Mako Mining Provides Q2 2022 Production Results
LEGAL*56510516.1
1
595 Burrard Street, Suite 2833
Vancouver, BC V7X 1K8
Tel: (604) 646-1580
www.makominingcorp.com
TSX-V: MKO | OTCQX: MAKOF
Suite 700 - 838 West Hastings St.
Vancouver, BC - V6C 0A6
IR: (647) 203-8793
www.makominingcorp.com
TSX-V: MKO | OTCQX: MAKOF
July 20th, 2022
TSX-V: MKO; OTCQX: MAKOF
Mako Mining Provides Q2 2022 Production Results
Mako Mining Corp. (TSX-V: MKO; OTCQX: MAKOF) (“Mako” or the “ Company”) is pleased to provide
second quarter 2022 (“Q2 2022”) production results from its San Albino gold mine (“San Albino ”) in
northern Nicaragua , which is the fourth full quarter of production results since declaring commercial
production on July 1st, 2021. Financial results for Q2 2022, including detailed reporting of our operating
costs, are expected to be released in August.
Q2 2022 Production Highlights
• 47,220 tonnes mined containing 11,421 ounces of gold (“oz Au”) at a blended grade of 7.52
grams per tonne gold (“g/t Au”)
o 22,560 tonnes mined containing 9,324 oz Au from diluted vein material at 12.85 g/t Au
o 24,660 tonnes mined contain ing 2,097 oz Au from historical dump and other mineralized
material above cutoff grade (“historical dump + other”) at 2.65 g/t Au
o 7.0:1 strip ratio for Phase 1
o 26.5:1 strip ratio overall which includes accelerated waste development of the West and the
Central Pit (“Arras Zone”)
• 49,332 tonnes milled containing 11,576 oz Au at a blended grade of 7.30 g/t Au
o 47% and 53% from diluted vein and hanging-wall/footwall, respectively
o 589 tonnes per day (“tpd”) milled at 92% availability
o 74.5% gold recoveries (majority of material processed was fresh material)
• 139,401 tonnes in stockpile containing 13,385 oz Au at a blended grade of 2.99 g/t Au
• 8,630 oz Au recovered and 9,027 oz Au sold at an average realized price of US$ 1,866 per
ounce
Akiba Leisman, Chief Executive Officer of Mako states that, “ this quarter was the fourth full quarter of
commercial production at San Albino . The mine is performing well, where the diluted vein material
continues to positively reconcile to the resource model, and mill throughput has been running at above
nameplate capacity of 500 tonnes per day, including all availability factors . The mill averaged 589 tonnes
per day for the quarter at 92% availability, 8% above nameplate capacity . Replenishment of spare parts
and minor adjustments to the plant since the beginning of the year improved mill availability throughout the
first half of 2022, and we expect to be running at or above nameplate capacity for the foreseeable future .
Recoveries have been below the 86% metallurgical recoveries predicted in our December 2019
metallurgical update (see press release dated December 13, 2019), due to organic carbon present in the
hanging-wall and footwall of the vein. The plant is going through a series of optimizations to eliminate free
cyanide concentrations in the recycled water , which will continue throughout Q3 2022. Additionally, we
LEGAL*56510516.1
2
have implemented robust sampling mechanisms, and mining and stockpiling processes aimed at ensuring
that particularly problematic material is kept away from the mill. Fortunately, the high grade vein material
is not as problematic as the hanging -wall and footwall mater ial, and to the extent possible we will be
processing the diluted vein separately during the quarter with the plant optimized specifically for the high
grade material. With all of these changes, we are optimistic that improvements in recoveries can be made
later this year . A total of 9,027 ounc es were sold in the quarter ( 9,580 ounces sold in Q1 2022), and
operating cash flow from the mine remains robust, with exploration expenditures increasing, preparations
for rainy season complete, an aggregate of US$10.3 million of principal being repaid under the Company’s
loan facility with Wexford and Sailfish Royalty Corp. since the beginning of Q3 2021, and 2 million common
shares repurchased through our normal course issuer bid.”
