Monument Announces Progress of the Burnakura Gold Project

Corporate Updates

November 08, 2018 News Release Release #20 2018

Monument Announces Progress of the Burnakura Gold Project

Vancouver, B.C. Monument Mining Limited (TSX -V: MMY and FSE: D7Q1) ("Monument" or the "Company") is pleased

to announce progress of the Burnakura Gold Project at Murchison in Western Australia. Along with completion of a recent

NI43-101 Mineral Resource up date, further work has been carried out under the Preliminary Economic Assessment Study

(“PEA”), which includes underground mining opportunities.

President and CEO Cathy Zhai comments, "After updating the mineral resource estimation at Burnakura Gold Proj ect under

the NI43-101 Technical Report in July 2018, we have completed an initial economic assessment under the PEA study with an

increase of mill capacity to 500ktpa from 260ktpa. Based on those assessments, we have re -strategized development of the

Burnakura Gold Project. The planned gold production is postponed until completion of the PEA to include underground

mining opportunities that would potentially allow for a better return to shareholders.”

Ms. Zhai further commented: “Our past successful drill programs have produced significant results with positive geological

implications and provided us much more understanding of the control structure. It is now critical to engage a disciplined,

effective and efficient exploration strategy to test our unders tanding of the regional geological targets for new discoveries

while adding gold inventory to the existing defined deposits. The strategy will provide an economic scale of the project

potential and allow us to hopefully move towards to placing Burnakura into production with a lower risk profile.”

Updated Resources and PEA Study

At Burnakura, in July 2018, SRK Consulting (Australasia) Pty Ltd (“SRK”) completed the “NI 43 -101 Technical Report:

Updated Mineral Resources, Burnakura Gold Project, Western Australia.” A total of 293koz Indicated Gold Mineral

Resources at 2.3 g/t Au for 4,043kt and 88koz of Inferred Gold Mineral Resources at 1.8 g/t Au for 1,551kt was reported and

has tripled from the previous reported resource estimates in 2015.

The PEA program is designed to identify the economic potential in a large scale at Burnakura, Tuckanarra and Gabanintha

(together the “Murchison Gold Projects”) including open pits and underground mining opportunities. The NOA 7/8 resource

estimates form a significant part of the Indicated Resources at Burnakura, resulting in an initial internal economic assessment

being carried out in June and completed in October on the underground mining potential with a corresponding increase in the

existing mill capacity to 500ktpa from 260ktpa , based on which staged mining alternatives have been evaluated a s a part of

the PEA study. The metallurgical drill samples were assayed, a further diagnostic leaching testwork has also been carried out

on NOA7/8 core samples.

The ongoing PEA study is preliminary in nature, including inferred mineral resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be categorized as mineral

reserves, and there is no certainty that the PEA will be realized.

Regional and Local Exploration

The recent deep drilling program at Burnakura has positive geological implications, showing mineralization is continuous at

depth at ANA and extended approximately 130m down plunge at NOA7/8. A geological structural study was completed with

updates reflecting new g eological information to interpret regional geology. Regional and localized drill targets have been

identified and ranked with priority at Burnakura and entire Murchison Gold Project.

The Company is in review of geological information, exploration milesto nes and strategy, preparing to commence the

exploration programs in the New Year to test the geological interpretation through deep drilling programs for plausible

underground extension and /or repetition targets at ANA, NOA 1 and NOA 2, and NOA 7/8 areas, and a new regional target

at NOA 9.

Structural Geology Study

Several highly prospective exploration targets based on structural mapping have been developed by International Geoscience

Structural Geology expert, Dr Warwick Crowe, presented in the Figure below:

Among those targets, NOA 9 (see figure below) was identified through regional aeromagnetic interpretation. NOA 9 is located

in an area of alluvial cover at the extreme north end of the Burnakura project area. A prospective NNW trending structure has

been mapped which is known to control the mineralization. The target is under transported cover.

Although conceptual in nature, it is recommended that this target be tested as high -priority because it has the potential

opportunity to rapidly and materially transform the economics of the Murchison Project. It should be possible to test this with

a few lines of aircore drilling (or if required by ground conditions, RC drilling).

The scientific and technical information in this press release has been prepared by Mark Lynch -Staunton, MCSM, MAIG,

M.Sc Mining Geology; and supervised and approved by Roger Stangler, MEng, MAusIMM, MAIG, a Qualified Person as

defined by NI43-101, both retained by Monument Mining Limited.

About Monument

Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that owns and

operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is

advancing several exploration and development projects including the Mengapur Copper-Iron Project, in Pahang

State of Malaysia, and the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra in the

Murchison area of Western Australia. The Company employs approximately 19 5 people in both regions and is

committed to the highest standards of environmental management, social responsibility, and health and safety for

its employees and neighboring communities.

Cathy Zhai, President and CEO

Monument Mining Limited

Suite 1580 -1100 Melville Street

Vancouver, BC V6E 4A6

FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:

Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 [email protected]

Wolfgang Seybold, Axino GmbH T: +49 711-82 09 7211 [email protected]

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release."

Forward-Looking Statement

This news release includes statements containing forward -looking information about Monument, its business and future plans (“forward-

looking statements”). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not

historical facts and include the Company’s plans with respect to its mineral projects and the timing and results of proposed programs and

events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology

such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled ", "estimates", "forecasts", "intends", "anticipates" or

"does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could",

"would", "might" or "will be taken", "occur" or "be achi eved". The forward-looking statements in this news release are subject to various

risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expres sed or implied

by the forward -looking statements. These risks and certain other factors include, without limitation: risks related to general business,

economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration acti vities;

uncertainties in the progress and timing of development activities; foreign operations risks; other risks inherent in the mining industry and

other risks described in the management discussion and analysis of the Company and the technical reports on the Company’s projects, all

of which are available under the profile of the Company on SEDAR at www.sedar.com. Material factors and assumptions used to develop

forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and

the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be b eyond the

control of Monument; assumptions and expectations regarding the results of exploration on the Company’s projects; assumptions regarding

the future price of gold of other minerals; the timing and amount of estimated future production; the expected timing and res ults of

development and exploration activities; costs of future activities; capital and operating expenditures; success of exploration activities;

mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis

of the Company and the technical reports on the Company’s projects, all of which are available under the profile of the Company on SEDAR

at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results to differ materially

from those contained in forward -looking statements, t here may be other factors that cause results not to be as anticipated, estimated or

intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially

from those anticipated in su ch statements. Accordingly, readers should not place undue reliance on forward -looking statements. The

Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.