been installed

and is under commissioning to improve the working environment and avoid contamination.

Routine deliveries of ammonium nitrate emulsion to the Austin Powders explosives depot continued. The

site-based 13 tonne capacity emulsion tanker was replaced by a 16-tonne capacity unit and blasting was

carried out on up to five days per week as required.

Construction of the TSF upgrade resumed in August 2023. Zone A and Zone C fill to 540 mRL was

completed at the main embankment and the upstream slope was lined with riprap to protect against

erosion. Construction of the TSF south embankments was completed and riprap placed on the upstream

slopes. The new spillway will be constructed in January 2024 followed by the installation of the seepage

sumps and related pipework at the toe of the main embankment. The overall TSF upgrade is expected to

be completed by February 2024.

Gold Concentrate Shipments and Sales

To date the flotation plant has produced over 16,000 tonnes of concentrates at a grade of 37 g/t Au.

Shipments have been made to three separate buyers and negotiations continue with several potential

new customers. To date over 12,500 tonnes of concentrate have been delivered to Johor a nd Port Klang

Free Zones. Export permits have been renewed with the relevant state authorities as required. Transport

of the latest delivery of 3,500 wet metric tonnes to Port Klang Free Zone has been completed with vessel

to depart in mid-January 2024. Sale of a further 3,000 tonnes of concentrate currently available has been

finalized and shipment preparation of the concentrate to the port is in progress.

Warehouse review and improvements are ongoing including tightened up of security features.

Stock Compensation

To reward the success of placing the Sulphide Gold Project into commercial production, the Company also

announces that the board has granted under its equity compensation plans a total 3.4 million restricted

share units and 3.8 million incentive stock options to its directors, officers and employees . Each stock

option is exercisable at a price of $0.145 for a term of five years from the date of grant with a three years

vesting period.

About Monument

Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that 100%

owns and operates the Selinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison

area of Western Australia. It has 20% interest in Tuckanarra Gold Project jointly owned with Odyssey Gold

Ltd in the same region. The Company employs approximately 250 people in both regions and is committed

to the highest standards of environmental management, social responsibility, and health and safety for

its employees and neighboring communities.

Cathy Zhai, President and CEO

Monument Mining Limited

Suite 1580 -1100 Melville Street

P a g e 4 | 4

Vancouver, BC V6E 4A6

FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:

Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 [email protected]

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

Disclaimer Regarding Forward-Looking Statements

This news release includes statements containing forward -looking information about Monument, its business and future plans

("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future

events that are not historical facts and include the Company's plans with respect to its mineral projects, expectations regarding

the completion of the ramp -up period to target production level at Selinsing and the timing thereof, expectations regarding the

Company’s continuing ability to source explosives from suppliers, expectations regarding completion of the proposed storage shed

and ammonium nitrate depot and the timing thereof, and the timing and results of the other proposed programs and events

referred to in this news release. Generally, forward -looking information can be identified by the use of forward -looking

terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts",

"intends", "antici pates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain

actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward -looking

statements in this n ews release are subject to various risks, uncertainties and other factors that could cause actual results or

achievements to differ materially from those expressed or implied by the forward -looking statements. These risks and certain

other factors include , without limitation: risks related to general business, economic, competitive, geopolitical and social

uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timin g of

development activities, including those related to the ramp -up process at Selinsing and the completion of the proposed storage

shed and ammonium nitrate depot; uncertainties and risks related to the Company’s ability to source explosives from suppliers ;

foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and

analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the

Company on SEDAR at ww w.sedar.com. Material factors and assumptions used to develop forward -looking statements in this

news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows

which may be generated from th e operations, general economic factors and other factors that may be beyond the control of

Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding

the future price of gold of other minera ls; the timing and amount of estimated future production; assumptions regarding the

timing and results of development activities, including the ramp -up process at Selinsing and the completion of the proposed

storage shed and ammonium nitrate depot; expecta tions that the Company will continue to be able to source explosives from

suppliers in a timely manner; costs of future activities; capital and operating expenditures; success of exploration activities; mining

or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis

of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Compa ny

on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results

to differ materially from those contained in forward -looking statements, there may be other factors that cause results not to be

as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results

and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue

reliance on forward-looking statements. The Company does not undertake to update any forward -looking statements, except in

accordance with applicable securities laws.