Table 1 – Production Results
* Includes historical dump, hanging-wall, footwall, historical muck and all other non-vein mineralized material above cutoff grade
**For the purpose of calculating revenue, payments to Sailfish are deducted from the Average Realized Price
Units Q3 2021 Q4 2021 Q1 2022 Q2 2022
Mined
Diluted Vein
Tonnes t 14,329 17,500 17,400 22,560
Gold Grade g/t 15.80 16.94 15.59 12.85
Contained Gold oz 7,278 9,530 8,723 9,324
Historical Dump + Other*
Tonnes t 36,881 26,660 32,380 24,660
Gold Grade g/t 2.72 3.17 2.74 2.65
Contained Gold oz 3,220 2,720 2,854 2,097
Waste
Tonnes t 794,791 776,539 1,516,510 1,249,926
Strip Ratio Phase 1 15.5 17.6 17.9 7.1
Strip Ratio Total N.A N.A 30.5 26.5
Milled
Diluted Vein % 56% 51% 48% 47%
Historical Dump + Other* % 44% 49% 52% 53%
Tonnes t 33,441 38,313 46,869 49,332
Gold Grade g/t 8.25 9.01 7.20 7.30
Contained Gold oz 8,873 11,102 10,843 11,576
Mill Availability % 85% 82% 87% 92%
Average Tonnes per Day t/day 429 507 596 589
Recovered
Recoveries % 92.9% 92.7% 85.6% 74.5%
Gold Recovered oz 8,239 10,291 9,280 8,630
Gold Sold oz 8,280 9,588 9,580 9,027
Average Realized Price** US$/oz 1,783 1,797 1,870 1,866
w:o
LEGAL*56510516.1
3
Table 2 – Mining by phases Q2 2022
Table 3 – Quarter End Stockpile Statistics
* Includes stockpiles of mineralized material at the crusher.
** Includes historical dump, hangingwall, footwall, historical muck and all other non-vein mineralized material above cutoff grade.
Mining
The mine averaged 519 tpd of diluted vein material a nd historical dump + other in Q2 2022 with a strip
ratio of 26.5 in total from the West Pit and Arras Zone that includes accelerated waste stripping in
preparation for the rainy season (see Table 2). The current stockpile is 139,401 tonnes with 4,061 tonnes
of higher grade diluted vein mineralization with a grade of 11.81 g/t Au and 135,340 tonnes at 2.72 g/t Au
of historical dump + other for a total contained gold of 13,385 oz (mineral grade of 2.99 g/t Au).
The higher-grade material for the quarter came from the West Pit with an average grade of 8.02 g/t Au. As
we are now deeper in the deposit we are mining mostly fresh material . The detailed grade control
processes and procedures have been very effe ctive in controlling mining dilution with a range as low as
30 cm on either side of the vein. Along with geological mapping and assays, additional lab testing has
Units West Pit
Phase 1
West Pit
Phase 2
West Pit
Phase 3
Arras
Zone Total
Ore Tonnes t 37,180 3,460 920 5,660 47,220
Au Grade g/t 8.41 5.11 3.07 3.87 7.52
Au Ounces oz 10,057 568 91 705 11,421
Waste Tonnes t 264,028 436,273 215,216 334,409 1,249,926
Strip Ratio w:t 7.1x 126.1x 233.9x 59.1x 26.5x
Units Q3 2021 Q4 2021 Q1 2022 Q2 2022
Diluted Vein*
Tonnes t 3,545 6,510 2,959 4,061
Gold Grade g/t 11.86 13.62 7.95 11.81
Contained Gold oz 1,352 2,850 756 1,543
Historical Dump + Other**
Tonnes t 125,486 132,092 145,091 135,340
Gold Grade g/t 2.38 2.35 2.25 2.72
Contained Gold oz 9,608 9,982 10,513 11,842
Total
Tonnes t 129,031 138,602 148,050 139,401
Gold Grade g/t 2.64 2.88 2.37 2.99
Contained Gold oz 10,960 12,832 11,269 13,385
LEGAL*56510516.1
4
been implemented to identify increased organic content of the more difficult to process mater ial, typically
found in the footwall and hanging -wall rather than the high -grade vein itself. These improvements have
increased the ability to selectively mine, separate, and stockpile according to grade and metallurgical
characteristics while maintaining low dilution.
There were no additional night shifts to increase production during Q2. The rainy season started in mid-
May and, as anticipated, production was delayed due to weather with a decline in June tonnage of
approximately 22%. Although year-to-date production remains 1.6% over forecast, a limited extra shift of
one excavator and seven trucks will start in July in an effort to ensure waste stripping stays on schedule.
Milling
All components of the 500 tpd gravity and carbon -in-leach processing plant have been fully operational
since the beginning of May 2021. During Q2, 2022, the plant has been averaging 589 tpd at 92% availability
(see Table 1). In Q2 2022 the plant processed 47% diluted vein material and 53% historical dump + other
to achieve an average blended grade of 7.30 g/t Au and recovering an average of 74.5% (see Table 1).
The first two quarters of 2022 saw the mill operate at a throughput rate significantly higher than previous
quarters. This was primarily due to improved equipment performance. The gold recovery was lower than
previous quarters due to the much higher quantity of fresh material in the mill feed.
The fresh material contains naturally occurring carbo n which can interfere with the gold recovery
process. Eliminating free cyanide in the grinding circuit and only adding cyanide to the slurry in the CIL is
essential in order to achieve optimal recoveries. Reducing cyanide concentrations from recycled water to
optimal levels required a change in reagents. We were previously using the standard INCO/SO2 process
(sodium metabisulfite and copper sulfate) but the results weren`t consistent and reliable. To adjust, we are
now detoxing with sodium hypochlorite (com mon bleach), but the logistics needed to obtain necessary
quantities took some time to develop. Further mill optimization efforts to lower cyanide concentrations in
the mill grinding circuit are planned in the months ahead to more effectively treat the increased quantity of
fresh material feeding the mill.
In the meantime, we have developed robust sampling mechanisms and mining and stockpiling processes
aimed at ensuring particularly problematic material is kept away from the mill. The high grade vein material
does not exhibit as strong pre-robbing tendencies as the material from the hanging-wall and footwall, and
to the extent possible we will be processing that material separately during the quarter with the plant
optimized specifically for the high grade material.
In addition, a second carbon stripping vessel is scheduled for installation in the third quarter of 2022 which
will further debottleneck the carbon stripping circuit.
All of the above mentioned improvements to the processing plant have helped the plant achieve processing
rates of an average of 589 tpd in Q2 2022, with over 9,000 ounces of gold sold for the third consecutive
quarter (see Table 1).
LEGAL*56510516.1
5
Qualified Person
John Rust, a metallurgical engineer and qualified person (as defined under NI 43-101) has read and
approved the technical information contained in this press release. Mr. Rust is a senior metallurgist and a
consultant to the Company.
On behalf of the Board,
Akiba Leisman
Chief Executive Officer
About Mako
Mako Mining Corp. is a publicly listed gold mining, development and exploration company. The Company
operates the high -grade San Albino gold mine in Nueva Segovia, Nicaragua, which ranks as one of the
highest-grade open pit gold mines globally. Mako’s primary objective is to operate San Albino profitably
and fund exploration of prospective targets on its district-scale land package.
For further information: Mako Mining Corp., Akiba Leisman, Chief Executive Officer, Telephone: 203-862-
7059, E -mail: [email protected] or visit our website at www.makominingcorp.com and
SEDAR www.sedar.com.
Forward-Looking Information: Statements contained herein, other than historical fact, may be considered “forward-
looking information” within the meaning of applicable securities laws. The forward -looking information contained
herein is based on the Company’s plans and certain expectations and assumptions, including that Q2, 2022 detailed
operating costs and financial results will be available in August 2022; that the replenishment of spare parts and minor
adjustments to the plant are expected to further improve mill availability for the first quarter of 2022 and beyond; that
we expect to be running at or above nameplate capacity for the foreseeable future , and that we are optimistic that
improvements in recoveries can be made thereafter ; now that the gravity circuit is operating continuously it is
expected to improve recoveries and reduce processing costs of the high-grade mineralization; the additional carbon
stripping vessel is expected to increase stripping capacity in the elution circuit and be operational in Q 3 2022; ;and
that the Company can operate San Albino profitably in order to fund exploration of prospective targets on its district-
scale land package. Such forward -looking information is subject to a variety of risks and uncertainties which could
cause actual events or results to diffe r materially from those reflected in the forward -looking information, including,
without limitation, the risk that the expected improvements noted will not be completed in the timeframes expected
and/or will lead to the improvements expected; that the Company is not successful in operating San Albino profitably
and/or funding its exploration of prospectus targets on its district-scale land package; political risks and uncertainties
involving the Company’s exploration properties; the inherent uncertainty of cost estimates and the potential for
unexpected costs and expense; commodity price fluctuations and other risks and uncertainties as disclosed in the
Company’s public disclosure filings on SEDAR at www.sedar.com. Such information contained herein repre sents
management’s best judgment as of the date hereof, based on information currently available and is included for the
purposes of providing investors with the Company’s expectations regarding the Company’s Q2 2022 production
results at San Albino gold p roject, and may not be appropriate for other purposes. Mako does not undertake to
update any forward-looking information, except in accordance with applicable securities laws.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.